Jefferson Street Roadway and Multimodal Improvements
FIR Design
Description:
Interwest with assistance from the Team (BHA Design, Larsen Structural Design, Hines Inc.,
and Clanton & Associates) will coordinate with Engineering to complete the design plans and
documents for the Jefferson Street Roadway and Multimodal Improvements from North College
Avenue south to Mountain Ave./Lincoln Ave. for a Field Inspection Review (FIR) submittal to
the Colorado Department of Transportation (CDOT). This corridor has been studied and a
preferred roadway geometry has been documented and accepted by the City Council and CDOT
through an Intergovernmental Agreement and formal adoption in the US 287/SH 14 Access
Management Report. More than likely, one minor change to the preferred roadway geometry will
occur. As required by the Poudre Fire Authority, the medians will be broken up and become
pocket medians instead of extending along the project corridor as in the preferred roadway
geometry.
As part of this project, eight (8) street improvement projects have been identified along Jefferson
Street for the improvements. These improvements include:
Jefferson Street Parking Lot
Jefferson Park and Rodizio Frontage
Southwest side of Jefferson Street (N. College Ave. to Linden St.)
Both sides of Jefferson Street (Linden St. to Lincoln Ave.)
Pocket Medians (N. College Ave. to Linden St.)
Lincoln St. & Jefferson St. Intersection
Coordination of Future Utility Improvements (designed and constructed by
others)
Right-of-Way Acquisitions (under separate work order)
The following is a detailed explanation of each team member’s responsibility to complete this
improvement project for a FIR submission to the CDOT:
Tasks:
1. Base Map Preparation – Now that the improvements have been identified for the
roadway and multimodal street improvement project, Interwest will review all the
existing baseline information that was used for the Conceptual Design study and compile
it into a single project base map. This will include existing topographic survey, property
information, existing utility information and utility master plans. If additional survey is
required for this task, it will be provided by the City Survey Department. This task will
result in a base map that will be used for the project throughout the design and any
project displays/exhibits and deliverables that may be necessary.
2. Roadway Preliminary Layout (20% Design) – Interwest will prepare a preliminary
layout of the roadway and medians which will be presented to the City for their approval.
November 10, 2015
2
3. Roadway FIR Plans (60% Design) –After approval of the preliminary layout, Interwest
will move to the FIR Design of the roadway plans. Interwest will prepare FIR plans in
CDOT format, FIR Cost Estimate, and a drainage report for submittal to the City and
CDOT. The FIR plan set will include roadway and median plans and grading plans. The
Roadway FIR plans will include the following:
1. Cover Sheet
2. General Notes
3. Standard Plans Sheet
4. Survey Control Diagram
5. Ownership Map
6. Typical Roadway Sections
7. Demolition Plan
8. Roadway & Curb Plan and Profile
9. Preliminary Grading Plan
10. Cross Sections at 50’ intervals
11. Conceptual Phasing
12. Future Utility Improvements (For Information Only and designed by others)
4. Public Input & Meetings/Project Coordination – Interwest will meet with city staff
and stakeholders to obtain input on the roadway and multimodal improvements and the
urban design exhibits. We will provide appropriate displays to facilitate plan input, will
collect comments and will prepare meeting minutes of discussions. We anticipate the
following input meetings:
City departments including Poudre Fire Authority, FCMoves, Planning, Art in
Public Places staff, Historic Preservation staff (10 meetings)
Open House – to share input findings and obtain additional design input (1
meetings)
City Utilities – to clarify what City Utilities is designing on their potential utility
project within our project limits (5 meetings)
FIR design review meeting with City and CDOT personnel (1 meetings)
Public Artist (2 meetings)
Downtown Development Authority Board Meeting (1 meetings)
Transportation Board (1 meeting)
City Council (1 meeting)
5. Urban Design Exhibits – BHA Design Inc. (BHA) will provide the urban design
elements for this project corridor. BHA will provide the City with two (2) urban
design/gateway concepts and two (2) sidewalk and median urban design concepts
referencing the Downtown River District Plan and incorporating the Old Town
characteristics. This task will include renderings requested by the City and any other
exhibits necessary for the roadway and multimodal improvements along Jefferson Street.
6. Urban Design Preliminary (20% Design) – BHA will prepare preliminary urban design
enhancements for the roadway and medians which will be presented to the City for their
approval. This task will include preliminary base map illustrating urban design
improvements, site plans, landscape plans, construction details and a cost estimate.
November 10, 2015
3
7. Urban Design FIR Plans (60% Design) –After approval of the preliminary urban design
enhancements, BHA will prepare FIR plans in CDOT format, cost estimate, and
preliminary special conditions for submittal to the City and CDOT. The Urban Design
FIR plans will include the following:
1. Site Plans
2. Layout Plans
3. Landscape Plans
4. Planting Details
5. Site Construction Details
6. Regulatory Sign Details (Sign Plans by others)
7. Preliminary Summary of Quantities
8. Public Input & Meetings/Project Coordination – BHA will meet with city staff and
stakeholders to obtain input on the roadway and multimodal improvements and the urban
design exhibits. BHA will provide appropriate displays to facilitate plan input and
anticipate the following input meetings:
City departments including Poudre Fire Authority, FCMoves, Planning, Art in
Public Places staff, Historic Preservation staff (10 meetings)
Open House – to share input findings and obtain additional design input (1
meetings)
City Utilities – to clarify what City Utilities is designing on their potential utility
project within our project limits (5 meetings)
FIR design review meeting with City and CDOT personnel (1 meetings)
Public Artist (2 meetings)
Downtown Development Authority Board Meeting (1 meetings)
Transportation Board (1 meeting)
City Council (1 meeting)
9. Structural Design – Larsen Structural Design (Larsen) will provide the structural
services for this project. It is anticipated structural design and details will be needed for
the urban design enhancements along Jefferson Street. Larsen will provide the design
plans, cost estimate, and details as necessary for FIR submission.
10. Irrigation Preliminary Layout (20%) – Hines Inc. (Hines) will provide the irrigation
improvements for this project. Hines will prepare the preliminary irrigation design for
the roadway and medians enhancements which will be presented to the City for their
approval. This task includes the verification of existing conditions and the preliminary
irrigation design. As part of the verification of existing conditions Hines will:
Visit the site to verify existing site conditions for planning future irrigation system
requirements and equipment preferences.
Determine point-of-connection (POC) location(s), available pressure, and size in
coordination with the Civil Engineer (CE) or Landscape Architect (LA) prior to
design.
Will coordinate the mainline and wire routing, as well as the controller location(s)
and power requirements with the CE and LA, as necessary.
November 10, 2015
4
If the project site limits of construction require modifications to existing irrigation
systems Hines will meet with a Representative of those specific sites to confirm
the location of the existing irrigation water tap location(s), mainline size and
location, controller size, and the type and location of sprinkler heads or drip
irrigation equipment.
Obtain and adhere to City of Fort Collins irrigation design standards and CDOT
irrigation design standards.
Obtain As-built drawings if available to document any existing system equipment
types, sizes, capacity, location, and pipe routing.
Attend one (1) visit to the site and two (2) design/coordination meetings
As part of the preliminary irrigation design, Hines will develop a set of drawings that
show proposed irrigation water source(s), mainline pipe routing, isolation valve locations,
pipe and wiring sleeves under hardscapes, and controller location(s) with electrical power
drop requirements (master plan design will be based upon the landscape improvements
recommended for this project). In addition, Hines will include construction details,
specifications, and attend two (2) design/coordination meetings for the preliminary
irrigation design.
11. Irrigation FIR Plans (60% Design) – After approval of the preliminary layout, Hines
will prepare FIR plans in CDOT format showing proposed irrigation water source(s),
mainline pipe routing, isolation valve locations, pipe and wiring sleeves under
hardscapes, and controller location(s) with electrical power drop requirements (master
plan design will be based upon the landscape improvements recommended for this
project). In addition, FIR Design construction details, specifications and a cost estimate
will be prepared for submission to the City and CDOT. Hines will attend the FIR design
meeting and coordinate with the City and other design team members
12. Electrical Preliminary Layout (20%) – Clanton & Associates (Clanton) will provide
the electrical and lighting improvements for this project. Clanton will prepare the
preliminary electrical and lighting design enhancements for the roadway and medians
which will be presented to the City for their approval. This task will include:
Preliminary pedestrian lighting concepts
Preliminary parking lot lighting concepts
Proposed luminaire types
Kick-off meeting in Fort Collins
Design meeting in Fort Collins
Utility coordination meeting in Fort Collins
13. Electrical FIR Plans (60% Design) – After approval of the preliminary layout, Clanton
will provide FIR level plans in CDOT format and cost estimate for submittal to the City
and CDOT. Clanton will attend the FIR design meeting and coordinate with the City and
other design team members. This task will include:
FIR Design parking lot lighting layout
FIR Design luminaire selection
Catalog cut sheets of proposed lighting equipment
November 10, 2015
5
FIR Design lighting calculations
FIR Design lighting specifications
Utility coordination
Irrigation power feed coordination
Preliminary electrical engineering
FIR Design cost analysis
Two design meetings in Fort Collins
Utility coordination meeting in Fort Collins
Schedule
It is anticipated the FIR Plan submissions will be in mid 2016.
Assumptions
1. ROW Plans and Clearances will be in a separate work order.
2. Services after FIR approval will be in a separate work order.
3. All plans will be prepared on 11” x 17” plan sheets in CDOT format.
4. City review prior to the FIR 60% submittal will be a continuous process (during meetings
and via document sharing). The goal of the team is to move to the FIR 60% milestone
without a formal submittal and review period.
5. Utilities will be relocated as part of the Utility Improvements for the River District which
will be designed by the City of Fort Collins Utility Department.
6. Signal modifications will be designed by the City.
7. Landscape and urban design improvements will be limited to areas within the public
right-of-way.
8. Improvements to Jefferson Street & College Avenue intersection are not included in this
work. (Previously Built)
9. Duration of the design process is anticipated to be 18 months.
10. Custom luminaires and light art are not included in this work.
11. Subsurface environmental studies are not anticipated.
$ 117.42 $ 86.82 $ 78.34 $ 54.84
1 Base Map Preparation Interwest 4 8 8 40 $ 3,985 $ - $ 3,985
2 Roadway Preliminary Layout (20% Design) Interwest 24 40 40 40 $ 11,618 $ 200 $ 11,818
3 Roadway FIR Plans (60% Design) Interwest 60 160 160 120 $ 40,052 $ 500 $ 40,552
4 Public Input & Meetings/Project Coordination Interwest 88 45 24 15 $ 16,943 $ 1,500 $ 18,443
5Urban Design Exhibits BHA 30700 $ 30,700 $ 1,000 $ 31,700
6 Urban Design Preliminary Layout (20% Design) BHA 13100 $ 13,100 $ 1,000 $ 14,100
7 Urban Design FIR Plans (60% Design) BHA 17900 $ 17,900 $ 1,000 $ 18,900
8 Public Input & Meetings/Project Coordination BHA 15300 $ 15,300 $ 800 $ 16,100
9 Structural Design Larsen 4000 $ 4,000 $ 100 $ 4,100
10 Irrigation Preliminary Layout (20% Design) Hines 6500 $ 6,500 $ 50 $ 6,550
11 Irrigation FIR Plans (60% Design) Hines 6100 $ 6,100 $ 50 $ 6,150
12 Electrical Preliminary Layout (20% Design) Clanton 8200 $ 8,200 $ 200 $ 8,400
13 Electrical FIR Plans (60% Design) Clanton 11500 $ 11,500 $ 200 $ 11,700
176 253 232 215 $ 77,000 $ 4,000 $ 12,600 $ 19,700 $ 185,897 $ 6,600 $ 192,497
Clanton
Electrical
BHA Design
Project
Designer
Jefferson Street Roadway and Multimodal Improvements
Interwest Team - Fee Estimate - 11/10/15
Total Cost
Per Task
Labor Cost
Per Task
Est. Reimb.
Project Manager
Sr. Project
Engineer
Project Engineer
Interwest Consulting Group (2013 CDOT Rates + 10%)
Hines
Irrigation
Larsen
Structural
Total Hours or Cost
Jefferson Street
FIR Design
TASKS
Team
Member
by Task