Loading...
HomeMy WebLinkAboutRESPONSE - RFP - 8105 FORT COLLINS UTILITIES VEHICLE STORAGE FACILITIES (3)Step II -Proposal 8106 - Fort Collins Utilities Vehicle Storage Facilities June 24, 2015 Presented to City of Fort Collins c/o Chad Mapp – Project Manager John Stephen CPPO, LEED AP, Senior Buyer QUALITY INTEGRITY VALUE Fort Collins Vehicle Storage Facility 8106 Index 1. Cover Letter 2. Statement of Understanding 3. Team Organization and Management Plan 4. Project Experience and Qualifications 5. Key Personnel 6. Design Process 7. Project Cost, Schedule, and Quality Control 8. Guaranteed Maximum Price 9. Schedule 10. Proposal Security 11. Required Schematic Drawings 12. Proprietary Information QUALITY INTEGRITY VALUE Elder Construction, Inc. Tom Elder, President Patrick Elder, Preconstruction Manager, LEED AP 7380 Greendale Road, Windsor CO 80550 Phone 970.744.4731 Fax 970.744.2257 tom@elderconstructioninc.com patrick@elderconstructioninc.com Architecture West, LLC Stephen J. Steinbicker, AIA, NCARB, LEED Accredited Professional BD+C 160 Palmer Drive, Fort Collins CO 80525 Phone 970.207.0424 Fax 970.207.0424 Steve@architecturewestllc.com Tab1 Cover Letter June 24, 2015 Chad Mapp, Project Manager & John Stephen, CPPO, LEED AP, Senior Buyer City of Fort Collins 215 N. Mason St 2nd Floor Fort Collins, CO 80522 RE: 8106 Fort Collins Utilities Vehicle Storage Facilities Step II Proposal Dear Mr. Mapp & Stephen; Thank you for allowing Elder Construction the opportunity to provide you with our Step II GMP Proposal. For over 21 years Elder Construction has been developing strong and lasting relationships with clients looking for experienced and quality construction services. Elder Construction thrives on bringing together industry knowledge through the use of organized construction methods in helping companies realize their future potential. STEP II GMP $1,498,792.00 One Million Four Hundred and Ninety-Eight Thousand Seven Hundred and Ninety-Two dollars and zero cents. **Please reference Tab 8 for GMP breakout, detail and suggested project alternates. Please feel free to contact me with any questions during your review. Tom Elder President Page 1 of 48 QUALITY INTEGRITY VALUE Tab2 Statement of Understanding 700 Light and Power Building Basis of Design: General Building Information • Building Size 162’x65’ (10,530sf) • This GMP and design assumes vehicle parking/storage only. No additional activities such as truck washing, maintenance are anticipated. • This design and GMP incorporate the City’s Building and Design and Construction Standards. Sanitary Sewer • There is an existing 27 inch sewer line that runs diagonally across the service yard to the north of the proposed structure. There is an existing manhole located approximately 175 feet east of the proposed structure and just south of the eastern most vehicle storage building. A new 4 inch PVC service line will be required to serve the sand / oil separator for the structure. The service line will need to cross an existing 24 inch North Weld water line. All sanitary sewer design and construction shall conform to the Fort Collins Utilities standards and specifications. Domestic Water • There is an existing 6 inch dead end water line approximately 175 feet north of the proposed structure. A new service line (size to be determined) will be required to serve the proposed eye wash stations and wall hydrants. The service line will need to cross an existing 27 inch sanitary sewer line and 24 inch North Weld water line. There are two (2) existing fire hydrants within the service yard, one adjacent to each of the existing structures. At this time it is not known whether Poudre Fire Authority would require a third fire hydrant to be installed in closer proximity to the structure. The final determination will be based on the distance from an available hydrant to the most remote corner of the proposed structure. All water service design and construction shall conform to the Fort Collins Utilities standards and specifications. • Water Tap Fees and Water Rights for new water line are not included within this GMP. • It is assumed the project team will be able to install the new water line over the top of the existing 27” sewer main. Site Electrical • This GMP proposal assumes the City of Fort Collins Light and Power will provide an electrical transformer within ten feet of the new building. This GMP proposal does not include cost for trenching primary service, providing primary service, or cost associated with a new transformer. • We have included two runs of 200lf of 2” conduit only for tele data. Wire and termination to be provided by local service providers. Nat. Gas Distribution • This GMP proposal assumes the City of Fort Collins will pay all Xcel Energy infrastructure costs associated with providing a new gas meter to be located on the building. Site Drainage • The proposed structure will be placed in an area of existing asphalt within the service yard; therefore, there will be no increase in impervious area and no requirement for stormwater detention. The site sheet flows to the south and runoff is directed via an existing storm drainage pipe to a detention and water quality pond located Page 2 of 48 QUALITY INTEGRITY VALUE to the northeast of the property. The city has indicated there may possibly be a need to modify the existing water quality structure within the pond to account for the water quality capture volume (WQCV) associated with the proposed development as this site was not previously accounted for in the pond design. Additional pond grading to increase volume is not anticipated. • Additional low impact development (LID) water quality enhancement features have not been anticipated or included within this GMP proposal. Due to the current site constraints and use of these facilities pervious pavers, bio-retention, rain garden or grass lined swale are not practical. Site Paving • We have included patching and repair of existing asphalt around the building as necessary to provide the building foundation system, new utility connections, and new exterior concrete aprons. Additional site grading or re-pavement has not been included. • We have not included any pavement replacement beyond current site boundary. Landscaping and Site Improvements • None anticipated (to be confirmed with the Minor Amendment Review) Building Concrete • Spread footing foundation with 2’ stem wall final calculation after soils testing, using 3500 P.S.I. concrete. • 6”concrete interior floor with WWM 1.4x1.4 wire mesh. 4000 P.S.I. concrete • Concrete cure, hardener, and control joints included. • We have included 6” reinforced concrete aprons on the north and south side of the building. • The use of 15mil vapor barrier under the building slab is not anticipated or included. • Heating of interior slab on grade construction is not included in the designed, however priced as an add alternate to the project. • Heating of exterior slab on grade construction is not included in the design to have heating elements. • Twenty Four (24) – 6” pipe 10ga. Concrete filled bollards. • 152’ of trench drain with 12” galvanized traffic rated grating. Masonry • We have included a 2’ of 4” masonry unit veneer wainscot on around the perimeter of the building. Steel • All necessary anchor bolts included. Woods and Plastics • We have included rough carpentry as necessary to complete the intended design scope. Thermal & Moisture Control • R-38 roof insulation and R-45.3 wall insulation system (2” insulated metal panel and fiberglass batts with vapor barrier). Openings • Two – 3070 prefinished steel man doors with panic hardware, threshold and weather-stripped. Page 3 of 48 QUALITY INTEGRITY VALUE • Six (6) – 22’ x 12’ Amarr model 2700 Steel insulated and weather-stripped overhead doors with electric operators. • Six (6) – 22’ x 12’ Amarr model 2700 Steel insulated with row of full view lights and weather-stripped overhead doors with electric operators. • Six (6) – 22’x2’ Bronze aluminum with low E glass Finishes • None anticipated Specialites • None anticipated Equipment • None anticipated Furnishings • None anticipated Special Construction (Pre-Engineered Metal Building) • One – “Multi-Span” 65’ x 162’ x 25’ Steel Building with 1:12 Roof Slope • Building designed using IBC 2012 with 20 lb. Live Load, 30 lb. Ground Snow Load, and 115 M.P.H. Wind Load. • Building to have “Standing Seam” roof. • Building to have 2” Insulated Metal Wall Panels. • Interior walls to be have interior liner panel extending from 2’ concrete wall to 7’-4”. Exposed vinyl insulation above. • 162 feet of gutter and downspouts • Full inside perimeter of 7’4” liner panel. Fire Protection • We have included a single wet fire sprinkler protection system to meet NFPA 13 requirements. Plumbing • Provide new water service and reduced pressure backflow preventer for building. o Provide two (2) interior hose bibs. o Provide two (2) exterior hose bibs. o Provide boiler make-up water line with reduced pressure backflow preventer. o Provide one (1) trench drain, assumed 150 foot length. o Provide 1,000 gallon sand/oil interceptor. • Provide two (2) portable eyewash stations. Due to building temperature being below ANSI standard for ‘tepid water’, provide model with internal heater. HAWS 7501FP or equivalent. • Provide gas piping for HVAC equipment. HVAC • Radiant tube heaters at roof/ceiling for heating. Page 4 of 48 QUALITY INTEGRITY VALUE • Provide six (6) gas-fired radiant tube heaters. Solaronics MTS 100/65N40 or equivalent. Radiant tube heaters to be two-stage with tube length of 42 ft, and 100 MBH input. • Provide a total of three thermostats, with each thermostat controlling two (2) tube heaters. • Note that if CNG/LNG vehicles are to be storage within the building, eight (8) tube heaters will be required. Re-Ver-Ber-Ray DX3-40-60 or equivalent. Radiant tube heaters required to have maximum surface temperature of 750F per NFPA 30A, 60 MBH input and 40 ft tube length. • Provide single wall galvanized piping intakes with wall terminations, and type ‘B’ vents with roof terminations. Electrical • We have included a new 200amp Electrical Service • Full cut-off wall packs to be provided on the building. Additional site lighting is not included within this GMP • We have included one (1) 220v receptacle, and ten (10) 110v convenience receptacles • We have included High Bay LED light fixtures • Battery charging stations are specifically excluded within this design and GMP. • Security system will include FOB access control on exterior doors only. Communication and Security cabling and associated equipment will be installed by City of Fort Collins. Raceways only have been included in the GMP pricing. Project Exclusions • This design and GMP specifically excludes the following design criteria o Provision to meet LEED Gold as this project type can not be certified by the LEED program o Provisions to meet the River District design criteria o Provision to meet the Art in Public Spaces design criteria • This design and GMP specifically excludes additional site parking requirements. • This design and GMP specifically excludes landscaping, irrigation, and additional site improvements not specifically listed below. • This GMP excludes all applicable taxes consistent with tax exempt projects. • Low Impact Development Requirements are specifically excluded in this design and GMP. • Interior office and restroom facilities are specifically excluded in this design and GMP. • This design and GMP specially excludes the storage of Hazardous materials. • This design and GMP specially excludes all building modeling and commissioning. • This design and GMP specially excludes any redundant or backup systems beyond standard life safety systems. Suggested Project Alternates • Building Alternate # 1 – Provide insulated metal roof panels in place of standing seam roof system • Building Alternate # 2 – Provide full height interior wall panel • Building Alternate # 3 - Provide interior ceiling wall panel • Plumbing – Alternate #1 - In lieu of base bid, provide hard-piped eye/face washes. o Provide two (2) wall mount eye/face washes. Page 5 of 48 QUALITY INTEGRITY VALUE o Provide one (1) tankless gas-fired water heater and associated PVC intake and vent piping. o Water heater to be sealed combustion type. o Provide gas piping to water heater. o Provide two (2) tempering valves. • HVAC – System Alternate #1 - Radiant floor heat with heat generated by gas-fired boiler with continuous R-10 rigid insulated slab. o Provide radiant floor tubing. 5/8” at 12” on center. Approximately 10,500 feet of tubing. o Uponor hePEX or equivalent with oxygen barrier. Provide manifolds as required. o Provide (1) condensing boiler. Total output minimum 400 MBH. Lochinvar Knight XL KBN501 or equivalent. Provide PVC vent, PVC intake and gas piping. o Provide ASME expansion tank. o Provide inline heating water pump. Approximately 40 gpm flow. • HVAC – System Alternate #2 - Radiant floor heat with heat generated by ground-source heat loop with continuous R-10 rigid insulated slab. o Provide radiant floor tubing. 5/8” at 12” on center. Approximately 10,500 feet of tubing. Uponor hePEX or equivalent with oxygen barrier. Provide manifolds as required. o Provide (2) 15-ton water-to-water heat pumps. Water Furnace NDW180 or equivalent. Total heat capacity approximately 400 MBH. o Ground source loop tubing will be required. Quantity requirements to be determined by Geo designer. o Provide inline secondary heating loop water pump. Approximately 60 gpm flow. o Provide (2) inline primary heating loop water pumps. Approximately 24 gpm each. o Provide (2) ground source loop pumps. Approximately 100 gpm each. o Provide (3) expansion tanks. o Ground loop tubing to be filled with 30% propylene glycol. o Geo-Thermal Exchange infrastructure to be provide by City of Fort Collins. • HVAC – Alternate 3 - For general exhaust and summer heat removal. o Provide one (1) wall prop exhaust fan with wall hood, motorized backdraft damper, and motor guards. Sized for 10,000 cfm. Provide with VFD for soft start. Fan to be controlled manually by wall switch. o Provide two (2) intake louvers with motorized dampers. Each louver system approximately 60” x 48”. • HVAC – Alternate #4 - This alternate would be required if CNG or LNG vehicles are to be stored within the building per NFPA 52. The system in alternate #A above could be omitted, and this system could be used in a manual mode if desired for general exhaust and summer heat removal. o Provide two (2) inline exhaust fans, each sized for 11,000 cfm. Exhaust fans to include an explosion proof motor. o Provide roof exhaust hood for each fan, with motorized backdraft damper. o Provide four (4) low intake louvers with motorized dampers. Each louver approximately 60” x 48”. Page 6 of 48 QUALITY INTEGRITY VALUE o Provide methane detection system. Upon detection, system to initiate visual alarm, audible alarm, open intake dampers and operate exhaust fans. • Electrical Alternate #1 – Provide Photovoltaic System o 39.06kW system, o 310 Watt module/36kW inverter combination o 40.6kW array. 701 Water Building Basis of Design General Building Information • Building Size 160’x35’ (5,600sf) Sanitary Sewer • There is an existing 27 inch sewer line within W. Vine Drive to the south and an 8 inch sewer line to the north of the proposed structure. However, at this time there are no proposed restrooms or sand/oil separators that would warrant the need to extend sewer service to the structure. Water • There is an existing 12 inch water line in W. Vine Drive to the south, a 6 inch water line in Wood Street to the east, and an 8 inch water line to the west of the proposed structure. However, at this time there are no proposed restrooms or other water requirements that would warrant the need to extend water service to the structure. Site Drainage • The proposed structure will be placed in an area of existing concrete and gravel within the service yard; therefore, there will be minimal to no increase in impervious area and no requirement for stormwater detention. The site sheet flows to the north and runoff is directed via an existing storm drainage pipe to a detention and water quality pond located to the north of the property. The city has indicated there may possibly be a need to modify the existing water quality structure within the pond to account for the water quality capture volume (WQCV) associated with the proposed development as this site was not previously accounted for in the pond design. Additional pond grading to increase volume is not anticipated. • Additional low impact development (LID) water quality enhancement features have not been anticipated or included within this GMP proposal. Due to the current site constraints and use of these facilities pervious pavers, bio-retention, rain garden or grass lined swale are not practical. Site Electrical • This GMP proposal assumes the City of Fort Collins Light and Power will provide an electrical transformer within ten feet of the new building. This GMP proposal does not include cost for trenching primary service, providing primary service, or cost associated with a new transformer. Landscaping and Site Improvements • None anticipated (to be confirmed with Minor Amendment review) Building Concrete • Spread footing foundation with 2’ stem wall final calculation after soils testing, using 3500 P.S.I. concrete. • 6”concrete interior floor with WWM 1.4x1.4 wire mesh. 4000 P.S.I. concrete Page 7 of 48 QUALITY INTEGRITY VALUE • The use of 15mil vapor barrier is not anticipated or included. • Seven (7) – 6” pipe 10ga. Concrete filled bollards. • We have not included any exterior concrete aprons. • Heating of exterior slab on grade construction is not include in the design to have heating elements. Masonry • None anticipated Steel • All necessary anchor bolts included. Woods and Plastics • We have included rough carpentry as necessary to complete the intended design scope. Thermal & Moisture Control • None anticipated Openings • None anticipated Finishes • None anticipated Specialites • None anticipated Equipment • None anticipated Furnishings • None anticipated Special Construction (Pre-Engineered Metal Building) • One – “Clear-Span” 35’ x 160’ x 21’ Steel Building with 1:12 Roof Slope (Open on the east side, no wall panel finishes). • Building designed using IBC 2012 with 20 lb. Live Load, 30 lb. Ground Snow Load, and 115 M.P.H. Wind Load. • Building to have “Standing Seam” roof. • Building to have “PBR” walls. • 160 feet of gutter and downspouts • Interior walls to be have interior liner panel extending from 2’ concrete wall to 7’-4”. Fire Protection • A fire sprinkler or suppression system has not been included in this design or GMP pricing. Plumbing • Provisions for water service or compressed air have not been included in this design or GMP pricing. • Provisions for a trench drainage system have not been included in this design or GMP pricing. Page 8 of 48 QUALITY INTEGRITY VALUE HVAC • None anticipated Electrical • We have included a new 200amp Electrical Service • Full cut-off wall packs to be provided on the building. Additional site lighting is not included within this GMP • We have included Ten (10) 20amp receptacles for vehicle block heaters. • We have included High Bay LED light fixtures • Battery charging stations are specifically excluded within this design and GMP. Project Exclusions • This design and GMP specifically excludes the following design criteria o Provision to meet LEED Gold as this project type can not be certified by the LEED program o Provisions to meet the River District design criteria o Provision to meet the Art in Public Spaces design criteria • This design and GMP specifically excludes additional site parking requirements. • This design and GMP specifically excludes landscaping, irrigation, and additional site improvements not specifically listed below. • This GMP excludes all applicable taxes consistent with tax exempt projects. • Low Impact Development Requirements are specifically excluded in this design and GMP. • Interior office and restroom facilities are specifically excluded in this design and GMP. • This design and GMP specially excludes the storage of Hazardous materials. • This design and GMP specially excludes all building modeling and commissioning. • This design and GMP specially excludes any redundant or backup systems beyond standard life safety systems. Suggested Project Alternates • Electrical Alternate #1 – Provide Photovoltaic System o 39.06kW system, o 310 Watt module/36kW inverter combination o 40.6kW array. Page 9 of 48 QUALITY INTEGRITY VALUE Tab 3 Management Experience and Capability Project Coordinator (Stacie Gallagher) • Maintain As-built/Record Drawings • RFI Management • Submittals Management • Project Closeout Project Manager Tim Stern • Project oversight and planning • Project accounting and cost control • Organize and maintain team communication and coordination • Oversight of project documents • Value Estimating Site Superintendent Audie Wilson • Site Supervision • Safety • Scheduling • Constructability Reviews • Quality Control Carpenter Foreman Carpenters Labors Elder Construction Patrick Elder - Preconstruction Manager Preconstruction Services Architecture West, LLC Steve Steinbicker- Design Architect Consultant Team Coordinator Architect / Planner / Interior Designer Architecture West, LLC Mechanical / Plumbing Engineer The Ballard Group, Inc. Electrical Engineer SRB Consulting Engineering Structural Engineer Weeks & Associates, Inc. Civil Engineer Interwest Consulting Group Traffic / Transportation Engineer Delich Associates Geotechnical Engineer & Material Testing Earth Engineering Consultants Owner City of Fort Collins Facilities Staff- Water Department & Power Department Elder Construction Austin Dodder- Construction Manager Project oversight and planning Page 10 of 48 QUALITY INTEGRITY VALUE Elder Construction will provide a staffed onsite Superintendent, and required carpenters and labors. The project will also include a dedicated project manager and project coordinator/project engineer located off-site in our main office. Construction Manager – Responsible for the overall project leadership and manages all areas of construction, including weekly progress reviews with Elder staff and regular site visits. Superintendent – Responsible for the overall onsite leader is the Superintendent. The main point of contact for all major decisions onsite including coordination of all subcontractors, ensuring that materials arrive onsite, inspections by state and local officials occur at each stage in the construction process, and that the schedule and budget is maintained. The Superintendent and the Project Manager work together as team to make sure project stays on track. In addition they are the communicating voices during the owner, architects, and contractor’s (OAC) meetings providing overall status updates. Project Manager – Responsible for overall leadership and direction for the project from start to finish. The project manager’s primary responsibilities include: reviewing and issuing subcontracts, project accounting, managing the budget, cost value engineering, pricing and reviewing change orders, and holding regular status meetings with subcontractors and owners. Additional functions include closely working with the Superintendent in maintaining and updating the schedule to insure the project completes on time. The project manager will also assist the Project Engineer in the RFI and Submittal processes. Project Coordinator/Engineer - Our project coordinator/engineer will seamlessly coordinate with the subcontractors to ensure the correct building materials are being used and delivered according to the schedule. Our project coordinator/engineer will also manage the administrative obligations for the team, including insurance, subcontract execution and project closeout. Carpenter/Laborers – Our carpenter/labors report to the Superintendent and are responsible for completing all self performed activities. They will is also responsible for assisting in temporary protection and subcontractor coordination needs as required. Owner Coordination Meetings In order to keep the owner fully informed and to keep open communication, Elder puts together regular weekly Owner, Architect’s and Contractors (OAC) meetings. In this meeting every detail of the project is reviewed. Meeting minutes are passed out and reviewed identifying key issues that need to be addressed on the project. An updated schedule is included and reviewed. This keeps the owner up to date on critical activities, integration with the owner’s subcontractors and review of the overall completion date. In addition, request for Information, Submittal, and Change Order logs are provided and reviewed. This provides the opportunity to prioritize any outstanding submittals and RFI’s that need to be addressed quickly to stay on track. Subcontractor Coordination Meetings Every week, in addition to OAC meetings, Elder Construction Staff will conduct a subcontractor coordination meeting. In these meetings the schedule is reviewed, subcontractors provided an update of current status, safety, major deliveries, and coordination of critical upcoming work programs. Submittal, RFI, and Change Order logs are discussed and notification of any required inspections and shut downs are reviewed. The goals of these meetings are to keep all subcontractors informed of critical items and overall project progress. Page 11 of 48 QUALITY INTEGRITY VALUE Tab 4 Design Build Experience & Project Profiles (Please reference Project Team and Team Member Experience in Section 5 Team Experience) Recently Completed Vehicle Maintenance / PEMB / Public Projects / LEED Projects Vehicle Maintenance Titan Machinery (Completed as a Design/Build Team) Schmidt Earthbuilders Poudre Valley Electric Mountain View Fire Protection District Fire Station No. 4 Mountain View Fire Protection District - Longmont Mountain View Fire Protection District Fire Station No. 3 Mountain View Fire Protection District – Erie Fire Station #14 – Colorado Springs Falcon School District 49 – Auxiliary Bus Service Facility Pre-Engineered Metal Buildings Titan Machinery (Completed as a Design/Build Team) Petersen Sierra Longview Genesis SuperVac Waterford World Beverage Napa Auto Parts Elder Construction, Inc. Hartford Homes Risk Removal The Classical Academy Sand Creek High School Field House Spillway Office Building Towncenter Office/Warehouse Building SA Robotics Public Projects Mead Community Center Nederland Community Center Lochbuie Town Hall & Police Services Center Pioneer Charter School Freedom Elementary School Loveland Classical Schools Carter Lake Marina Cherokee Metropolitan Water District Building Hanover Fire Support Service Bldg Widefield School District 3 – Webster Elementary City of Colorado Springs - Cold Storage Building Falcon #49 - Sand Creek High School Field House Falcon School District 49 – Auxiliary Bus Service Facility Fire Station #14 – Colorado Springs Mountain View Administrative Offices LEED Projects Nederland Community Center Sister Mary Alice Murphy Center for Hope Peloton Cycles Pioneer Charter School Mountain View Fire Protection District Fire Station No. 3 Mead Community Center Lochbuie Town Hall Sundance Professional Center Page 12 of 48 QUALITY INTEGRITY VALUE PEMB Vehicle Maintenance (Design Build) Architecture West and Elder teamed up to provide a single source project delivery for the Titan Machinery Project. The team effectively managed the project from the initial site plan review process with the Town of Windsor to the complete delivery of an interior remodel of the office area, pre-engineered metal building addition to provide for additional parts storage, complete upgrade of HVAC system in the garage/shop to provide vehicle exhaust, and a new wash bay facility with new domestic water, sanitary sewer, primary electric, and natural gas utilities services. CLIENT Titan Machinery 644 E. Beaton Drive West Fargo ND 58078 DESIGN/BUILD TEAM Elder Construction, Inc. Architecture West, LLC TB Group Weeks Structural Engineering Integrated Mechanical SRB Engineering LOCATION 7250 Greendale Road Windsor, CO BUILDING INFORMATION Building Type V-B, B & S-1 Occupancy 1,482 square foot interior office remodel 2,285 square foot Pre-Engineered Metal Building Addition 6,500 square foot Garage Maintenance 6,000 square foot Vehicle Wash Bay PROJECT DURATION 5 months CONTRACT VALUE $ 758,942.00 Page 13 of 48 QUALITY INTEGRITY VALUE Public Vehicle Storage- LEED* Gold (Pending) Architecture West spearheaded this project for the Town of Mead, which included both the Mountain View Fire Protection District Fire Station No. 3 and the Mead Community Center. The east side of the building features a combined fire station and vehicle storage facility, while the remainder of the building is occupied by administration offices, assembly areas and other community facilities that make up the new Community Center. The entire building is currently pending LEED* Gold Certification. CLIENT Town of Mead, Colorado BUILDING INFORMATION Building Type V-B, A-3, B & S-1 Occupancy 13,500 square foot building, LEED* Gold (Pending) 1,731 square foot vehicle storage area PROJECT DURATION 9 months CONTRACT VALUE $ 2,650,000 PEMB Architecture West played a key role in the design-build-assist process for the Genesis Fixtures Project, which included new office space as well as research and development, warehouse and production facilities. CLIENT Genesis Fixtures, Inc. Fort Collins, Colorado BUILDING INFORMATION Building Type II-A, B & S-1 Occupancy 161,980 square foot Pre-Engineered Metal Building 30,000 square foot office space PROJECT DURATION 7 months CONTRACT VALUE $ 4,260,000 Page 14 of 48 QUALITY INTEGRITY VALUE LEED*-CS Gold Certified Nederland Community Center - Community Recreation Center, Gymnasium, Exercise Areas, Community Meeting Rooms and Classrooms, Administrative Offices, Theatre CLIENT Town of Nederland, Colorado BUILDING INFORMATION Building Type V-B, A-3, B & S-1 Occupancy 26,181 square foot building, LEED* Gold Certified PROJECT DURATION 10 months CONTRACT VALUE $ 2,175,000 LEED*-CS Gold Certified Sundance Professional Centre - Multi-Tenant Professional / Medical Offices CLIENT Loveland, Colorado BUILDING INFORMATION Building Type V-B, B Occupancy 19,000 square foot Pre-Engineered Metal Building EPA Energy Star Design Rating of 97 Bronze Award for Construction Excellence PROJECT DURATION 11 months CONTRACT VALUE $ 2,850,000 Page 15 of 48 QUALITY INTEGRITY VALUE Financial Capability Identify Project Financial Arrangements Elder Construction and Architecture West acknowledge both firms have the financial capacity to absorb project start-up costs as well as maintain the day to day working financial aspects of the project. Pending or Outstanding Claims or Judgements Elder Construction, Inc. nor Architecture West, LLC are not currently involved in any pending or outstanding construction claims or judgements. Banking and Financial Institution References Wells Fargo 90 S. Cascade Colorado Springs, CO 80903 Paul Teichert 719-577-5496 Financial Statements Financial Statements provided as hard copy in Phase I. Letter of Bonding Capacity Financial Statements provided as hard copy in Phase I. Insurance Certificates Financial Statements provided as hard copy in Phase I. Page 16 of 48 QUALITY INTEGRITY VALUE Tab 5 Key Personnel EDUCATION Ohio State University Bachelor of Science Architecture REGISTRATION COLORADO, #B-1772 NCARB #63677 AFFILIATIONS AMERICAN INSTITUTE OF ARCHITECTS NCARB (NATIONAL COUNCIL OF ARCHITECTS REGISTRATION BOARDS) LEED ACCREDITED PROFESSIONAL ,BD+C (LEADERSHIP IN ENERGY AND ENVIRONMENTAL DESIGN) US GREEN BUILDING COUNCIL: COLO. NORTH CHAPTER MEMBER ENERGY STAR PARTNER INSTITUTE FOR THE BUILT ENVIRONMENT ADVISORY BOARD MEMBER FRONT RANGE COMMUNITY COLLEGE ADVISORY BOARD MEMBER CITY OF FORT COLLINS AND LARIMER COUNTY IBC BUILDING CODE REVIEW BOARD MEMBER CONTACT INFORMATION Architecture West, LLC 160 Palmer Drive Fort Collins, CO 80524 www.architecturewestllc.com Phone 970.207.0424 steve@architecturewestllc.com STEPHEN J. STEINBICKER, AIA, NCARB, LEED AP, BD+C PRINCIPAL ARCHITECT A Principal of Architecture West, Steve founded the firm in 1996 with the goal of focusing on sustainable design and integrated design with a design-build team integration and collaborative approach. His superior delivery system balances clients’ needs with value. A LEED Accredited Professional since 2004, Steve is passionate about applying creative, sustainable design principles tied to practical solutions to the firm’s design projects, producing high-performance buildings. His areas of expertise include architectural design, sustainable/daylighting design, construction documents and contract administration, whole integrated design approach and project development, site analysis/selection, land planning, programming,. Selected Relevant Experience • Mead Fire Station &Town Hall/Community Center Addition & Remodel, Mead CO; pursuing LEED Gold Certification; 13,500 sf • Mountain View Fire Protection District, Fire Station #1, Longmont, CO; Remodel & Tenant Finish; 5,400 sf • Mountain View Fire Protection District, Fire Station #4, Niwot, CO; Addition & Remodel; 7,460 sf • Lochbuie Town Hall, Lochbuie, CO; Community Services & Police Hdqtrs., Designed to LEED Gold Standards, 13,000 sf • Loveland Classical High School, Loveland ,CO;13,400 sf • Professional and Medical Offices; LEED-CS Gold Certified; EPA Energy Star design rating of 97; 19,000 sf • Colorado Springs School District #11 Freedom Elementary School, Colorado Springs,CO; built to LEED standards; 62,000 sf QUALITY INTEGRITY VALUE EDUCATION Colorado State University Bachelor of Administration Business Management Minor in Construction Management FIRM EXPERIENCE Elder Construction, Inc. Loveland, Colorado 2009-Present Icon Group, Inc. Castel Rock, Colorado 2007-2008 GE Johnson Construction Denver, Colorado 2004-2007 Elder Construction, Inc. Colorado Springs, Colorado 1997-2002 PROFESSIONAL ACCREDITATIONS 2006 IBC General Contractors License #614 U.S. Green Building Council CONTACT INFORMATION Elder Construction, Inc. 7380 Greendale Road Windsor, CO 80550 www.elderconstructioninc.com Phone 970.744.4731 Fax 970.744.2257 patrick@elderconstructioninc.com PATRICK ELDER, LEED AP PRECONSTRUCTION MANAGER Patrick Elder is the Preconstruction Manager for Elder Construction’s Northern Colorado office. Patrick has over 10 years of construction experience in a wide range of construction markets including extensive experience in Colorado. Upon graduation from Colorado State University with a B.A. in Business Management and minor in Construction Management Patrick went to work for GE Johnson Construction, a large general contractor in Colorado as a Project Engineer and Estimator. While with GE Johnson Construction Patrick estimated commercial and multi- family construction projects up to and over $100 million in construction cost. After 4 years with GE Johnson Construction, Patrick joined the Icon Group, a construction consulting firm, where he spent his time focused on delivering exceptional preconstruction services to clients in Indiana, Texas, Idaho, Utah and Colorado. While with the Icon Group Patrick estimated Healthcare, resort and multi-family projects ranging up to $191 million in value. Patrick is responsible for providing overall leadership and direction in the preconstruction phase of projects including conceptual/budget estimates and cost study analysis. Project Experience (PEMB) Napa Auto Parts, Fredrick CO Risk Removal, Windsor CO Elder Construction, Windsor CO Hartford Homes, Timnath CO NoCo Self-Storage Facility, Timnath CO Bee Clean Auto Wash, Greeley CO Page 18 of 48 QUALITY INTEGRITY VALUE EDUCATION Colorado State University Bachelor of Science Construction Management FIRM EXPERIENCE Elder Construction, Inc. Windsor, Colorado 2011-Present GE Johnson Construction Colorado Springs, Colorado 2003-2011 Skeet Dodder Construction Colorado Springs, Colorado 1997-2003 REFERENCES Sangre de Cristo School District Mr. Brady Stagner 719.378.2321 GE Johnson Construction Mike Kosters 303.930.9000 Klipp Architecture Mr. Jay Ireland 303.893.1990 PROFESSIONAL ACCREDITATIONS U.S. Green Building Council CONTACT INFORMATION Elder Construction, Inc. 7380 Greendale Road Windsor, CO 80550 www.elderconstructioninc.com Phone 970.744.4731 Fax 970.744.2257 austin@elderconstructioninc.com AUSTIN DODDER, LEED GA OPERATION MANAGER Austin Dodder is Elder Construction’s Operation Manager for Elder Construction’s Northern Colorado office. After graduating from Colorado State University with a Bachelor’s of Science in Construction Management. Austin spent the first seven years working for a large regional general contractor. His experience has included various job assignments in many remote locations. In 2011 Austin joined Elder Construction by joining the Northern Colorado Office to oversee the field operations of the Northern Office. Project Experience Sangre de Cristo PK-12 School, Masa CO $19 million, 80,000sf PK-12 school with a 40 acre site. Manor Vail Penthouses, Vail CO $100 million addition of 17 high-end penthouses including a 4 story underground parking structure with roof top garden and 4 acre site. Northstar Base Village Phases 1, 2 and 3, Truckee CA $225 million, 7 building mixed use resort and spa including a 60 acre site in Truckee, CA. Edgemont Building A, Steamboat CO $42 million, 100,000sf, eight-story mixed use resort and spa that included 39 high end condos in Steamboat Springs, CO. Napa Auto 20/20 Vision Center Rocky Mountain Family Vision Platteville Family Dental QUALITY INTEGRITY VALUE FIRM EXPERIENCE Elder Construction, Inc. Loveland, Colorado 2013-Present Boardwalk Builders, Inc. Fort Collins, Colorado 2012-2013 Delta Construction, Inc. Fort Collins, Colorado 2003-2010 Growling Bear Co Greeley, Colorado 2000-2003 REFERENCES Christian Bachelet Maximo Development Group 970.224.9204 Mark D’Rosario PE Principal, CE Group 970.266.8888 Walk Gantt, AIA, LEED AP Kenney and Associates 970.663.0548 PROFESSIONAL ACCREDITATIONS LEED Accredited Professional CDOT Erosion Control OSHA 10-Hour Course Red Cross Adult CPR Red Cross First Aid CONTACT INFORMATION Elder Construction, Inc. 471 N. Denver Ave Loveland, CO 80538 www.elderconstructioninc.com Phone 970.744.4731 Fax 970.744.2257 audie@elderconstructioninc.com AUDIE WILSON, LEED AP SUPERINTENDENT Audie Wilson has over 30 years experience as a construction superintendent and has managed a wide range of projects including manufacturing facilities, banks, restaurants, fire stations, mixed use buildings, data centers, and office / warehouse buildings. His experience has lead him to build structures in Colorado, Wyoming, Utah, and California. As project superintendent Audie is the on-site leader of the project. Audie serves as the main point of contact for all major decisions onsite, including coordination of all subcontractors, ensuring that materials arrive onsite, inspections by state and local officials occur at each stage in the construction process and that the schedule and budget is maintained. Project Experience Wendy’s Restaurant Centennial Bank of the West Eaton Fire Station Advanced Manufacturing Technology Larimer County Community Corrections Kroll Factual Data Mc Whinney Flex R and D #1 Mc Whinney Flex R and D #2 Campus West Mixed Use QUALITY INTEGRITY VALUE EDUCATION Colorado State University Bachelor of Science Mathematics FIRM EXPERIENCE Elder Construction, Inc. Windsor, Colorado 2013-Present The Neenan Company Fort Collins, CO 2011-2013 Delta Construction Fort Collins, CO 2003-2010 The Neenan Company Fort Collins, CO 1994-2002 REFERENCES Bruce Clark New Belgium Brewing Company 970-443-1747 CONTACT INFORMATION Elder Construction, Inc. 7380 Greendale Road Windsor, CO 80550 www.elderconstructioninc.com Phone 970.744.4731 Fax 970.744.2257 tim@elderconstructioninc.com TIM STERN, LEED AP PROJECT MANAGER Tim Stern will be the Project Manager on the project. As project manager, Tim is responsible for providing overall leadership and direction to the project from start to finish. Tim’s primary responsibilities include: reviewing and issuing subcontracts, project accounting, managing the budget, cost value engineering, pricing and reviewing change orders, and holding regular status meetings with subcontractors and owners. Additional functions include closely working with the Superintendent in maintaining and updating the schedule to insure the project completes on time. Tim will also assist the Project Engineer in the RFI and Submittal processes. Tim strives to lead the team in a collaborative effort which optimizes the client’s value, providing key information, and strategies early to help make informed and timely decisions to lower costs and drive sensitive construction schedules. Project Experience Aspen Arbor Animal Hospital: ($3.5M) 28,000 SF total with an 8,000 SF hospital and boarding facility with one surgery room, 24 hour emergency service, dog and cat boarding, and grooming / dog wash. The development also includes 20,000 square feet of multi-tenant flex/retail space that may include complimentary pet related businesses – Broomfield, Colorado. Edora Pool Ice Center: ($3M) 30,000 SF Design-Build second sheet of ice at EPIC. Includes a new ice sheet, dasher board system, spectator area, new men’s and women’s locker rooms, and a heated ice dumping pit—Fort Collins, Colorado. Front Range Internet: ($380,000) 15,000 SF office and data center tenant finish includes a back- up power generator and Liebert computer room air-conditioning, redundant fiber optic utility services and network operating center—Fort Collins, Colorado. Greeley Medical Clinic: ($3.7M) 40,000 SF tenant finish inside the Medical Center of the Rockies MOB II. This tenant finish includes a MRI, CT scanner, two x-ray rooms, ultrasound rooms, and hanging surgical microscopes – Loveland, Colorado. New Belgium Brewing Company: ($3M) Two concurrent Design-Build projects consisting of a four story malt grain storage and handling building and a 16 vessel beer fermentation facility – QUALITY INTEGRITY VALUE Tab 6 Design Process Methodology and Sustainable Project Solutions The Design Build services of Elder / Architecture West, LLC Team have a long-term commitment & collaboration on high performance design, with an Integrated Design approach, on a significant number of projects. Design charettes become an effective way for early dynamic workshops, goal setting, conceptualization, broad user input, quickly, increasing the initial ‘front- end’ time but allowing for a more comprehensive Pre-Construction Budgeting analysis. This provides an opportunity to gather the entire building team, owners and stakeholders to identify goals, process, issues and solutions. Environmental issues are defined, strategies explored and innovative solutions discovered. We have created a distinct owner value development process with a specific focus on embracing creative ideas and open environment, specifically with vehicle maintenance, LEED* Certified, Public & PEMB projects. Architecture West provides land planning, interior design and award-winning architectural designs that are responsive to both the owners' needs and the environment. Architecture West is committed to high performance sustainable building. Our projects have been significantly enhanced by responsible and responsive architectural planning and design. Our goal is to produce a building that will meet/ exceed the required LEED*- Gold Standards, have minimal environmental impact with the maximum amount of human comfort, and greater energy performance. The consultant team of architects, planners, sustainability experts, and engineers specializing on Energy Modeling, Envelope Testing, provide a practical and confirmed experience, at the highest levels of the Construction Industry. Focusing the integrated vision of a skilled design team on whole systems solutions for a specific project results in quality, timeless and sustainable architecture. This collaboration can combine beauty with practicality, meld amenity with economics, and honor the needs of both present and future generations. This process results in "real time" coordination of all design criteria through the synergy of the team Architecture West utilizes AutoDesk Revit, the latest in BIM (Building Information Modeling) technology to design and construct projects in 3D. The benefits of 3D modeling is the ability to observe the design in real-time, challenging ourselves, our Consultants and the Client, providing multiple options and design solutions. This not only helps us to study and test concepts before they are integrated but also allows us to identify potential conflicts in the earliest design phases, saving time and money. This software also allows us to collaborate with Structural and MEP teams. Architecture West and Group 14 Engineering have worked together for years. Elder recently teamed up on the Mead Town Hall & Fire Station. Group14 facilitated and documented the LEED Gold Certification for this project, and provided energy analysis and commissioning. The project demonstrated over 40% interior water savings, achieved all 19 energy optimization points, and followed LEED v4 construction waste recycling to earn an Innovation Point while recycling over 75% of the waste. For energy efficiency, the key was keeping the systems simple while still providing occupancy control to minimize unoccupied energy consumption. A 14 kW photovoltaic system offsets 21% of the building energy consumption by cost. Design Team Organization Architecture West, LLC will be the coordinator of the Design Consultants and Construction Team. This will be a very lateral approach with multiple joint Integrated Design meetings, giving all vested Parties, the ability to question, challenge, evaluate and study alternate/options, as we go through the initial Schematic Design Phase. A ‘whole-systems’ thinking / building approach, searches for selections that benefit in multiple ways, are synergistic, window daylighting / ventilation/ lighting controls, for Page 22 of 48 QUALITY INTEGRITY VALUE example. DRT, Development Review Team meetings will provide regular opportunities for ‘progress’ updates and evaluations, with specific core groups/focuses Enhanced, planning, energy, sustainability/LEED* issues. Design Process • Establish Owner Goals & Programming requirements. • Utilize Design Charette & LEED* Scorecard evaluation, to track project status and progress. • Coordinate ‘real-time’ Pre-Construction estimating in qualifying the final Budget. • Continual Design Development and DRT (Design Review Team) reviews with Client representatives and core Construction/Design Team members. • On-going Construction Document reviews from City Cx and Modeling consultants, peer, LEED*, Budgets, and Constructability reviews. • Monitoring and coordinating Construction phase, questions, specifications & CD documents. • Coordinate with City’s Final Commissioning, testing and final delivery/acceptance. Low Energy & Sustainable Design Features Daylighting, occupancy sensors, Photo voltaic panels, high-performing insulation systems, fluid applied air/moisture barriers, low-flow water fixtures, Energy recovery systems, high-performing Mechanical systems including Geo-thermal heating & cooling systems, Solar Wall air and water pre-heating systems, chilled beam design, ice storage & other synergistic, mutually beneficial opportunities/solutions. Elements of a Successful Team - Goals, Communication & Decision Making Team building is comprised of several elements, initiated and developed over the project life; Goal setting, Roles definition and responsibilities, coordinated Problem solving & Relationship management. The Team Building starts with the LEED* Design Charette, and continues with Owner/Contractor/Consultant Integrated design collaboration meetings. These project meetings are formatted on consistent timelines and are often tied to Critical Path dates of decision making & delivery of project documents. Key Schematic & Design Development reviews are critical to client ‘buy-in and contractor budgeting analysis, allowing the project to move forward from concept to completion. The General Contractor and Design team are working for the same goals of the project/client. Trust in the whole team, practical decision making with a constant challenge of creativity and constructability. Trust that the functional and fiscal goal of the client are FIRST, consultants evaluate options and alternates, Trust that the sustainability is a part of all decision making, long term value, energy systems evaluations, first –cost vs. long term operational and maintenance costs. Design-build-assist with the client in the making decisions of alternatives presented by the design team and budgeted by the contractor. Team building certainly continues with Municipal and Fire Authorities, understanding Codes and having a mutual relationship with governing Authorities. Our Team has a long standing working relationship with Fort Collins Staff at the Planning, Building Department and PFA agencies. Page 23 of 48 QUALITY INTEGRITY VALUE Tab 7 Project Cost, Schedule and Quality Control Methodology for Controlling Costs Elder Construction will work with the ownership group and the design team to establish the overall guiding design goals and principles. These Design Principles will be the framework in which decisions will be made and evaluated throughout the project. Goals will be established for all aspects of the design and preconstruction phases. Schedule milestones will be set. Budgets will be clearly established and laid out for all to understand. During this phase, we will also begin to test the project costs to make sure we are within the budget. Cost control and working within the budget is of paramount concern, and is the responsibility of the entire Team. The architect and engineers will work closely with Elder Construction to control project costs. This will ensure that, as the project design is finalized, we are collaborating on the materials and considerations that not only meet the budget requirements but also provides the best value solution. Elder Construction will be an active part of the final design along side the design team. This is not only so we can monitor the budget, but also ensure constructability. We want to make sure that any materials chosen and methods selected through the design or scope integration, are the most efficient systems to build. Additionally, Elder Construction will review the drawings and specifications for any scope gaps or areas for potential clarification for the subcontract team. By performing due diligence up front, we will save time once we are under construction. Another advantage of being involved during the design phase is to identify all of the submittals, including the long lead items, up front. By knowing what is needed to be submitted or ordered immediately, Elder Construction can start the submittal process and work to minimize any potential schedule impacts. Elder Construction utilizes key costing data bases and state of the art computer software to prepare detailed estimates and construction schedules early. This focus allows our clients and designers to make immediate decisions before documents are complete and construction starts are compromised. A cornerstone of our company’s success is an estimating system that produces accurate and complete estimates in the shortest possible timeframe. We spend our careers understanding, tracking, and validating construction cost so our clients don’t have to. We combine detailed quantity surveys and current marketing pricing to produce estimates that hold true. Value Engineering Approach Value engineering is a mindset and team approach involving the owner, design team, consultants, contractor and trades. Value engineering is approached by understanding the goal of the project and creatively providing the ownership group with ideas, options, and cost information to make informed decisions. Value Engineering is a systematic method for analyzing a project site to identify essential functions, design opportunities and alternate methods to meet your project’s budget and schedule requirements. We work closely with our clients to provide value that respect your intent and meets your time and cost requirements. Through the value engineering process, we will evaluate the design, construction materials and systems involved to determine if there are more cost-effective options to achieve the same result. We evaluate the impact on initial cost of construction, operations, maintenance and life cycle cost. Step One – Understand the goals of the project (Budget, Programing, Aesthetics) Step Two – Collaborate with the design team, consultants, and trade to identify area of cost savings Step Three – Develop cost and time elements related to these areas of cost saving Step Four – Present to the ownership group, track, and incorporate into the design documents. Page 24 of 48 QUALITY INTEGRITY VALUE Construction Schedule Critical path activities are the driving force behind the completion date for any project schedule and maintaining them is a must if construction is to stay on track. Schedule Creation Each schedule is created based upon analysis of the drawings, identification of critical construction activities, critical approvals, and past experiences. The project schedule is completed and reviewed by the project team allowing for discussion, “outside the box thinking,” and planning. Every part of the construction process will be studied. Critical submittals will be added to the schedule and tied in accordingly to their installation dates; identification of critical sections of the construction will be determined and broken out accordingly. Any activity over 10 days will be broken up into multiple activities to provide the most detail possible. After this back and forth discussion the final schedule will take place and be issued to subcontractors for their review and feed back. In this process both the Project Manager and the Superintendent have ownership in the schedule and understand how the schedule was generated. Identifying the Critical Path Critical Activities are activities on the schedule that cannot be changed or moved otherwise they affect the completion date. Identifying these is critical for a competent, correct and realistic schedule. One way Elder identifies these are by submittal requirements and the fabrication time of the material. During the bid process and while the preliminary schedules are being produced Elder is following up with subcontractors to identify material fabrication time for critical activities. Each of these submittals are included in the schedule in their own section and provided a fabrication time based on comments from subcontractors and suppliers. The submittal activity is then linked to the installation activity accurately representing the date the critical activity can be installed. Construction Safety Safety of our clients, employees, and subcontractors is of paramount importance to us when setting up a job site. Elder will visually define its areas of work, and restrict access to people with appropriate personal protection equipment. Each worker goes through an onsite safety orientation with a member of Elder Construction Team prior to starting his work on the job site and is provided with an orientation pamphlet. This pamphlet is designed to be a quick reference guide and knowledge base for anyone on the jobsite. Orientation pamphlet provides information regarding • Emergency contact numbers • Site Layout Plan showing; access points, parking, laydown areas and do not enter locations • Elder Construction Safety Guidelines • Clients Safety Guidelines (City of Fort Collins) Safety Officers Jim Howard is Elder’s in house safety officer. David Wilson of Employers Resources of Colorado is Elder outside consultant for safety. The primary goals of the safety manager are: • Oversee implementation of the Elder Construction, Inc. safety program. • Annually review the Elder Construction, Inc. safety policy and safety rules. • Maintain accurate records and annually report the results of workplace accident and injury trend analysis. • Recommend actions to reduce the frequency and severity of accidents and illnesses. • Integrate safety into the day-to-day activities of all employees. • Coordinate the new employee orientation and safety training programs. • Assist Elder Construction, Inc. in compliance with government standards concerning safety and health. • Assist supervisors with accident investigation. Page 25 of 48 QUALITY INTEGRITY VALUE • Identify unsafe conditions and practices and determine remedies. Subcontractors Elder construction has been in business for over 20 years and over that time period, we have developed a successful working relationship with a number of subcontractors. In our relationships with our subcontractors, in our creative innovations that provide real value, in our deep commitment that goes above and beyond expectations, Elder exercises honesty and integrity in everything we do. Hiring a subcontractor is not just a partner in the construction process, but a partnership that turns it into a friendship that will last beyond the current project and well into the future. Because of this history and relationships, Elder has an extensive data base of subcontractors to solicit from. Below is a guide line of how we intend to select the list of subcontractors and vendors. Each subcontractor we select will provide a proposal package confirming they meet the requirements we set forth. We believed that these requirements will provide a comprehensive and complete list of the most qualified subcontractors to bid this project. We do encourage suggestions not only from the owner but also the architect on additional subcontractors; however, any requested subcontractor will have to meet the same requirements for review. Once bidding is complete the two low contractors will be interviewed to verify the content of their bid package and review the schedule and their manpower capabilities as it relates to the schedule. Proposal Requirements · Comparable Job Experience/ Current Work Load · Relationship with Elder · References Page 26 of 48 QUALITY INTEGRITY VALUE Tab 8 Guaranteed Maximum Price 8106 Fort Collins Utilites Vehicle Storage Facilities Step II GMP June 24, 2015 Total Project Notes General Conditions $ 114,073 Deisgn Fees $ 66,070 Preconstruction $ 5,000 Construction $ 1,122,029 Site Improvements $ - Included In Construction Above Off-Site Improvements $ - None Anticipated Equipment $ - Included In Construction Above Contingencies $ - See Below Estimate Totals $ 1,307,172 $ 3,200 $ 6,600 $ 3,900 $ 65,359 $ 27,725 $ 84,837.30 $ 191,620 $ 1,498,792 Overhead and Profit Total Indirect Costs Total GMP Pay & Performance Bond Description Total Direct Costs Building Plan Review Fee Building Permit Fire Dept Permit Const. Contingency Design Build Team Acknowledges receipt of the following documents from the City of Fort Collins • RPP – 8106 Fort Collins Utilities Vehicle Storage Facilities • Addendum No. 1 • Geotechnical Investigation provided by CTL Thomson dated May 19, 2015 • Vehicle Storage Building Utility Services Department Plans dated May 2005 Page 27 of 48 QUALITY INTEGRITY VALUE Suggested Project Alternate Pricing Refer to Basis of Design Section for full description. Alternates do not include additional general conditions. General conditions to be determined at the time of alternate selection based on impact to project schedule. Alternates Building 700 Light and Power Building Alternate # 1 Add $ 72,241.00 Building Alternate # 2 Add $ 20,929.00 Building Alternate # 3 Add $ 34,954.00 Plumbing – Alternate #1 Add $ 9,222.00 HVAC – System Alternate #1 Add $ 162,650.00 HVAC – System Alternate #2 Add $ 184,168.00 HVAC – Alternate 3 Add $ 10,547.00 HVAC – Alternate #4 Add $ 61,035.00 Electrical Alternate #1 Add $ 107,060.00 Alternates Building 701 Water Electrical Alternate #1 Add $ 107,060.00 General Condition Detail Superintendent Project Manager Project Assistant General Liability Insurance Plans Temp. Toilet Conex Rental - 20' Construction Office Monthly Rental Construction Office Setup/Remove Drinking Water Construction Office Internet Construction Office Utilities Construction Office Supplies Final Cleaning As-built Drawings & Record Keeping Design Fee Detail Civil Design Landscape Design Planning Documents Architectural Structural Mechanical and Plumbing Electrical Fire Protection Reimbursable Page 28 of 48 QUALITY INTEGRITY VALUE Contingency We have included a 5% construction contingency to account for level of current schematic design and current cost unpredictability in the market. Design/Build team is will to omit contingency to the cost saving split as outlined in the construction contract if awarded. Final contingency to be determined at final permit document pricing exercise. Hourly Rates Architect $115/hr. Construction Manager $95/hr. Preconstruction Manager $95/hr. Project Manager $90/hr. Site Superintendent $80/hr. Project Coordinator $45/hr. Carpenter $45/hr. Labor $30/hr. Page 29 of 48 ID Task Name Duration Start Finish Predecessors 0 2722N - Fort Collins Vehicle Storage - RFP Schedule 165 days Wed 6/24/15 Mon 2/15/16 1 Preconstruction 87 days Wed 6/24/15 Mon 10/26/15 2 Submit Proposal 0 days Wed 6/24/15 Wed 6/24/15 3 Award 0 days Mon 7/6/15 Mon 7/6/15 4 Confirm Design with City of Fort Collins 10 days Mon 7/6/15 Fri 7/17/15 3 6 Order Pre-Engineered Metal Building 0 days Fri 7/17/15 Fri 7/17/15 4 7 Complete Construction Documents 20 days Mon 7/20/15 Fri 8/14/15 4 8 Complete Structural Engineering and Building Documents 20 days Mon 7/20/15 Fri 8/14/15 6 9 Submit for Building Permit 0 days Fri 8/14/15 Fri 8/14/15 7,8 10 Plan Review Period 40 days Mon 8/17/15 Mon 10/12/15 9 11 Final Construction Pricing 15 days Mon 8/17/15 Fri 9/4/15 9 12 Permit Issued 0 days Mon 10/12/15 Mon 10/12/15 10 13 Mobilize Jobsite 1 day Tue 10/13/15 Tue 10/13/15 24FS-30 days,12 14 Submittals 35 days Mon 7/20/15 Fri 9/4/15 15 Metal Building 10 days Mon 7/20/15 Fri 7/31/15 6 16 Utilities 15 days Mon 8/17/15 Fri 9/4/15 7 17 Concrete and Reinforcing 10 days Mon 8/17/15 Fri 8/28/15 7 18 Garage Doors 10 days Mon 8/17/15 Fri 8/28/15 7 19 Masonry 10 days Mon 8/24/15 Fri 9/4/15 7FS+5 days 20 Mechanical 10 days Mon 8/24/15 Fri 9/4/15 7FS+5 days 21 Plumbing 10 days Mon 8/24/15 Fri 9/4/15 7FS+5 days 22 Electrical 10 days Mon 8/24/15 Fri 9/4/15 7FS+5 days 5 Submit Minor Amendment 10 days Mon 8/3/15 Fri 8/14/15 4FS+10 days 23 Lead Times 60 days Mon 8/3/15 Mon 10/26/15 24 Metal Building 60 days Mon 8/3/15 Mon 10/26/15 15 26 Concrete and Reinforcing 10 days Mon 8/31/15 Mon 9/14/15 17 27 Garage Doors 30 days Mon 8/31/15 Mon 10/12/15 18 25 Utilities 20 days Tue 9/8/15 Mon 10/5/15 16 28 Masonry 10 days Tue 9/8/15 Mon 9/21/15 19 29 Mechanical 20 days Tue 9/8/15 Mon 10/5/15 20 30 Plumbing 20 days Tue 9/8/15 Mon 10/5/15 21 31 Electrical 30 days Tue 9/8/15 Mon 10/19/15 22 32 Light and Power Building 87 days Wed 10/14/15 Mon 2/15/16 33 Site Demolition 2 days Wed 10/14/15 Thu 10/15/15 13 34 Site Utilities 5 days Fri 10/16/15 Thu 10/22/15 33 35 Foundation Excavation 3 days Fri 10/23/15 Tue 10/27/15 34 36 Form, Reinforced and Place Footings 3 days Wed 10/28/15 Fri 10/30/15 35 37 Form, Reinforced and Place Foundations 5 days Mon 11/2/15 Fri 11/6/15 36 38 Damproof and Insulation 1 day Mon 11/9/15 Mon 11/9/15 37 39 Backfill Foundation 2 days Tue 11/10/15 Wed 11/11/15 38 40 Install Underground 2 days Thu 11/12/15 Fri 11/13/15 39 41 Inspect Underground 1 day Mon 11/16/15 Mon 11/16/15 40 42 Form, Reinforce and Place Slab 3 days Tue 11/17/15 Thu 11/19/15 41 2722N - Fort Co C Preconstruction Submit Proposal Award Confirm Design with City of Fort Collins Order Pre-Engineered Metal Building Complete Construction Documents Complete Structural Engineering and Building Documents Submit for Building Permit Plan Review Period Final Construction Pricing Permit Issued Mobilize Jobsite Submittals Metal Building Utilities ID Task Name Duration Start Finish Predecessors 43 Erect Metal Building 25 days Fri 11/20/15 Mon 12/28/15 42,24 44 Place Bollards 2 days Tue 12/29/15 Wed 12/30/15 43 45 Place Site Concrete 3 days Thu 12/31/15 Mon 1/4/16 44 46 Install Masonry 4 days Tue 1/5/16 Fri 1/8/16 45 47 MEP Rough-ins 4 days Mon 1/11/16 Thu 1/14/16 46 48 MEP Inspections 1 day Fri 1/15/16 Fri 1/15/16 47 49 Install Liner Panels 3 days Mon 1/18/16 Wed 1/20/16 48 50 Install Garage Doors 5 days Thu 1/21/16 Wed 1/27/16 49 51 ECI Punch list 5 days Thu 1/28/16 Wed 2/3/16 50 52 Final Clean 2 days Thu 2/4/16 Fri 2/5/16 51 53 Final Inspections 1 day Mon 2/8/16 Mon 2/8/16 52 54 OAC Punch list 5 days Tue 2/9/16 Mon 2/15/16 53 55 Water Building 72 days Wed 10/28/15 Mon 2/8/16 56 Site Demolition 2 days Wed 10/28/15 Thu 10/29/15 35 57 Site Utilities 3 days Fri 10/30/15 Tue 11/3/15 56 58 Foundation Excavation 2 days Wed 11/4/15 Thu 11/5/15 57 59 Form, Reinforced and Place Footings 3 days Mon 11/9/15 Wed 11/11/15 58,37 60 Form, Reinforced and Place Foundations 5 days Thu 11/12/15 Wed 11/18/15 59 61 Damproof and Insulation 1 day Thu 11/19/15 Thu 11/19/15 60 62 Backfill Foundation 2 days Fri 11/20/15 Mon 11/23/15 61 63 Install Underground 1 day Tue 11/24/15 Tue 11/24/15 62 64 Inspect Underground 1 day Wed 11/25/15 Wed 11/25/15 63 65 Form, Reinforce and Place Slab 3 days Fri 11/27/15 Tue 12/1/15 64 66 Erect Metal Building 15 days Tue 12/29/15 Mon 1/18/16 65,43 67 Place Bollards 2 days Tue 1/19/16 Wed 1/20/16 66 68 Place Site Concrete 3 days Thu 1/21/16 Mon 1/25/16 67 69 MEP Rough-ins 1 day Tue 1/26/16 Tue 1/26/16 68 70 MEP Inspections 1 day Wed 1/27/16 Wed 1/27/16 69 71 ECI Punch list 3 days Thu 1/28/16 Mon 2/1/16 70 72 Final Clean 1 day Tue 2/2/16 Tue 2/2/16 71 73 Final Inspections 1 day Wed 2/3/16 Wed 2/3/16 72 74 OAC Punch list 3 days Thu 2/4/16 Mon 2/8/16 73 75 Owner Turnover 0 days Mon 2/15/16 Mon 2/15/16 54,74 Erect Metal Building Place Bollards Place Site Concrete Install Masonry MEP Rough-ins MEP Inspections Install Liner Panels Install Garage Doors ECI Punch list Final Clean Final Inspections OAC Punch list Water Building Site Demolition Site Utilities Foundation Excavation Form, Reinforced and Place Footings Form, Reinforced and Place Foundations Damproof and Insulation Backfill Foundation Install Underground Inspect Underground Form, Reinforce and Place Slab Erect Metal Building Place Bollards Place Site Concrete Page 32 of 48 Page 33 of 48 LOCHBUIE TOWN HALL PL1.3 01/30/13 LOCHBUIE, COLORADO 703 WELD COUNTY ROAD 37 LOCHBUIE TOWN HALL 703 WELD COUNTY ROAD 37 160 PALMER DRIVE, FORT COLLINS, COLORADO (970) 207-0424 LOCHBUIE, COLORADO SITE PLAN NORTH SITE PLAN MAY 5, 2015 SS0' 10' 15' 20' 30' 40' 60' Page 34 of 48 LOCHBUIE TOWN HALL PL1.3 01/30/13 LOCHBUIE, COLORADO 703 WELD COUNTY ROAD 37 LOCHBUIE TOWN HALL 703 WELD COUNTY ROAD 37 160 PALMER DRIVE, FORT COLLINS, COLORADO (970) 207-0424 LOCHBUIE, COLORADO SITE PLAN NORTH SITE PLAN MAY 5, 2015 SS0' 10' 15' 20' 30' 40' 60' 24" North Weld Water SS SS SS W W W 700 WOOD ST. L&P WA Page 35 of 48 LOCHBUIE TOWN HALL PL1.3 01/30/13 LOCHBUIE, COLORADO 703 WELD COUNTY ROAD 37 LOCHBUIE TOWN HALL 703 WELD COUNTY ROAD 37 160 PALMER DRIVE, FORT COLLINS, COLORADO (970) 207-0424 LOCHBUIE, COLORADO SITE PLAN NORTH SITE PLAN MAY 5, 2015 SS0' 10' 15' 20' 30' 40' 60' Page 36 of 48 162' - 0" 65' - 0" 2 A2.2 A2.2 4 A2.2 3 A2.2 1 1 2 3 4 5 6 7 D C B A TRENCH DRAIN TRENCH DRAIN TRENCH DRAIN F1 SLOPE DN P1 W8 29' - 0" 26' - 0" 26' - 0" 26' - 0" 26' - 0" 29' - 0" 21' - 8" 21' - 8" 21' - 8" 3.02 3.02 3.02 3.02 C8 6.01 6.01 6.01 6.01 6.01 6.01 6.02 6.02 6.02 6.02 6.02 6.02 6.03 6.03 GARAGE 101 NEW 6" CONCRETE SLAB EXISTING CONCRETE PAVEMENT EXISTING CONCRETE PAVEMENT F1 F1 P2 P2 SYSTEM NOTES- INTERIOR WALLS DESIGNATION DESCRIPTION W8 PRE-FINISHED INSULATED R-45.5 METAL WALL PANEL OVER METAL GIRTS & PEMB. STRUCTURE. W12 4" CONCRETE MASONRY UNIT VENEER OVER 2” (R-10) RIGID INSULATION AND REINFORCED CONCRETE WALL, (REF: STRUCTURAL) SYSTEM NOTES- FLOORS DESIGNATION DESCRIPTION 6" REINFORCED CONCRETE SLAB ON COMPACTED 4” FILL, (REF: STR'L) F1 P1 EXISTING CONCRETE PAVEMENT P2 4” CONCRETE WALKS ON COMPACTED GRADE SYSTEM NOTES- ROOFS DESIGNATION DESCRIPTION R1 PRE-FINISHED STANDING SEAM INSULATED R-38 METAL ROOF OVER PEMB. STRUCTURE FLOOR PLAN 100' - 0" T.O. ROOF 119' - 5" B.O. ROOF 114' - 0" 1 2 3 4 5 6 7 2" R1 5.01 W8 W2 6.02 6.02 6.02 3.01 3.02 3.02 3.02 3.02 5.01 29' - 0" 26' - 0" 26' - 0" 26' - 0" 26' - 0" 29' - 0" 3.03 FLOOR PLAN 100' - 0" T.O. ROOF 119' - 5" B.O. ROOF 114' - 0" A B C D 12 1 8" 8" 6.03 3.01 3.02 3.02 R1 5.01 2" W8 21' - 8" 21' - 8" 21' - 8" 3.03 FLOOR PLAN 100' - 0" T.O. ROOF 119' - 5" B.O. ROOF 114' - 0" D C B A 112 21' - 8" 21' - 8" 21' - 8" 8" 8" W8 5.01 3.01 3.02 3.02 6.03 R1 2" 3.03 FLOOR PLAN 100' - 0" T.O. ROOF 119' - 5" B.O. ROOF 114' - 0" 7 6 5 4 3 2 1 1 A2.2 A2.2 A2.2 A2.2 2 3 4 160' - 0" 28' - 0" 26' - 0" 26' - 0" 26' - 0" 26' - 0" 28' - 0" 35' - 0" 1 2 3 A B C D E F G 3.02 3.02 3.02 P1 P2 P3 P1 P1 P1 P3 P2 GARAGE 101 5 A2.2 NEW 6" CONCRETE SLAB EXISTING CONCRETE PAVEMENT EXISTING GRAVEL ON GRADE SYSTEM NOTES- ROOFS DESIGNATION DESCRIPTION R1 PRE-FINISHED STANDING SEAM R-38 METAL ROOF OVER PEMB. STRUCTURE SYSTEM NOTES- CEILINGS DESIGNATION DESCRIPTION C1 EXPOSED PRE-FINISHED METAL ROOF PANEL C2 EXPOSED STRUCTURE SYSTEM NOTES- INTERIOR WALLS DESIGNATION DESCRIPTION W8 PRE-FINISHED INSULATED METAL WALL PANEL, R-45.5 OVER METAL GIRTS & PEMB. STRUCTURE. PROVIDE THERMAL BRIDGING SEPARATION AIR/WATER ENVELOPE BARRIER SYSTEM NOTES- FLOORS DESIGNATION DESCRIPTION P1 EXISTING GRAVEL ON GRADE P2 6” REINFORCED CONCRETE PAVEMENT ON COMPACTED GRADE P3 EXISTING CONCRETE PAVEMENT TO REMAIN, PATCH & REPAIR AS NEEDED 1 A2.2 A2.2 A2.2 ROOF BEARING 114' - 0" FLOOR PLAN 100' - 0" T.O. ROOF 118' - 6" G F E D C B A 3.01 3.01 3.02 3.02 5.01 5.02 5.02 5.03 W8 W8 R1 ROOF BEARING 114' - 0" FLOOR PLAN 100' - 0" T.O. ROOF 118' - 6" 3 2 1 3.01 3.01 3.02 5.01 W8 R1 1 12 ROOF BEARING 114' - 0" FLOOR PLAN 100' - 0" T.O. ROOF 118' - 6" A B C D E F G 3.01 3.01 6.04 W8 R1 ROOF BEARING 114' - 0" FLOOR PLAN 100' - 0" T.O. ROOF 118' - 6" 1 2 3 3.01 3.01 3.02 5.01 W8 R1 12 1 SYSTEM NOTES- ROOFS DESIGNATION DESCRIPTION R1 PRE-FINISHED STANDING SEAM R-38 METAL ROOF OVER PEMB. STRUCTURE SYSTEM NOTES- CEILINGS DESIGNATION DESCRIPTION C1 EXPOSED PRE-FINISHED METAL ROOF PANEL C2 EXPOSED STRUCTURE Fort Collins Vehicle Services ALTERNATE DESIGN OPTIONS Water Services 701 Wood Street Light & Power Services 700 Wood Street RFP: #8106 6.24.15 Page 41 of 48 THE SITE Light & Power Services 700 Wood Street Water Services 701 Wood Street Elm Street RFP: #8106 6.24.15 Page 42 of 48 THE VISION RFP: #8106 6.24.15 Page 43 of 48 CONCRETE WITH RECYCLED HIGH FLY-ASH CONTENT RECLAIMED BRICK PAVER BLOCKS FOR STORMWATER MANAGEMENT ROOF DOWNSPOUTS TO PROVIDE WATER TO XERISCAPE LANDSCAPE LIVING WALL PANELS OF IVY TO CREATE ORGANIC ARCHITECTURE ON-SITE ELECTRICITY PRODUCTION THROUGH PHOTOVOLTAICS PORTION OF ON-SITE P.V. ELECTRICITY TO CONTRIBUTE TO CAR CHARGING STATIONS SUN SCREEN TO CONTROL DAYLIGHTING AND MAINTAIN BUILDING COOLING RFP: #8106 THERMAL CHIMNEY TO PROVIDE PASSIVE HEAT EXHAUST 6.24.15 Light & Power Services, 700 Wood Street Page 44 of 48 ON-SITE ELECTRICITY PRODUCTION THROUGH PHOTOVOLTAICS RFP: #8106 6.24.15 Water Services, 701 Wood Street WEST DAYLIGHTING TRANSOMS PASSIVE IRRIGATION DRAINS TO THE WEST – PROVIDES LANDSCAPE SCREENING TO ADJACENT RESIDENTIAL USES EXISTING GRAVEL – L.I.D. STORMWATER MITIGATION Page 45 of 48 POSSIBLE GREEN FEATURES RFP: #8106 6.24.15 Page 46 of 48 RFP: #8106 6.24.15 Light & Power Services 700 Wood Street Page 47 of 48 RFP: #8106 6.24.15 Water Services 701 Wood Street Page 48 of 48 SYSTEM NOTES- INTERIOR WALLS DESIGNATION DESCRIPTION W8 PRE-FINISHED INSULATED METAL WALL PANEL, R-45.5 OVER METAL GIRTS & PEMB. STRUCTURE. PROVIDE THERMAL BRIDGING SEPARATION AIR/WATER ENVELOPE BARRIER SYSTEM NOTES- FLOORS DESIGNATION DESCRIPTION P1 EXISTING GRAVEL ON GRADE P2 6” REINFORCED CONCRETE PAVEMENT ON COMPACTED GRADE P3 EXISTING CONCRETE PAVEMENT TO REMAIN, PATCH & REPAIR AS NEEDED PRE-FINISHED METAL WALL PANEL (3 SIDES) (BEYOND) PRE-FINISHED STANDING SEAM METAL ROOF NEW 6" REINFORCED CONCRETE SLAB-ON-GRADE REINFORCED CONCRETE FOOTING & FOUNDATIONS STEEL/CONCRETE BOLLARDS ROOF BEARING 114' - 0" FLOOR PLAN 100' - 0" T.O. ROOF 118' - 6" 3.01 3.01 3.02 5.02 5.03 5.01 6.04 GARAGE 101 G F E D C B A R1 3.01 3.01 5.02 5.02 5.03 5.03 GARAGE 101 GARAGE 101 14' - 0" 18' - 6" EXISTING CONC. NEW 6" CONC. SLAB-ON-GRADE PVMT. SHEET NUMBER SHEET NAME ISSUE DATE REVISIONS CHECKED BY JOB NUMBER DRAWN BY THESE PLANS ARE COPYRIGHTED AND ARE SUBJECT TO COPYRIGHT PROTECTION AS AN 'ARCHITECTURAL WORK' UNDER THE COPYRIGHT PROTECTION ACT OF 1990. - ALL CONSTRUCTION SHALL CONFORM TO CURRENT UNIFORM BUILDING CODE AND ALL OTHER APPLICABLE CODES. - DO NOT SCALE DRAWINGS FOR DIMENSIONS. CONSTRUCTION MANAGERS, SUB- CONTRACTORS AND ALL OTHER SUPPLIERS TO THIS PROJECT, HAVE THE COMPLETE RESPONSIBILITY TO NOTIFY ENGINEERS, ARCHITECTS AND ALL OTHER DESIGN PROFESSIONALS OF ANY DIS- CREPANCIES, CONFLICTS, BUILDING OR OTHER CODE REQUIREMENTS AS REP- RESENTED BY THESE CONSTRUCTION DOCUMENTS. ANY PROFESSIONAL LIABILITY CLAIMS SHALL BE LIMITED TO THE EXTENT OF SAID DESIGNERS FEE, ONLY AND IS HEREBY RECOGNIZED AS SUCH BY ANY CLAIMANTS, OWNERS, LIEN HOLDERS OR OTHERS. 701 WOOD STREET FORT COLLINS, COLORADO A2.2 ELEVATIONS 6.24.15 SJS SKF Project Number CITY OF FORT COLLINS WOOD STREET VEHICLE STORAGE - WATER SERVICES A2.2 1/16" = 1'-0" 1 EAST ELEVATION A2.2 1/16" = 1'-0" 2 NORTH ELEVATION A2.2 1/16" = 1'-0" 3 WEST ELEVATION A2.2 1/16" = 1'-0" 4 SOUTH ELEVATION KEY NOTES NO. DESCRIPTION 3.01 REINFORCED CONCRETE FOOTINGS & FOUNDATIONS, (REF: STRUCTURAL) 3.02 CONCRETE BOLLARDS (REF: STRUCTRUAL) 5.01 PRE-FINISHED METAL TRIM, EAVE/FASCIA FLASHING, GUTTERS & DOWNSPOUTS 5.02 PEMB. MAIN FRAME 5.03 PEMB METAL PURLIN OR GIRTS 6.04 CONTINUOUS POLYCARBONATE TRANSOM PANELS 26.01 LIGHTING - (REF: ELECTRICAL) A2.2 1/8" = 1'-0" 5 PARTIAL EAST ELEVATION DETAILS A2.2 1/16" = 1'-0" 6 WEST-EAST SECTION A2.2 1/16" = 1'-0" 7 SOUTH-NORTH SECTION A2.2 1/8" = 1'-0" 8 WEST-EAST SECTION DETAILS Page 40 of 48 A2.2 2 3 4 1 2 3 A B C D E F G 5.02 5.02 5.02 5.03 5.03 5.03 5.03 C2 C1 5 A2.2 EXPOSED METAL ROOF (SOFFIT) 1 A2.2 A2.2 A2.2 A2.2 2 3 4 1 2 3 A B C D E F G 5.01 1/12 5 A2.2 P.F. METAL FLASHING, GUTTER, AND DOWNSPOUT POSSIBLE PV SYSTEM LAYOUT 24" NORTH WELD WATER EXISTING MAINT. BLD'G. EXISTING CONC. PVMT. PROPOSED WATER BUILDING 160' 35' SHEET NUMBER SHEET NAME ISSUE DATE REVISIONS CHECKED BY JOB NUMBER DRAWN BY THESE PLANS ARE COPYRIGHTED AND ARE SUBJECT TO COPYRIGHT PROTECTION AS AN 'ARCHITECTURAL WORK' UNDER THE COPYRIGHT PROTECTION ACT OF 1990. - ALL CONSTRUCTION SHALL CONFORM TO CURRENT UNIFORM BUILDING CODE AND ALL OTHER APPLICABLE CODES. - DO NOT SCALE DRAWINGS FOR DIMENSIONS. CONSTRUCTION MANAGERS, SUB- CONTRACTORS AND ALL OTHER SUPPLIERS TO THIS PROJECT, HAVE THE COMPLETE RESPONSIBILITY TO NOTIFY ENGINEERS, ARCHITECTS AND ALL OTHER DESIGN PROFESSIONALS OF ANY DIS- CREPANCIES, CONFLICTS, BUILDING OR OTHER CODE REQUIREMENTS AS REP- RESENTED BY THESE CONSTRUCTION DOCUMENTS. ANY PROFESSIONAL LIABILITY CLAIMS SHALL BE LIMITED TO THE EXTENT OF SAID DESIGNERS FEE, ONLY AND IS HEREBY RECOGNIZED AS SUCH BY ANY CLAIMANTS, OWNERS, LIEN HOLDERS OR OTHERS. 701 WOOD STREET FORT COLLINS, COLORADO A2.1 FLOOR PLAN 6.24.15 SJS SKF Project Number CITY OF FORT COLLINS WOOD STREET VEHICLE STORAGE - WATER SERVICES NORTH A2.1 1/16" = 1'-0" 2 FLOOR PLAN KEY NOTES NO. DESCRIPTION 3.01 REINFORCED CONCRETE FOOTINGS & FOUNDATIONS, (REF: STRUCTURAL) 3.02 CONCRETE BOLLARDS (REF: STRUCTRUAL) 5.01 PRE-FINISHED METAL TRIM, EAVE/FASCIA FLASHING, GUTTERS & DOWNSPOUTS 5.02 PEMB. MAIN FRAME 5.03 PEMB METAL PURLIN OR GIRTS 6.04 CONTINUOUS POLYCARBONATE TRANSOM PANELS 26.01 LIGHTING - (REF: ELECTRICAL) A2.1 1/16" = 1'-0" 1 RCP A2.1 1/16" = 1'-0" 3 ROOF PLAN A2.1 1" = 30'-0" 4 SITE Page 39 of 48 W8 R1 3.02 3.02 3.01 3.02 3.02 6.01 6.01 6.01 W8 3.03 6.04 6.04 6.04 SYSTEM NOTES- ROOFS DESIGNATION DESCRIPTION R1 PRE-FINISHED STANDING SEAM INSULATED R-38 METAL ROOF OVER PEMB. STRUCTURE SYSTEM NOTES- CEILINGS DESIGNATION DESCRIPTION C1 EXPOSED PRE-FINISHED METAL ROOF PANEL, Min. (R-30)" OVER PEMB. STRUCTURE C2 EXPOSED STRUCTURE SYSTEM NOTES- INTERIOR WALLS DESIGNATION DESCRIPTION W8 PRE-FINISHED INSULATED R-45.5 METAL WALL PANEL OVER METAL GIRTS & PEMB. STRUCTURE. W12 4" CONCRETE MASONRY UNIT VENEER OVER 2” (R-10) RIGID INSULATION AND REINFORCED CONCRETE WALL, (REF: STRUCTURAL) SYSTEM NOTES- FLOORS DESIGNATION DESCRIPTION 6" REINFORCED CONCRETE SLAB ON COMPACTED 4” FILL, (REF: STR'L) F1 P1 EXISTING CONCRETE PAVEMENT P2 4” CONCRETE WALKS ON COMPACTED GRADE PRE-FINISHED STANDING SEAM INSULATED METAL ROOF PRE-FINISHED INSULATED METAL WALL PANEL INSULATED GLASS GARAGE DOOR CONCRETE MASONRY UNIT VENEER NEW 6" REINFORCED CONCRETE SLAB-ON-GRADE REINFORCED CONCRETE FOOTING & FOUNDATIONS STEEL/CONCRETE BOLLARDS PRE-FINISHED METAL FASCIA, GUTTER, & DOWNSPOUT FLOOR PLAN 100' - 0" T.O. ROOF 119' - 5" B.O. ROOF 114' - 0" A B C D F1 R1 6.04 W8 6.01 6.02 5.02 5.03 3.01 3.02 3.03 5.02 5.02 7.01 19' - 5" 14' - 0" GARAGE 101 LOW 'E' TRANSOM WINDOWS F1 F1 F1 FLOOR PLAN 100' - 0" 1 2 3 4 5 6 7 6.01 6.01 6.01 R1 W8 3.01 3.03 SHEET NUMBER SHEET NAME ISSUE DATE REVISIONS CHECKED BY JOB NUMBER DRAWN BY THESE PLANS ARE COPYRIGHTED AND ARE SUBJECT TO COPYRIGHT PROTECTION AS AN 'ARCHITECTURAL WORK' UNDER THE COPYRIGHT PROTECTION ACT OF 1990. - ALL CONSTRUCTION SHALL CONFORM TO CURRENT UNIFORM BUILDING CODE AND ALL OTHER APPLICABLE CODES. - DO NOT SCALE DRAWINGS FOR DIMENSIONS. CONSTRUCTION MANAGERS, SUB- CONTRACTORS AND ALL OTHER SUPPLIERS TO THIS PROJECT, HAVE THE COMPLETE RESPONSIBILITY TO NOTIFY ENGINEERS, ARCHITECTS AND ALL OTHER DESIGN PROFESSIONALS OF ANY DIS- CREPANCIES, CONFLICTS, BUILDING OR OTHER CODE REQUIREMENTS AS REP- RESENTED BY THESE CONSTRUCTION DOCUMENTS. ANY PROFESSIONAL LIABILITY CLAIMS SHALL BE LIMITED TO THE EXTENT OF SAID DESIGNERS FEE, ONLY AND IS HEREBY RECOGNIZED AS SUCH BY ANY CLAIMANTS, OWNERS, LIEN HOLDERS OR OTHERS. 700 WOOD STREET FORT COLLINS, COLORADO A2.2 ELEVATIONS 6.24.15 SJS JDT Project Number CITY OF FORT COLLINS WOOD STREET VEHICLE STORAGE - LIGHT & POWER A2.2 1/16" = 1'-0" 1 SOUTH ELEVATION A2.2 1/16" = 1'-0" 2 EAST ELEVATION A2.2 1/16" = 1'-0" 3 WEST ELEVATION A2.2 1/16" = 1'-0" 4 NORTH ELEVATION KEY NOTES NO. DESCRIPTION 3.01 CONCRETE FOUNDATION, (REF: STRUCTRUAL) 3.02 PRECAST CONCRETE BOLLARDS (REF: STRUCTRUAL) 3.03 2' X 4" CONCRETE VENEER OVER 2' X 8" CAST-IN-PLACE CONCRETE WALL 5.01 PRE-FINISHED METAL FLASHING, GUTTERS & DOWNSPOUTS 5.02 MAIN FRAME RAFTER 5.03 P.F. METAL PURLIN 6.01 12' X 22' 6-PANEL P.F. METAL GARAGE DOOR W/ VISION PANELS 6.02 12' X 22' 6-PANEL INSULATED GLASS GARAGE DOOR 6.03 3' X 7' INSULATED P.F. METAL DOOR W/ VISION PANELS 6.04 (x4) 5'-6" X 2'-0" LOW 'E' TRANSOM WINDOW 7.01 CONTINUOUS RIDGE CAP 22.01 FLOOR DRAIN -( REF: PLUMBING DRWG) 23.01 ROOF PENETRATION - (REF: MECHANICAL) 26.01 LIGHTING - (REF: ELECTRICAL) A2.2 1/8" = 1'-0" 5 PARTIAL SOUTH ELEVATION DETAILS A2.2 1/16" = 1'-0" 6 SOUTH-NORTH BUILDING SECTION A2.2 1/8" = 1'-0" 7 SOUTH-NORTH BUILDING SECTION DETAILS A2.2 1/16" = 1'-0" 8 WEST-EAST BUILDING SECTION Page 38 of 48 SYSTEM NOTES- CEILINGS DESIGNATION DESCRIPTION C1 EXPOSED PRE-FINISHED METAL ROOF PANEL, Min. (R-30)" OVER PEMB. STRUCTURE C2 EXPOSED STRUCTURE 1. NOTIFY ARCHITECT IMMEDIATELY WITH ANY DISCREPENCIES REGARDING THE CONTRACT DOCUMENTS. 2. VERIFY ALL EXISTING AND FIELD CONDITIONS, PRIOR TO ANY WORK INITIATION. 3. ALL WALLS TO BE W8 UNLESS OTHERWISE NOTED. 4. ALL DIMENSIONS ARE TO GRID LINES, FACE OF FRAMING UNLESS NOTED OTHERWISE. GENERAL NOTES 24" NORTH WELD WATER PROPOSED L&P BUILDING 162' 65' SHEET NUMBER SHEET NAME ISSUE DATE REVISIONS CHECKED BY JOB NUMBER DRAWN BY THESE PLANS ARE COPYRIGHTED AND ARE SUBJECT TO COPYRIGHT PROTECTION AS AN 'ARCHITECTURAL WORK' UNDER THE COPYRIGHT PROTECTION ACT OF 1990. - ALL CONSTRUCTION SHALL CONFORM TO CURRENT UNIFORM BUILDING CODE AND ALL OTHER APPLICABLE CODES. - DO NOT SCALE DRAWINGS FOR DIMENSIONS. CONSTRUCTION MANAGERS, SUB- CONTRACTORS AND ALL OTHER SUPPLIERS TO THIS PROJECT, HAVE THE COMPLETE RESPONSIBILITY TO NOTIFY ENGINEERS, ARCHITECTS AND ALL OTHER DESIGN PROFESSIONALS OF ANY DIS- CREPANCIES, CONFLICTS, BUILDING OR OTHER CODE REQUIREMENTS AS REP- RESENTED BY THESE CONSTRUCTION DOCUMENTS. ANY PROFESSIONAL LIABILITY CLAIMS SHALL BE LIMITED TO THE EXTENT OF SAID DESIGNERS FEE, ONLY AND IS HEREBY RECOGNIZED AS SUCH BY ANY CLAIMANTS, OWNERS, LIEN HOLDERS OR OTHERS. 700 WOOD STREET FORT COLLINS, COLORADO A2.1 FLOOR PLAN 6.24.15 SJS JDT Project Number CITY OF FORT COLLINS WOOD STREET VEHICLE STORAGE - LIGHT & POWER NORTH A2.1 1/16" = 1'-0" 1 FLOOR PLAN KEY NOTES NO. DESCRIPTION 3.01 CONCRETE FOUNDATION, (REF: STRUCTRUAL) 3.02 PRECAST CONCRETE BOLLARDS (REF: STRUCTRUAL) 3.03 2' X 4" CONCRETE VENEER OVER 2' X 8" CAST-IN-PLACE CONCRETE WALL 5.01 PRE-FINISHED METAL FLASHING, GUTTERS & DOWNSPOUTS 5.02 MAIN FRAME RAFTER 5.03 P.F. METAL PURLIN 6.01 12' X 22' 6-PANEL P.F. METAL GARAGE DOOR W/ VISION PANELS 6.02 12' X 22' 6-PANEL INSULATED GLASS GARAGE DOOR 6.03 3' X 7' INSULATED P.F. METAL DOOR W/ VISION PANELS 6.04 (x4) 5'-6" X 2'-0" LOW 'E' TRANSOM WINDOW 7.01 CONTINUOUS RIDGE CAP 22.01 FLOOR DRAIN -( REF: PLUMBING DRWG) 23.01 ROOF PENETRATION - (REF: MECHANICAL) 26.01 LIGHTING - (REF: ELECTRICAL) A2.1 1" = 30'-0" 2 SITE NORTH Page 37 of 48 MEP Rough-ins MEP Inspections ECI Punch list Final Clean Final Inspections OAC Punch list Owner Turnov Jun Jul Aug Sep Oct Nov Dec Jan Feb Qtr 3, 2015 Qtr 4, 2015 Qtr 1, 2016 Task Milestone Summary Project Summary Critical Completed In Progress Project: 2722N - Fort Collins Vehicle Storage - RFP Schedule Date: Wed 6/24/15 Page 2 Page 31 of 48 Concrete and Reinforcing Garage Doors Masonry Mechanical Plumbing Electrical Submit Minor Amendment Lead Times Metal Building Concrete and Reinforcing Garage Doors Utilities Masonry Mechanical Plumbing Electrical Light and Powe Site Demolition Site Utilities Foundation Excavation Form, Reinforced and Place Footings Form, Reinforced and Place Foundations Damproof and Insulation Backfill Foundation Install Underground Inspect Underground Form, Reinforce and Place Slab Jun Jul Aug Sep Oct Nov Dec Jan Feb Qtr 3, 2015 Qtr 4, 2015 Qtr 1, 2016 Task Milestone Summary Project Summary Critical Completed In Progress Project: 2722N - Fort Collins Vehicle Storage - RFP Schedule Date: Wed 6/24/15 Page 1 Page 30 of 48 Fort Collins, Colorado Page 21 of 48 Cathedral Home for Children Wahoos’ Fish Tacos RV America Dr. Dhupar Office and Rehab Center Page 20 of 48 Endodontic of the Rockies Advanced Dental Jonathan Nelson, DDS Dr. Walton DDS Page 19 of 48 • Pioneer Charter School, Expeditionary Learning/Outward Bound High School, Fort Collins, CO; designed to Silver LEED specifications; 26,333 sf • Nederland Community Center, Nederland, CO; community center, theater, offices; LEED Gold certified; 40,000 sf • Sister Mary Alice Murphy Center for Hope, Fort Collins, CO; United Way resource center and offices; LEED-NC Silver Certified; 10,000 sf • Peloton Cycles, Fort Collins, CO; Retail & Office Building; LEED-NC Gold Certification pending; 14,000 sf • Carter Lake Marina, Loveland, CO; 4,500 sf Page 17 of 48