ADDENDUM NO. 2
SPECIFICATIONS AND CONTRACT DOCUMENTS
Description of BID 8125: Intersection Improvements at Vine & Shields
OPENING DATE: 3:00 PM (Our Clock) June 17, 2015
To all prospective bidders under the specifications and contract documents described above,
the following changes/additions are hereby made and detailed in the following sections of this
addendum:
Exhibit 1 – Revised Bid Schedule
Exhibit 2 – Clarifications & Revisions
Please contact John Stephen, CPPO, LEED AP, Senior Buyer at (970) 221-6777 with any
questions regarding this addendum.
RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED BY A WRITTEN STATEMENT
ENCLOSED WITH THE BID/QUOTE STATING THAT THIS ADDENDUM HAS BEEN
RECEIVED.
Financial Services
Purchasing Division
215 N. Mason St. 2nd Floor
PO Box 580
Fort Collins, CO 80522
970.221.6775
970.221.6707
fcgov.com/purchasing
EXHIBIT 1 – REVISED BID SCHEDULE
Addendum 2
8125 Intersection Improvements at Vine & Shields Page 2 of 5
201-00000 CLEARING AND GRUBBING LS 1 $ -
202-00010 REMOVAL OF TREE EA 59 $ -
202-00031 REMOVAL OF FIRE HYDRANT EA 1 $ -
202-00032 REMOVAL OF VALVE EA 1 $ -
202-00035 REMOVAL OF PIPE LF 20 $ -
202-00200 REMOVAL OF SIDEWALK SY 449 $ -
202-00203 REMOVAL OF CURB AND GUTTER LF 680 $ -
202-00205 REMOVAL OF WHEEL STOP EA 9 $ -
202-00210 REMOVAL OF CONCRETE PAVEMENT SY 37 $ -
202-00220 REMOVAL OF ASPHALT MAT SY 6627 $ -
202-00810 REMOVAL OF GROUND SIGN EA 8 $ -
202-00815 REMOVE SIGN (SPECIAL) EA 1 $ -
202-00828 REMOVAL OF TRAFFIC SIGNAL EQUIPMENT LS 1 $ -
202-01000 REMOVAL OF FENCE LF 1093 $ -
203-00010 UNCLASSIFIED EXCAVATION (COMPLETE IN PLACE) CY 2355 $ -
203-00010 MUCK EXCAVATION CY 450 $ -
203-01597 POTHOLING HOUR 50 $ -
206-00510 FILTER MATERIAL (CLASS A) CY 0.7 $ -
207-00210 STOCKPILE TOPSOIL CY 50 $ -
207-00405 TOPSOIL (SPECIAL) CY 279.4 $ -
208-00018 GRAVEL BAG LF 198 $ -
208-00020 SILT FENCE LF 2186 $ -
208-00045 CONCRETE WASHOUT STRUCTURE EA 1 $ -
208-00050 STORM DRAIN INLET PROTECTION EA 2 $ -
208-00070 VEHICLE TRACKING PAD EA 1 $ -
208-00103 SEDIMENT REMOVAL AND DISPOSAL (LABOR) HOUR 20 $ -
208-00105 SEDIMENT REMOVAL AND DISPOSAL (EQUIPMENT) HOUR 20 $ -
208-00205 EROSION CONTROL SUPERVISOR HOUR 40 $ -
210-00010 RESET MAILBOX STRUCTURE EA 1 $ -
210-00035 RESET WATER METER EA 2 $ -
210-00810 RESET GROUND SIGN EA 7 $ -
210-04010 ADJUST MANHOLE EA 4 $ -
210-04015 MODIFY MANHOLE EA 1 $ -
210-04050 ADJUST VALVE BOX EA 2 $ -
212-00006 SEEDING (NATIVE) AC 0.11 $ -
212-00032 SOIL CONDITIONING AC 0.11 $ -
ITEM NO. ITEM DESCRIPTION UNITQUANTITY UNIT COST COST
Addendum 2
8125 Intersection Improvements at Vine & Shields Page 3 of 5
212-00040 SOIL PREPARATION (LAWN) AC 0.37 $ -
212-00050 SOD SF 15886 $ -
213-00004 MULCHING (WEED FREE STRAW) AC 0.11 $ -
213-00005 MULCHING (DECORATIVE) CF 1614 $ -
213-00008 MULCHING (WOOD CHIP) CF 166 $ -
213-00067 ROCK MULCH (WEED FREE) SF 2029 $ -
213-00070 LANDSCAPE WEED BARRIER FABRIC SY 734 $ -
213-00440 METAL LANDSCAPE BORDER (1/8 x 4 INCH) LF 85 $ -
213-00700 LANDSCAPE BOULDER EA 117 $ -
214-0000 LANDSCAPE MAINTENANCE LS 1 $ -
214-00215 DECIDIOUS TREE (1.5 INCH CALIPER) EA 8 $ -
214-00220 DECIDIOUS TREE (2 INCH CALIPER) EA 33 $ -
214-00350 DECIDIOUS SHRUB (5 GALLON CONTAINER) EA 120 $ -
214-00506 EVERGREEN TREE (6 FOOT) (BALL AND BURLAP) EA 1 $ -
214-00650 EVERGREEN SHRUB (5 GALLON CONTAINER) EA 34 $ -
214-00910 PERENNIALS (1 GALLON CONTAINER) EA 310 $ -
304-06000 AGGREGATE BASE COURSE (ABC)(CLASS 6) TON 3600 $ -
403-00720 HOT MIX ASPHALT (PATCHING)(ASPHALT) TON 19 $ -
403-33741 HOT MIX ASPHALT (GRADING S) (75) (PG 64-22) TON 730.8 $ -
403-34841 HOT MIX ASPHALT (GRADING S) (75) (PG 64-28) TON 265.7 $ -
412-00800 CONCRETE PAVEMENT (8 INCH) SY 426.6 $ -
412-00801 CONCRETE PAVEMENT (8 INCH) (SPEICAL) (DAVIS COLOR TILE RED 1117) SY 216.6 $ -
412-00801 CONCRETE PAVEMENT (8 INCH) (SPEICIAL) (DAVIS COLOR OMAHA TAN 508 SY 286.9 $ -
412-00801 CONCRETE PAVEMENT (8 INCH) (SPECIAL) (DAVIS COLOR COCOA 6130) SY 126.3 $ -
412-00850 CONCRETE PAVEMENT(8.5") SY 2823.4 $ -
412-00870 CONCRETE PAVEMENT (8.5") (FAST TRACK) SY 941.1 $ -
420-00300 GEOTEXTILE (REINFORCEMENT) SY 1200 $ -
504-08050 STONE LANDSCAPE WALL SF 295.5 $ -
506-00210 RIPRAP (9 INCH) CY 2 $ -
601-00000 ART FOUNDATION L S 1 $ -
601-03000 CONCRETE CLASS D CY 21 $ -
602-00000 REINFORCING STEEL LB 829 $ -
605-00004 4 INCH N0N-PERFORATED PIPE UNDERDRAIN LF 233 $ -
605-00040 4 INCH PERFORATED PIPE UNDERDRAIN LF 194 $ -
605-85000 SURFACE SAND FILTER SF 158 $ -
607-11530 FENCE (SPECIAL) LF 210 $ -
608-00006 CONCRETE SIDEWALK (6 INCH) SY 1398 $ -
Addendum 2
8125 Intersection Improvements at Vine & Shields Page 4 of 5
608-00010 CONCRETE CURB RAMP SY 313 $ -
609-21010 CURB & GUTTER TYPE 2 (SECTION I-B) LF 1084 $ -
609-21020 CURB & GUTTER TYPE 2 (SECTION II-B) LF 2136 $ -
609-21021 CURB & GUTTER TYPE 2 (SECTION II-M) LF 297 $ -
609-40010 CURB TYPE 2 (SECTION B) LF 220 $ -
609-40130 CURB MEDIAN(SPECIAL) LF 411 $ -
614-80321 BARRICADE (TYPE 3 M-A) EA 1 $ -
619-50480 6 INCH PLASTIC PIPE LF 36 $ -
619-75048 6 INCH GATE VALVE EA 2 $ -
619-78048 6 INCH FIRE HYDRANT EA 2 $ -
621-00450 DETOUR PAVEMENT SY 983 $ -
623-00000 IRRIGATION SYSTEM LS 1 $ -
623-00602 2 INCH PLASTIC PIPE (IRRIGATION/SLEEVE) LF 900 $ -
623-00604 4 INCH PLASTIC PIPE (IRRIGATION/SLEEVE) LF 375 $ -
626-0000 MOBILIZATION LS 1 $ -
630-00000 FLAGGING HOUR 1200 $ -
630-00007 TRAFFIC CONTROL INSPECTION DAY 39 $ -
630-00012 TRAFFIC CONTROL MANAGEMENT DAY 96 $ -
630-10005 TRAFFIC CONTROL LS 1 $ -
630-80359 PORTABLE MESSAGE SIGN PANEL DAY 10 $ -
630-80370 CONCRETE BARRIER TEMPORARY LF 600 $ -
700-70010 F/A MINOR CONTRACT REVISIONS FA 1 $60,000.00 $ 60,000.00
700-70011 F/A PARTNERING FA 1 $2,500.00 $ 2,500.00
700-70016 F/A FUEL COST ADJUSTMENT FA 1 $8,000.00 $ 8,000.00
700-70019 F/A ASPHALT CEMENT COST ADJUSTMENT FA 1 $15,000.00 $ 15,000.00
700-70380 F/A EROSION CONTROL FA 1 $2,500.00 $ 2,500.00
700-70021 F/A ON THE JOB TRAINING FA 1 $960.00 $ 960.00
IN WORDS:
TOTAL BASE BID
Force Account
Addendum 2
8125 Intersection Improvements at Vine & Shields Page 5 of 5
EXHIBIT 2 – CLARIFICATIONS & REVISIONS
I. Project Clarifications:
A. None at this time.
II. Revisions to the Project Planset:
B. The quantity of Aggregate Base Course (ABC) (Class 6) “SHIELDS 11+58.32 to
16+18.93” on Sheet 21 has been changed from 487.7 TON to 2000 TON.
III. Revisions to the Project Specifications:
C. None at this time
IV. Pre-Bid Clarifications Not Resulting in Changes to the Bid Documents:
D. None at this time
V. Pre-Bid Clarifications Resulting in Changes to the Bid Documents:
E. None at this time
VI. Revisions to the Project Bid Tab:
F. The quantity of aggregate base has been changed from 2035.5 TON to 3600 TON.
The quantity was changed due to a bust found in the quantities on Sheet 21 from
Shields ST 11+58.32 to 16+18.93. The original quantity for this area was 487.7
TON, and it should be 2000 TON.