HomeMy WebLinkAboutRFP - 8123 CURED-IN-PLACE PIPE FOR SANITARY SEWERS STORMWATER MAINS REHABILITATION (2)Addendum 2 – 8123 Cured-in-Place Sanitary Sewers/Stormwater Mains Rehabilitation Page 1 of 3
ADDENDUM NO. 2
SPECIFICATIONS AND CONTRACT DOCUMENTS
Description of RFP 8123: Cured-in-Place Sanitary Sewers/Stormwater Mains Rehabilitation
OPENING DATE: 3:00 PM (Our Clock) June 1, 2015
To all prospective bidders under the specifications and contract documents described above,
the following changes/additions are hereby made and detailed in the following sections of this
addendum:
1. Additional Information
Exhibit 1 – Questions & Answers
Please contact Pat Johnson, CPPB, Senior Buyer at (970) 221-6777 with any questions
regarding this addendum.
RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED BY A WRITTEN STATEMENT
ENCLOSED WITH THE BID/QUOTE STATING THAT THIS ADDENDUM HAS BEEN
RECEIVED.
Financial Services
Purchasing Division
215 N. Mason St. 2nd Floor
PO Box 580
Fort Collins, CO 80522
970.221.6775
970.221.6707
fcgov.com/purchasing
Addendum 2 – 8123 Cured-in-Place Sanitary Sewers/Stormwater Mains Rehabilitation Page 2 of 3
EXHBIT 1 – QUESTIONS & ANSWERS
Q1. Do you have maps and flow data for the line segments in RFP 8123? This will be critical to
determine the pricing.
A.1 Stormwater – Maps are available with descriptions of the issues. Stormwater
does not have flow data for these lines, and typically only carry water when it’s
raining or landscape irrigation water is flowing.
A.1 Wastewater – Maps are available. Contractors will need to sign a release form
prior to the City releasing the maps to them. Email Pat Johnson at
pjohnson@fcgov.com, providing an email address of where to send the release
form.
For purposes of bidding, assume the line(s) are at full capacity. After a contract is
awarded, the City will negotiate with the awarded contractor based on actual flow
rates. The negotiation will take place with the awarded contractor this year and
on an annual basis as we prepare for the upcoming season’s work.
Q2. I am wanting to put together numbers for the bypass portion of this project and I was
wondering who I could get in contact with to provide me with the following:
1. Max peak flow of the system
2. Distance of the bypass
A2.1. Wastewater – Peak flows Mulberry WRF 6MGD; Drake WRF 23 MGD.
A2.2 The distance of the bypass is based on the length of the line segment.
Q3. In years past, the RFP did not include pricing and was an unidentified scope. It seems
there is a definitive scope at least for the first year. Can COFC provide maps and
locations to the scope of work as well as flows for the diameters above 12 “? It is difficult to
price at the quantities stated without the above information.
A3. For purposes of bidding, assume the line(s) are at full capacity. After a contract is
awarded, the City will negotiate with the awarded contractor based on actual flow
rates. The negotiation will take place with the awarded contractor this year and
on an annual basis as we prepare for the upcoming season’s work.
Q4. Is it acceptable to reference our Five Year Project List for this section which will be an
attachment, as it includes the information being requested for 3.g?
A4. Yes, it is acceptable to reference the 5 year project list.
Q5. We have a number of attachments (resume’s, safety records, etc.) that in our
interpretation of the proposal requirements should be included. While the proposal itself
will be under the 25-page limit, the attachments comprise that much (including divider
pages, sustainability section, etc.).
A5. Resumes and safety records should be included in the proposal’s 25 page limit.
The Financial documents do not need to be part of the 25 page limit and may be
sent as a separate document.
Addendum 2 – 8123 Cured-in-Place Sanitary Sewers/Stormwater Mains Rehabilitation Page 3 of 3
Q6. In 4., Company Resources: “List all projects and contract amounts completed by the firm
in the past five years”. Then in 5, Project experience: more defined with additional
information but same reference of ALL completed in the past 5 years. Please clarify and
change to either eliminate or as an attachment to the 25 pages.
A6. #4 is a list of projects with their respective contract amounts. Some firms may
provide other services as well as the main one requested, so their list of overall
projects (#4) may be larger.
#5 provides more detail regarding the ‘cured-in-place projects’. The lists may be
combined.