Loading...
HomeMy WebLinkAboutBID - 8122 LANDSCAPING AT HORSETOOTH & TIMBERLINE (2)SPECIFICATIONS AND CONTRACT DOCUMENTS FOR LANDSCAPING AT HORSETOOTH & TIMBERLINE BID NO. 8122 PURCHASING DIVISION 215 NORTH MASON STREET, 2ND FLOOR, FORT COLLINS MAY 27, 2015 – 3:00 P.M. (OUR CLOCK) Financial Services Purchasing Division 215 N. Mason St. 2nd Floor PO Box 580 Fort Collins, CO 80522 970.221.6775 970.221.6707 fcgov.com/purchasing CONTRACT DOCUMENTS TABLE OF CONTENTS Section Pages BID INFORMATION 00020 Notice Inviting Bids 00020-1 - 00020-2 00100 Instruction to Bidders 00100-1 - 00100-9 00300 Bid Form 00300-1 - 00300-3 00400 Supplements to Bid Forms 00400-1 00410 Bid Bond 00410-1 - 00410-2 00420 Statements of Bidders Qualifications 00420-1 - 00420-3 00430 Schedule of Major Subcontractors 00430-1 CONTRACT DOCUMENTS 00500 Agreement Forms 00500-1 00510 Notice of Award 00510-0 00520 Agreement 00520-1 - 00520-6 00530 Notice to Proceed 00530-1 00600 Bonds and Certificates 00600-1 00610 Performance Bond 00610-1 - 00610-2 00615 Payment Bond 00615-1 - 00615-2 00630 Certificate of Insurance 00630-1 00635 Certificate of Substantial Completion 00635-1 00640 Certificate of Final Acceptance 00640-1 00650 Lien Waiver Release (Contractor) 00650-1 - 00650-2 00660 Consent of Surety 00660-1 00670 Application for Exemption Certificate 00670-1 - 00670-2 CONDITIONS OF THE CONTRACT 00700 General Conditions 00700-1 - 00700-34 Exhibit GC-A GC-A1 - GC-A2 00800 Supplementary Conditions 00800-1 - 00800-2 00900 Addenda, Modifications, and Payment 00900-1 00950 Contract Change Order 00950-1 - 00950-2 00960 Application for Payment 00960-1 - 00960-4 SPECIFICATIONS SECTION 00020 INVITATION TO BID SECTION 00020 INVITATION TO BID Date: May 8, 2015 Sealed Bids will be received by the City of Fort Collins (hereinafter referred to as OWNER), at the office of the Purchasing Division, 3:00 P.M., our clock, on May 27, 2015, for the Landscaping at Horsetooth & Timberline; BID NO. 8122. If delivered, they are to be delivered to 215 North Mason Street, 2nd Floor, Fort Collins, Colorado, 80524. If mailed, the mailing address is P. O. Box 580, Fort Collins, CO 80522-0580. At said place and time, and promptly thereafter, all Bids that have been duly received will be publicly opened and read aloud. The Contract Documents provide for the construction of Bid 8122. The Work includes landscaping of East Horsetooth Road and South Timberline Road at the intersection and in the immediate vicinity of the intersection. The project includes: Topsoil placement, bark mulch and rock mulch placement, tree, shrub and grass plantings, sod placement, irrigation system installation, Low-Impact-Development system installation, median and parkway plantings, planter pots, Art in Public Places installation including foundations and pieces, decorative rock pieces, small rock retaining walls, landscape maintenance for two years. Construction surveying will be completed by the City of Fort Collins. All Bids must be in accordance with the Contract Documents on file with the City of Fort Collins, 215 North Mason St., 2nd floor, Fort Collins, Colorado 80524. The City encourages all disadvantaged business enterprises to submit bid in response to all invitations and will not be discriminated against on the grounds of race, color, national origin. A prebid conference and job walk with representatives of prospective Bidders will be held at 2:00 PM, on May 14, 2015, in Conference Room 1B at 215 N Mason Street, Fort Collins. Prospective Bidders are invited to present their questions relative to this Bid proposal at this meeting. The Contract Documents and Construction Drawings may be examined online at:  Rocky Mountain E-Purchasing System: www.rockymountainbidsystem.com Bids will be received as set forth in the Bidding Documents. The Work is expected to be commenced within the time as required by Section 2.3 of General Conditions. Substantial Completion of the Work is required as specified in the Agreement. The successful Bidder will be required to furnish a Performance Bond and a Payment Bond guaranteeing faithful performance and the payment of all bills and obligations arising from the performance of the Contract. No Bid may be withdrawn within a period of forty-five (45) days after the date fixed for opening Bids. The OWNER reserves the right to reject any and all Bids, and to waive any informalities and irregularities therein. Bid security in the amount of not less than 5% of the total Bid must accompany each Bid in the form specified in the Instructions to Bidders. Sales Prohibited/Conflict of Interest: No officer, employee, or member of City Council, shall have a financial interest in the sale to the City of any real or personal property, equipment, material, supplies or services where such officer or employee exercises directly or indirectly any decision- making authority concerning such sale or any supervisory authority over the services to be rendered. This rule also applies to subcontracts with the City. Soliciting or accepting any gift, gratuity favor, entertainment, kickback or any items of monetary value from any person who has or is seeking to do business with the City of Fort Collins is prohibited. City of Fort Collins Gerry S. Paul Director of Purchasing & Risk Management SECTION 00100 INSTRUCTIONS TO BIDDERS SECTION 00100 INSTRUCTIONS TO BIDDERS 1.0 DEFINED TERMS Terms used in these Instructions to Bidders which are defined in the Standard General Conditions of the Construction Contract (No. 1910-8, 1990 ed.) have the meanings assigned to them in the General Conditions. The term "Bidder" means one who submits a Bid to OWNER, as distinct from a sub-bidder, who submits a Bid to Bidder. The terms "Successful Bidder" means the lowest, qualified, responsible and responsive Bidder to whom OWNER (on basis of OWNER's evaluation as hereinafter provided) makes an award. The term "Bidding Documents" includes the Advertisement or Invitation to Bid, Instructions to Bidders, the Bid Form, and the proposed Contract Documents (including all Addenda issued prior to receipt of Bids). 2.0 COPIES OF BIDDING DOCUMENTS 2.1. Complete sets of Bidding Documents may be obtained as stated in the Invitation to Bid. No partial sets will be issued. The Bidding Documents may be examined at the locations identified in the Invitation to Bid. 2.2. Complete sets of Bidding Documents shall be used in preparing Bids; neither OWNER nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents. 2.3. The submitted Bid proposal shall include Sections 00300, 00410, 00420, and 00430 fully executed. 2.4. OWNER and Engineer, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids on the Work and do not confer a license or grant for any other use. 3.0 QUALIFICATION OF BIDDERS 3.1 To demonstrate qualifications to perform the Work, each Bidder must submit at the time of the Bid opening, a written statement of qualifications including financial data, a summary of previous experience, previous commitments and evidence of authority to conduct business in the jurisdiction where the Project is located. Each Bid must contain evidence of Bidder's qualification to do business in the state where the Project is located or covenant to obtain such qualification prior to award of the contract. The Statement of Qualifications shall be prepared on the form provided in Section 00420. 3.2. In accordance with Section 8-160 of the Code of the City of Fort Collins in determining whether a bidder is responsible, the following shall be considered: (1) The ability, capacity and skill of the bidder to perform the contract or provide the services required, (2) whether the bidder can perform the contract or provide the service promptly and within the time specified without delay or interference, (3) the character, integrity, reputation, judgment, experience and efficiency of the bidder, (4) the quality of the bidder's performance of previous contracts or services, (5) the previous and existing compliance by the bidder with laws and ordinances relating to the contract or service, (6) the sufficiency of the financial resources and ability of the bidder to perform the contract or provide the service, (7) the quality, availability and adaptability of the materials and services to the particular use required, (8) the ability of the bidder to provide future maintenance and service for the use of the subject of the contract, and (9) any other circumstances which will affect the bidder's performance of the contract. 3.3. Each Bidder may be required to show that he has handled former Work so that no just claims are pending against such Work. No Bid will be accepted from a Bidder who is engaged on any other Work which would impair his ability to perform or finance this Work. 3.4 No Bidder shall be in default on the performance of any other contract with the City or in the payment of any taxes, licenses or other monies due to the City. 4.0 EXAMINATION OF CONTRACT DOCUMENTS AND SITE 4.1. It is the responsibility of each Bidder, before submitting a Bid, to (a) examine the Contract Documents thoroughly, (b) visit the site to familiarize himself with local conditions that may in any manner affect cost, progress or performance of the Work, (c) familiarize himself with federal, state and local laws, ordinances, rules and regulations that may in any manner affect cost, progress or performance of the Work, (d) study and carefully correlate Bidder's observations with the Contract Documents, and (e) notify Engineer of all conflicts, errors or discrepancies in the Contract Documents. 4.2. Reference is made to the Supplementary Conditions for identification of: Subsurface and Physical Conditions SC-4.2. 4.3. The submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article 4, that without exception the Bid is premised upon performing and furnishing the Work required by the Contract Documents and such means, methods, techniques, sequences or procedures of construction as may be indicated in or required by the Contract Documents, and that the Contract Documents are sufficient in scope and detail to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work. 5.0 INTERPRETATIONS AND ADDENDA. 5.1. All questions about the meaning or intent of the Bidding Documents are to be submitted in writing to the Engineer and the OWNER. Interpretation or clarifications considered necessary in response to such questions will be issued only by Addenda. Questions received less than seven days prior to the date for opening of the Bids may not be answered. Only questions answered by formal written Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect. 5.2. All questions concerning the scope of this project should be directed to the Engineer. Questions regarding submittal of bids should be directed to the City of Fort Collins' Purchasing Division. 5.3. Addenda may also be issued to modify the Bidding Documents as deemed advisable by OWNER or Engineer. 5.4. Addenda will be mailed or delivered to all parties recorded by the OWNER as having received the Bidding documents. 6.0 BID SECURITY 6.1. Each Bid must be accompanied by Bid Security made payable to OWNER in the amount stated in the Invitation to Bid. The required security must be in the form of a certified or bank cashier's check payable to OWNER or a Bid Bond on the form enclosed herewith. The Bid Bond must be executed by a surety meeting the requirements of the General Conditions for surety bonds. 6.2. The Bid Security of the successful Bidder will be retained until such Bidder has executed the Agreement and furnished the required contract security, whereupon Bid Security will be returned. If the successful Bidder fails to execute and deliver the Agreement and furnish the required contract security within 15 days of the Notice of Award, OWNER may annul the Notice of Award and the Bid Security of that Bidder will be forfeited. The Bid Security of other Bidders whom OWNER believes to have reasonable chance receiving the award may be retained by OWNER until the earlier of the seventh day after the effective date of the Agreement or the thirty-first day after the Bid Opening, whereupon Bid Security furnished by such Bidders will be returned. Bid Security with Bids which are not competitive will be returned within seven days after the Bid opening. 7.0 CONTRACT TIME. The number of days within which, or the date by which the Work is to be substantially complete and also completed and ready for Final Payment (the Contract Times) are set forth in the Agreement. 8.0 LIQUIDATED DAMAGES. Provisions for liquidated damages are set forth in the Agreement. 9.0 SUBSTITUTE ("OR EQUAL") MATERIAL AND EQUIPMENT The Contract, if awarded, will be on the basis of material and equipment described on the Drawings or specified in the Specifications without consideration of possible substitute or "or equal" items. Whenever it is indicated on the Drawings or specified in the Specifications that a substitute or "or equal" item of material or equipment may be furnished or used by CONTRACTOR if acceptable to Engineer, application for such acceptance will not be considered by Engineer until after the "effective date of the Agreement". The procedure for submittal of any such application by CONTRACTOR and consideration by Engineer is set forth in the General Conditions which may be supplemented in the General Requirements. 10.0 SUBCONTRACTORS, SUPPLIERS AND OTHERS 10.1. Each Bidder shall submit at the Bid opening to OWNER a list of principal subcontractors he proposes to use in the Work. Refer to Section 00430 contained within these Documents. 10.2. If OWNER or Engineer after due investigation has reasonable objection to any proposed Subcontractor, either may, before the Notice of Award is given, request the apparent successful Bidder to submit an acceptable substitute without an increase in Bid price. If the apparent successful Bidder declines to make any substitution, OWNER may award the contract to the next lowest responsive and responsible Bidder that proposes to use acceptable subcontractors. Subcontractors, suppliers, other persons or organization listed and to whom OWNER or Engineer does not make written objection prior to the giving of the Notice of Award will be deemed acceptable to OWNER and ENGINEER subject to revocation of such acceptance after the effective date of the Agreement as provided in the General Conditions. 10.3. CONTRACTOR shall not be required to employ any subcontractor, supplier or other persons or organizations against whom he has reasonable objection. The use of subcontractors listed by the Bidder and accepted by OWNER prior to the Notice of Award will be required in the performance of the Work. 11.0 BID FORM. 11.1. A copy of the Bid Form is bound in the Contract Documents which may be retained by the Bidder. A separate unbound copy is enclosed for submission with the Bid. 11.2. Bid Forms must be complete in ink or typed. All lump sum prices on the form must be stated in words and numerals; in case of conflict, words will take precedence. Unit prices shall govern over extensions of sums. 11.3. Bids by corporations must be executed in the corporate name by the president or a vice-president (or other appropriate officer accompanied by evidence of authority to sign) and the corporate seal shall be affixed and attested by the secretary or an assistant secretary. The corporate address and state of incorporation shall be shown below the corporate name. 11.4. Bids by partnerships must be executed in the partnership name and signed by a partner, his title must appear under his signature and the official address of the partnership must be shown below the signature. 11.5. Bids by joint venture shall be signed by each participant in the joint venture or by an authorized agent of each participant. The full name of each person or company interested in the Bid shall be listed on the Bid Form. 11.6. The Bid shall contain an acknowledgement of receipt of all Addenda (the numbers of which must be filled in on the Bid Form). 11.7. No alterations in Bids, or in the printed forms therefore, by erasures, interpolations, or otherwise will be acceptable unless each such alteration is signed or initialed by the Bidder; if initialed, OWNER may require the Bidder to identify any alteration so initialed. 11.8. The address and telephone number for communications regarding the Bid shall be shown. 12.0 BID PRICING. Bids must be priced as set forth in the Bid Schedule or Schedules. 13.0 SUBMISSION OF BIDS. 13.1. Bids shall be submitted at the time and place indicated in the Invitation to Bid and shall be enclosed in an opaque sealed envelope marked with the Project title, Bid No., and name and address of the Bidder and accompanied by the Bid Security, Bid Form, Bid Bond, Statement of Bidders Qualifications, and Schedule of Subcontractors as required in Section 00430. If the Bid is sent through the mail or other delivery system, the sealed envelope shall be enclosed in a separate envelope with the notation "BID ENCLOSED" on the face of it. 13.2. Bids shall be deposited at the designated location prior to the time and date for receipt of Bids indicated in the Invitation to Bid, or any extension thereof made by addendum. Bids received after the time and date for receipt of Bids will be returned unopened. Bidder shall assume full responsibility for timely delivery at the location designated for receipt of Bids. 13.3. Oral, telephonic, telegraphic, or facsimile Bids are invalid and will not receive consideration. 13.4. No Bidder may submit more than one Bid. Multiple Bids under different names will not be accepted from one firm or association. 14.0 MODIFICATION AND WITHDRAWAL OF BIDS. 14.1. Bids may be modified or withdrawn by an appropriate document duly executed (in a manner that a Bid must be executed) and delivered to the place where Bids are to be submitted at any time prior to the opening of Bids. 14.2. Bids may also be modified or withdrawn in person by the Bidder or an authorized representative provided he can prove his identity and authority at any time prior to the opening of Bids. 14.3. Withdrawn Bids may be resubmitted up to the time designated for the receipt of Bids provided that they are then fully in conformance with these Instructions to Bidders. 15.0 OPENINGS OF BIDS. Bids will be opened and (unless obviously non-responsive) read aloud publicly as indicated in the Invitation to Bid. An abstract of the amounts of the Base Bids and major alternates (if any) will be made available after the opening of Bids. 16.0 BIDS TO REMAIN OPEN SUBJECT TO ACCEPTANCE. All Bids shall remain open for forty-five (45) days after the day of the Bid Opening, but OWNER may, in his sole discretion, release any Bid and return the Bid Security prior to that date. 17.0 AWARD OF CONTRACT. 17.1. OWNER reserves the right to reject any and all Bids, to waive any and all informalities not involving price, time or changes in the Work, to negotiate contract terms with the Successful Bidder, and the right to disregard all nonconforming, nonresponsive, unbalanced or conditional Bids. Also, OWNER reserves the right to reject the Bid of any Bidder if OWNER believes that it would not be in the best interest of the Project to make an award to that Bidder, whether because the Bid is not responsive or the Bidder is unqualified or of doubtful financial ability or fails to meet any other pertinent standard or criteria established by OWNER. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum. 17.2. In evaluating Bids, OWNER will consider the qualifications of the Bidders, whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices and other data, as may be requested in the Bid Form or prior to the Notice of Award. 17.3. OWNER may consider the qualification and experience of Subcontractors, Suppliers, and other persons and organizations proposed for those portions of the Work as to which the identity of Subcontractors, Suppliers, and other persons and organizations is submitted as requested by OWNER. OWNER also may consider the operating costs, maintenance requirements, performance data and guarantees of major items of materials and equipment proposed for incorporation in the Work when such data is required to be submitted prior to the Notice of Award. 17.4. OWNER may conduct such investigations as OWNER deems necessary to assist in the evaluation of any Bid and to establish the responsibility, qualifications and financial ability of the Bidder's proposed Subcontractors, Suppliers and other persons and organizations to do the Work in accordance with the Contract Documents to OWNER's satisfaction within the prescribed time. 17.5. If the Contract is to be awarded, it will be awarded to the lowest responsive and responsible Bidder whose evaluation by OWNER indicates to OWNER that the award will be in the best interest of the OWNER. Award shall be made on the evaluated lowest base bid excluding alternates. The basis for award shall be the lowest Bid total for the Schedule or, in the case of more than one schedule, for sum of all schedules. Only one contract will be awarded. 17.6. If the Contract is to be awarded, OWNER will give the Successful Bidder a Notice of Award within forty-five (45) days after the date of the Bid opening. 18.0 CONTRACT SECURITY. The General Conditions and the Supplementary Conditions set forth OWNER's requirements as to performance and other Bonds. When the Successful Bidder delivers the executed Agreement to the OWNER, it shall be accompanied by the required Contract Security. 19.0 SIGNING OF AGREEMENT. When OWNER gives a Notice of Award to the Successful Bidder, it will be accompanied by the required number of unsigned counterparts of the Agreement with all other written Contract Documents attached. Within fifteen (15) days thereafter, CONTRACTOR shall sign and deliver the required number of counterparts of the Agreement and attached documents to OWNER with the required Bonds. Within ten (10) days thereafter, OWNER hall deliver one fully signed counterpart to CONTRACTOR. Each counterpart is to be accompanied by a complete set of the Drawings with appropriate identification. 20.0 TAXES. OWNER is exempt from Colorado State Sales and Use Taxes on materials and equipment to be incorporated in the Work. Said taxes shall not be included in the Contract Price. Reference is made to the General and Supplementary Conditions. 21.0 RETAINAGE. Provisions concerning retainage are set forth in the Agreement. 22.0 PURCHASING RESTRICTIONS. Purchasing restrictions: The Bidder's authorized signature of this Bid assures the Bidder's compliance with the City's purchasing restrictions. A copy of the resolutions is available for review in the Purchasing and Risk Management Division or the City Clerk's office. A. Cement Restrictions: City of Fort Collins Resolution 91-121 requires that suppliers and producers of cement or products containing cement to certify that the cement was not made in cement kilns that burn hazardous waste as a fuel. 23.0 COLLUSIVE OR SHAM BIDS. Any Bid deemed by the City in its sole discretion to be a collusive or sham Bid will be rejected and reported to authorities as such. Your authorized signature of this Bid assures that such Bid is genuine and is not a collusive or sham Bid. 24.0 BID RESULTS. For information regarding results for individual Bids send a self-addressed, self-stamped envelope and a Bid tally will be mailed to you. Bid results will be posted in the Purchasing office seven (7) days after the Bid Opening. END OF SECTION SECTION 00300 BID FORM SECTION 00300 BID FORM PROJECT: 8122 Landscaping at Horsetooth & Timberline Place: Date: 1. In compliance with your Invitation to Bid dated , 20 and subject to all conditions thereof, the undersigned a (Corporation, Limited Liability Company, Partnership, Joint Venture, or Sole Proprietor) authorized to do business in the State of Colorado hereby proposes to furnish and do everything required by the Contract Documents to which this refers for the construction of all items listed on the following Bid Schedule or Bid Schedules. 2. The undersigned Bidder does hereby declare and stipulate that this proposal is made in good faith, without collusion or connection with any other person or persons Bidding for the same Work, and that it is made in pursuance of and subject to all the terms and conditions of the Invitation to Bid and Instructions to Bidders, the Agreement, the detailed Specifications, and the Drawings pertaining to the Work to be done, all of which have been examined by the undersigned. 3. Accompanying this Bid is a certified or cashier's check or standard Bid bond in the sum of ($ ) in accordance with the Invitation To Bid and Instructions to Bidders. 4. The undersigned Bidder agrees to execute the Agreement and a Performance Bond and a Payment Bond for the amount of the total of this Bid within fifteen (15) calendar days from the date when the written notice of the award of the contract is delivered to him at the address given on this Bid. The name and address of the corporate surety with which the Bidder proposes to furnish the specified performance and payment Bonds is as follows: . 5. All the various phases of Work enumerated in the Contract Documents with their individual jobs and overhead, whether specifically mentioned, included by implication or appurtenant thereto, are to be performed by the CONTRACTOR under one of the items listed in the Bid Schedule, irrespective of whether it is named in said list. 6. Payment for Work performed will be in accordance with the Bid Schedule or Bid Schedules subject to changes as provided in the Contract Documents. 7. The undersigned Bidder hereby acknowledges receipt of Addenda No. through . 8. BID SCHEDULE (Base Bid) General Labor HOUR 20 $ - Backhoe HOUR 15 $ - Top Soil Placement CY 348 $ - Erosion Log LNFT 200 $ - Sod SF 42000 $ - Landscape Weed Barrier Fabric SY 700 $ - Inorganic Mulch (Special) (3-6" Cobble) TON 35 $ - Inorganic Mulch (Special) (3/4" Rock Chips) TON 42 $ - Inorganic Mulch (Special) (4/12" Buff Rip-Rap Mulch) TON 43 $ - Inorganic Mulch (Special) (4/12" Mulch for Art Installation) TON 12 $ - Mulching (Special) (Medium Bark Mulch) CY 54 $ - Metal Landscape Border LF 290 $ - Decorative Railing LF 192 $ - Boulders - Buff Sandstone EA 126 $ - Boulders - River Rock EA 151 $ - Deciduous Trees - 2" Caliper EA 47 $ - Ornamental Trees - 2" Caliper EA 64 $ - Shrubs - 5 Gal. EA 255 $ - Ornamental Grasses - 1 Gal. EA 464 $ - Perennials - 1 Gal. EA 883 $ - Sandstone Bollards EA 6 $ - Planters EA 3 $ - Irrigation LS 1 $ - Landscape Maintenance (24 Months) LS 1 $ - Drilled Caisons (Art Foundation) LF 22 $ - LID Swale Soil Section LF 170 $ - Mobilization LS 1 $ - Construction Zone Traffic Control LS 1 $ - Flagging HOUR 200 $ - ITEM DESCRIPTION UNITQUANTITY UNIT COST COST 9. PRICES The foregoing prices shall include all labor, materials, transportation, shoring, removal, dewatering, overhead, profit, insurance, etc., to cover the complete Work in place of the several kinds called for. Bidder acknowledges that the OWNER has the right to delete items in the Bid or change quantities at his sole discretion without affecting the Agreement or prices of any item so long as the deletion or change does not exceed twenty-five percent (25%) of the total Agreement Price. RESPECTFULLY SUBMITTED: CONTRACTOR BY: Printed Date Title License Number (If Applicable) (Seal - if Bid is by corporation) Attest: Address Telephone Email 700-01 F/A Minor Contract Revisions FA 1 $30,000.00 $ 30,000.00 700-02 F/A Erosion Control FA 1 $1,000.00 $ 1,000.00 IN WORDS: TOTAL BASE BID SECTION 00400 SUPPLEMENTS TO BID FORMS 00410 Bid Bond 00420 Statement of Bidder's Qualifications 00430 Schedule of Subcontractors SECTION 00410 BID BOND KNOW ALL MEN BY THESE PRESENTS: that we, the undersigned as Principal, and , as Surety, are hereby held and firmly bound unto the City of Fort Collins, Colorado, as OWNER, in the sum of $ for the payment of which, well and truly to be made, we hereby jointly and severally bind ourselves, successors, and assigns. THE CONDITION of this obligation is such that whereas the Principal has submitted to the City of Fort Collins, Colorado the accompanying Bid and hereby made a part hereof to enter into a Construction Agreement for the construction of Fort Collins Project, 8122 Landscaping at Horsetooth & Timberline. NOW THEREFORE, (a) If said Bid shall be rejected, or (b) If said Bid shall be accepted and the Principal shall execute and deliver a Contract in the form of Contract attached hereto (properly completed in accordance with said Bid) and shall furnish a BOND for his faithful performance of said Contract, and for payment of all persons performing labor or furnishing materials in connection therewith, and shall in all other respects perform the Agreement created by the acceptance of said Bid, then this obligation shall be void; otherwise the same shall remain in force and effect, it being expressly understood and agreed that the liability of the Surety for any and all claims hereunder shall, in no event, exceed the penal amount of this obligation as herein stated. The Surety, for value received, hereby stipulates and agrees that the obligations of said Surety and its BOND shall be in no way impaired or affected by any extension of the time within which the OWNER may accept such Bid; and said Surety does hereby waive notice of any such extension. Surety Companies executing bonds must be authorized to transact business in the State of Colorado and be accepted by the OWNER. IN WITNESS WHEREOF, the Principal and the Surety have hereunto set their hands and seals this day of , 20__, and such of them as are corporations have caused their corporate seals to be hereto affixed and these presents to be signed by their proper officers, the day and year first set forth above. PRINCIPAL SURETY Name: Address: By: By: Title: Title: ATTEST: By: (SEAL) (SEAL) SECTION 00420 STATEMENT OF BIDDER'S QUALIFICATIONS All questions must be answered and the data given must be clear and comprehensive. This statement must be notarized. If necessary, questions may be answered on separate attached sheets. The Bidder may submit any additional information he desires. 1. Name of Bidder: 2. Permanent main office address: 3. When organized: 4. If a corporation, where incorporated: 5. How many years have you been engaged in the contracting business under your present firm or trade name? 6. Contracts on hand: (Schedule these, showing the amount of each contract and the appropriate anticipated dates of completion.) 7. General character of Work performed by your company: 8. Have you ever failed to complete any Work awarded to you? If so, where and why? 9. Have you ever defaulted on a contract? If so, where and why? 10. Are you debarred by any government agency? If yes list agency name. 11. List the more important projects recently completed by your company, stating the approximate cost of each, and the month and year completed, location and type of construction. 12. List your major equipment available for this contract. 13. Experience in construction Work similar in importance to this project: 14. Background and experience of the principal members of your organization, including officers: 15. Credit available: $ 16. Bank Reference: 17. Will you, upon request, fill out a detailed financial statement and furnish any other information that may be required by the OWNER? 18. Are you licensed as a General Contractor? If yes, in what city, county and state? What class, license and numbers? 19. Do you anticipate subcontracting Work under this Contract? If yes, what percent of total contract? And to whom? 20. Are any lawsuits pending against you or your firm at this time? IF yes, DETAIL 21. What are the limits of your public liability? DETAIL What company? 22. What are your company's bonding limitations? 23. The undersigned hereby authorizes and requests any person, firm or corporation to furnish any information requested by the OWNER in verification of the recital comprising this Statement of Bidder's Qualifications. Dated at ________________ this ______ day of __________________, 20__. Company: By: Printed: Title: State of County of being duly sworn deposes and says that he is of (Name) (Organization) and that the answers to the foregoing questions and all statements therein contained are true and correct. Subscribed and sworn to before me this _______ day of____________, 20__. (Seal) Notary Public My commission expires: . SECTION 00430 SCHEDULE OF SUBCONTRACTORS List all subcontractors for the work items listed below and all subcontractors performing over 15% of the contract. ITEM SUBCONTRACTOR SECTION 00500 AGREEMENT FORMS 00510 Notice of Award 00520 Agreement 00530 Notice to Proceed SECTION 00510 NOTICE OF AWARD DATE: [Date] TO: [Contractor] PROJECT: 8122 Landscaping at Horsetooth & Timberline OWNER: CITY OF FORT COLLINS (hereinafter referred to as "the OWNER") You are hereby notified that your Bid dated [Contractor's Bid Date] for the above project has been considered. You are the apparent successful Bidder and have been awarded an Agreement for 8122 Landscaping at Horsetooth & Timberline. The Price of your Agreement is ($ ). Three (3) copies of each of the proposed Contract Documents (except Drawings) accompany this Notice of Award. Three (3) sets of the Drawings will be delivered separately or otherwise made available to you immediately. You must comply with the following conditions precedent within fifteen (15) days of the date of this Notice of Award, that is by [Date]. 1. You must deliver to the OWNER three (3) fully executed counterparts of the Agreement including all the Contract Documents. Each of the Contract Documents must bear your signature on the cover of the page. 2. You must deliver with the executed Agreement the Contract Security (Bonds) as specified in the Instructions to Bidders, General Conditions (Article 5.1) and Supplementary Conditions. Failure to comply with these conditions within the time specified will entitle OWNER to consider your Bid abandoned, to annul this Notice of Award and to declare your Bid Security forfeited. Within ten (10) days after you comply with those conditions, OWNER will return to you one (1) fully-signed counterpart of the Agreement with the Contract Documents attached. City of Fort Collins OWNER By: Gerry S. Paul Director of Purchasing & Risk Management SECTION 00520 AGREEMENT THIS AGREEMENT is dated as of the [Day] day of [Month] in the year of 20[Year] and shall be effective on the date this AGREEMENT is signed by the City. The City of Fort Collins (hereinafter called OWNER) and [Contractor] (hereinafter called CONTRACTOR) OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set forth, agree as follows: ARTICLE 1. WORK CONTRACTOR shall complete all Work as specified or indicated in the Contract Documents. The Project for which the Work under the Contract Documents may be the whole or only a part is defined as the construction of the 8122 Landscaping at Horsetooth & Timberline.. ARTICLE 2. ENGINEER The Project has been designed by BHA Design, Inc. The City of Fort Collins Engineering Department is hereinafter called ENGINEER and will assume all duties and responsibilities and will have the rights and authority assigned to ENGINEER in the Contract Documents in connection with completion of the Work in accordance with the Contract Documents. ARTICLE 3. CONTRACT TIMES 3.1 The Work shall be Substantially Complete by November 16, 2015, after the date when the Contract Times commence to run as provided in the General Conditions and completed and ready for Final Payment and Acceptance in accordance with the General Conditions within fifteen (15) calendar days after the date when the Contract Times commence to run. 3.2. Liquidated Damages. OWNER and CONTRACTOR recognize that time is of the essence of this Agreement and that OWNER will suffer financial loss if the Work is not completed within the times specified in paragraph 3.1. above, plus any extensions thereof allowed in accordance with Article 12 of the General Conditions. They also recognize the delays, expenses and difficulties involved in proving in a legal preceding the actual loss suffered by OWNER if the Work is not completed on time. Accordingly, instead of requiring any such proof, OWNER and CONTRACTOR agree that as Liquidated damages for delay (but not as penalty) CONTRACTOR shall pay OWNER the amounts set forth hereafter. 1) Substantial Completion: Six Hundred Dollars ($600.00) for each calendar day or fraction thereof that expires after the November 16, 2015 deadline for Substantial Completion of the Work until the Work is Substantially Complete. 2) Final Acceptance: After Substantial Completion, Six Hundred Dollars ($600.00) for each calendar day or fraction thereof that expires after the fifteen (15) calendar day period for Final Payment and Acceptance until the Work is ready for Final Payment and Acceptance. ARTICLE 4. CONTRACT PRICE 4.1 OWNER shall pay CONTRACTOR for performance of the Work in accordance with the Contract Documents in current funds as follows: Dollars ($ ), in accordance with Section 00300, attached and incorporated herein by this reference. ARTICLE 5. PAYMENT PROCEDURES CONTRACTOR shall submit Applications for Payment in accordance with Article 14 of the General Conditions. Applications for Payment will be processed by ENGINEER as provided in the General Conditions. 5.1. PROGRESS PAYMENTS. OWNER shall make progress payments on account of the Contract Price on the basis of CONTRACTOR's Application for Payment as recommended by ENGINEER, once each month during construction as provided below. All progress payments will be on the basis of the progress of the Work measured by the schedule of values established in paragraph 2.6 of the General Conditions and in the case of Unit Price Work based on the number of units completed, and in accordance with the General Requirements concerning Unit Price Work. 5.1.1. Prior to Substantial Completion, Owner will be entitled to withhold as contract retainage five percent (5%) of each progress payment, but, in each case, less the aggregate of payments previously made and less such amounts as ENGINEER shall determine, or OWNER may withhold, in accordance with paragraph 14.7 of the General Conditions. If , in the sole discretion of Owner, on recommendation of Engineer, Owner determines that the character and progress of the Work have been satisfactory to OWNER and ENGINEER, OWNER may determine that as long as the character and progress of the Work remain satisfactory to them, there will be no additional retainage on account of Work completed in which case the remaining progress payments prior to Substantial Completion will be in an amount equal to 100% of the Work completed. 95% of materials and equipment not incorporated in the Work (but delivered, suitably stored and accompanied by documentation satisfactory to OWNER as provided in paragraph 14.2 of the General Conditions) may be included in the application Section 00520 Page 3 for payment. 5.1.2. Upon Substantial Completion payment will be made in an amount sufficient, if necessary, to increase total payments to CONTRACTOR to 95% of the Contract Price, less such amounts as ENGINEER shall determine or OWNER may withhold in accordance with paragraph 14.7 of the General Conditions or as provided by law. 5.2. FINAL PAYMENT. Upon Final Completion and Acceptance of the Work in accordance with paragraph 14.13 of the General Conditions, OWNER shall pay the remainder of the Contract Price as recommended by ENGINEER as provided in said paragraph 14.13. ARTICLE 6. CONTRACTOR'S REPRESENTATION In order to induce OWNER to enter into this Agreement, CONTRACTOR makes the following representations: 6.1. CONTRACTOR has familiarized himself with the nature and extent of the Contract Documents, Work, site, locality, and with all local conditions and Laws and Regulations that in any manner may affect cost, progress, performance or furnishing of the Work. 6.2. CONTRACTOR has studied carefully all reports of explorations and tests of subsurface conditions and drawings of physical conditions which are identified in the Supplementary Conditions as provided in paragraph 4.2 of the General Conditions. 6.3. CONTRACTOR has obtained and carefully studied (or assumes responsibility for obtaining and carefully studying) all such examinations, investigations, explorations, tests, reports, and studies (in addition to or to supplement those referred to in paragraph 6.2 above) which pertain to the subsurface or physical condition at or contiguous to the site or otherwise may affect the cost, progress, performance or furnishing of the Work as CONTRACTOR considers necessary for the performance or furnishing of the Work at the Contract Price, within the Contract Times and in accordance with the other terms and conditions of the Contract Documents, including specifically the provisions of paragraph 4.2 of the General Conditions; and no additional examinations, investigations, explorations, tests, reports, studies or similar information or data are or will be required by CONTRACTOR for such purposes. 6.4. CONTRACTOR has reviewed and checked all information and data shown or indicated on the Contract Documents with respect to existing Underground Facilities at or contiguous to the site and assumes responsibility for the accurate location of said Underground Facilities. No additional examinations, investigations, explorations, tests, reports, studies or similar information or data in respect of said Underground Facilities are or will be required by CONTRACTOR in order to perform and furnish the Work at the Contract Price, within the Contract Times and in accordance with the other terms and conditions of the Contract Documents, including specifically the provision of paragraph 4.3. of the General Conditions. 6.5. CONTRACTOR has correlated the results of all such observations, examinations, investigations, tests, reports and data with the terms and conditions of the Contract Documents. 6.6. CONTRACTOR has given ENGINEER written notice of all conflicts, errors or discrepancies that he has discovered in the Contract Documents and the written resolution thereof by ENGINEER is acceptable to CONTRACTOR. ARTICLE 7. CONTRACT DOCUMENTS 7.1 The Contract Documents which comprise the entire Agreement between OWNER and CONTRACTOR concerning the Work consist of the General Conditions, Supplementary Conditions, those items included in the definition of “Contract Documents” in Article 1.10 of the General Conditions, and such other items as are referenced in this Article 7, all of which are incorporated herein by this reference. 7.2 Forms for use by CONTRACTOR in performing the Work and related actions in carrying out the terms of this Agreement are deemed Contract Documents and incorporated herein by this reference, and include, but are not limited to, the following: 7.2.1 Certificate of Substantial Completion 7.2.2 Certificate of Final Acceptance 7.2.3 Lien Waiver Releases 7.2.4 Consent of Surety 7.2.5 Application for Exemption Certificate 7.2.6 Application for Payment 7.3 Drawings, consisting of a cover sheet and sheets numbered as follows: G1 – G4 LANDSCAPE GRADING PLANS L1 – L5 LANDSCAPE PLAN D1 – D3 SITE DETAILS IR1.0 – IR3.1 IRRIGATION PLANS The Contract Drawings shall be stamped "Final for Construction" and dated. Any revisions made shall be clearly identified and dated. 7.4. Addenda Numbers to , inclusive. 7.5. The Contract Documents also include all written amendments and other documents amending, modifying, or supplementing the Contract Documents pursuant to paragraphs 3.5 and 3.6 of the General Conditions. 7.6. There are no Contract Documents other than those listed or incorporated by reference in this Article 7. The Contract Documents may only be amended, modified or supplemented as provided in paragraphs 3.5 and 3.6 of the General Conditions. ARTICLE 8. MISCELLANEOUS 8.1. Terms used in this Agreement which are defined in Article I of the General Conditions shall have the meanings indicated in the General Conditions. 8.2. No assignment by a party hereto of any rights under or interests in the Contract Documents will be binding on another party hereto without the written consent of the party sought to be bound; and specifically but not without limitations, moneys that may become due and moneys that are due may not be assigned without such consent (except to the extent that the effect of this restriction may be limited by law), and unless specifically stated to the contrary in any written consent to an assignment no assignment will release or discharge that assignor from any duty or responsibility under the Contract Document. 8.3. OWNER and CONTRACTOR each binds itself, its partners, successors, assigns and legal representatives to the other party hereto, its partners, successors, assigns and legal representatives in respect to all covenants, Agreement and obligations contained in the Contract Document. OWNER: CITY OF FORT COLLINS CONTRACTOR: [CONTRACTOR] By: By: DARIN ATTEBERRY, CITY MANAGER By: GERRY S. PAUL PRINTED DIRECTOR OF PURCHASING Title: Date: Date: Attest: (CORPORATE SEAL) City Clerk Address for giving notices: P. O. Box 580 Fort Collins, CO 80522 Attest: Approved as to Form Address for giving notices: Assistant City Attorney License No.: SECTION 00530 NOTICE TO PROCEED Description of Work: 8122 Landscaping at Horsetooth & Timberline To: [Contractor] This notice is to advise you: That the contract covering the above described Work has been fully executed by the CONTRACTOR and the OWNER. That the required CONTRACTOR's Performance Bond and Payment Bond have been received by the OWNER. That the OWNER has approved the said Contract Documents. Therefore, as the CONTRACTOR for the above described Work, you are hereby authorized and directed to proceed within ( ) calendar days from receipt of this notice as required by the Agreement. Dated this day of , 20 . The dates for Substantial Completion and Final Acceptance shall be , 20_ and , 20__, respectively. City of Fort Collins OWNER By: Title: ACKNOWLEDGMENT OF NOTICE Receipt of the above Notice to Proceed is hereby acknowledged this day of , 20__. CONTRACTOR: [Contractor] By: Title: SECTION 00600 BONDS AND CERTIFICATES 00610 Performance Bond 00615 Payment Bond 00630 Certificate of Insurance 00635 Certificate of Substantial Completion 00640 Certificate of Final Acceptance 00650 Lien Waiver Release (CONTRACTOR) 00660 Consent of Surety 00670 Application for Exemption Certificate SECTION 00610 PERFORMANCE BOND Bond No. KNOW ALL MEN BY THESE PRESENTS: that (firm) (address) (an Individual), (a Partnership), (a Corporation), hereinafter referred to as the "Principal" and (Firm) (Address) hereinafter referred to as "the Surety", are held and firmly bound unto City of Fort Collins, 300 Laporte Ave, Fort Collins, Colorado 80522 a (Municipal Corporation) hereinafter referred to as the "OWNER", in the penal sum of Dollars ($ ) in lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, successors and assigns, jointly and severally, firmly by these presents. THE CONDITIONS OF THIS OBLIGATION are such that whereas the Principal entered into a certain Agreement with the OWNER, dated the [Day] day of [Month], 20[Year], a copy of which is hereto attached and made a part hereof for the performance of The City of Fort Collins Project, 8122 Landscaping at Horsetooth & Timberline. NOW, THEREFORE, if the Principal shall well, truly and faithfully perform its duties, all the undertakings, covenants, terms, conditions and agreements of said Agreement during the original term thereof, and any extensions thereof which may be granted by the OWNER, with or without Notice to the Surety and during the life of the guaranty period, and if the Principal shall satisfy all claims and demands incurred under such Agreement, and shall fully indemnify and save harmless the OWNER from all cost and damages which it may suffer by reason of failure to do so, and shall reimburse and repay the OWNER all outlay and expense which the OWNER may incur in making good any default then this obligation shall be void; otherwise to remain in full force and effect. PROVIDED, FURTHER, that the said Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Agreement or to the Work to be performed thereunder or the Specifications accompanying the same shall in any way affect its obligation on this bond; and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the Agreement or to the Work or to the Specifications. PROVIDED, FURTHER, that no final settlement between the OWNER and the CONTRACTOR shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfied. PROVIDED, FURTHER, that the Surety Company must be authorized to transact business in the State of Colorado and be acceptable to the OWNER. IN WITNESS WHEREOF, this instrument is executed in three (3) counterparts, each one of which shall be deemed an original, this _____ day of _____ ____, 20__. IN PRESENCE OF: Principal (Title) (Title) (Corporate Seal) (Address) IN PRESENCE OF: Other Partners _____________________________ By: _____________________________ By: IN PRESENCE OF: Surety _____________________________ By:_____________________________________ _____________________________ (Address) (Surety Seal) NOTE: Date of Bond must not be prior to date of Agreement. If CONTRACTOR is Partnership, all partners should execute Bond. SECTION 00615 PAYMENT BOND Bond No. KNOW ALL MEN BY THESE PRESENTS: that (firm) (address) (an Individual), (a Partnership), (a Corporation), hereinafter referred to as the "Principal" and (Firm) (Address) hereinafter referred to as "the Surety", are held and firmly bound unto the City of Fort Collins, 300 Laporte Ave., Fort Collins, Colorado 80522 a (Municipal Corporation) hereinafter referred to as "the OWNER", in the penal sum of Dollars ($ ) in lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, successors and assigns, jointly and severally, firmly by these presents. THE CONDITIONS OF THIS OBLIGATION are such that whereas the Principal entered into a certain Agreement with the OWNER, dated the [Day] day of [Month], 20[Year], a copy of which is hereto attached and made a part hereof for the performance of The City of Fort Collins Project, 8122 Landscaping at Horsetooth & Timberline. NOW, THEREFORE, if the Principal shall make payment to all persons, firms, subcontractors, and corporations furnishing materials for or performing labor in the prosecution of the Work provided for in such Agreement and any authorized extension or modification thereof, including all amounts due for materials, lubricants, repairs on machinery, equipment and tools, consumed, rented or used in connection with the construction of such Work, and all insurance premiums on said Work, and for all labor, performed in such Work whether by subcontractor or otherwise, then this obligation shall be void; otherwise to remain in full force and effect. PROVIDED, FURTHER, that the said Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Agreement or to the Work to be performed thereunder or the Specifications accompanying the same shall in any way affect its obligation on this bond; and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the Agreement or to the Work or to the Specifications. PROVIDED, FURTHER, that no final settlement between the OWNER and the CONTRACTOR shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfied. PROVIDED, FURTHER, that the Surety Company must be authorized to transact business in the State of Colorado and be acceptable to the OWNER. IN WITNESS WHEREOF, this instrument is executed in three (3) counterparts, each one of which shall be deemed an original, this day of , 20__. IN PRESENCE OF: Principal (Title) (Title) (Corporate Seal) (Address) IN PRESENCE OF: Other Partners _____________________________ By: _____________________________ By: IN PRESENCE OF: Surety _____________________________ By:_____________________________________ _____________________________ (Address) (Surety Seal) NOTE: Date of Bond must not be prior to date of Agreement. If CONTRACTOR is Partnership, all partners should execute Bond. SECTION 00630 CERTIFICATE OF INSURANCE CONTRACTOR shall insert his own standard form for Certificate of Insurance in accordance with the following requirements: 1. The Contractor will provide, from insurance companies acceptable to the City, the insurance coverage designated hereinafter and pay all costs. Before commencing work under this bid, the Contractor shall furnish the City with certificates of insurance showing the type, amount, class of operations covered, effective dates and date of expiration of policies, and containing substantially the following statement: “The insurance evidenced by this Certificate will not reduce coverage or limits and will not be cancelled, except after thirty (30) days written notice has been received by the City of Fort Collins.” In case of the breach of any provision of the Insurance Requirements, the City, at its option, may take out and maintain, at the expense of the Contractor, such insurance as the City may deem proper and may deduct the cost of such insurance from any monies which may be due or become due the Contractor under this Agreement. The City, its officers, agents and employees shall be named as additional insureds on the Contractor 's general liability and automobile liability insurance policies for any claims arising out of work performed under this Agreement. 2. Insurance coverages shall be as follows: A. Workers' Compensation & Employer's Liability. The Contractor shall maintain during the life of this Agreement for all of the Contractor's employees engaged in work performed under this agreement: 1. Workers' Compensation insurance with statutory limits as required by Colorado law. 2. Employer's Liability insurance with limits of $100,000 per accident, $500,000 disease aggregate, and $100,000 disease each employee. B. Commercial General & Vehicle Liability. The Contractor shall maintain during the life of this Agreement such commercial general liability and automobile liability insurance as will provide coverage for damage claims of personal injury, including accidental death, as well as for claims for property damage, which may arise directly or indirectly from the performance of work under this Agreement. Coverage for property damage shall be on a "broad form" basis. The amount of insurance for each coverage, Commercial General and Vehicle, shall not be less than $1,000,000 combined single limits for bodily injury and property damage. In the event any work is performed by a subcontractor, the Contractor shall be responsible for any liability directly or indirectly arising out of the work performed under this Agreement by a subcontractor, which liability is not covered by the subcontractor's insurance SECTION 00635 CERTIFICATE OF SUBSTANTIAL COMPLETION TO: CITY OF FORT COLLINS (OWNER) DATE OF SUBSTANTIAL COMPLETION: PROJECT TITLE: 8122 Landscaping at Horsetooth & Timberline PROJECT OR SPECIFIED PART SHALL LOCATION: Fort Collins, Colorado INCLUDE: OWNER: City of Fort Collins CONTRACTOR: [Contractor] CONTRACT DATE: [Date] The Work performed under this contract has been inspected by authorized representatives of the OWNER, CONTRACTOR, and the ENGINEER and the project or specified part of the project, as indicated above) is hereby declared to be substantially completed on the above date. A tentative list of items to be completed or corrected is appended hereto. This list may not be exhaustive, and the failure to include an item on it does not alter the responsibility of the CONTRACTOR to complete all the Work in accordance with the Contract Documents. ENGINEER AUTHORIZED REPRESENTATIVE DATE The CONTRACTOR accepts the above Certificate of Substantial Completion and agrees to complete and correct the items on the tentative list within the time indicated. CONTRACTOR AUTHORIZED REPRESENTATIVE DATE The OWNER accepts the project or specified area of the project as substantially complete and will assume full possession of the project or specified area of the project at 12:01 a.m., on . The responsibility for heat, utilities, security, and insurance under the Contract Documents shall be as set forth under "Remarks" below. CITY OF FORT COLLINS, COLORADO By: OWNER AUTHORIZED REPRESENTATIVE DATE REMARKS: SECTION 00640 CERTIFICATE OF FINAL ACCEPTANCE , 20__ TO: [Contractor] Gentlemen: You are hereby notified that on the day of , 20__, the City of Fort Collins, Colorado, has accepted the Work completed by [Contractor] for the City of Fort Collins project, 8122 Landscaping at Horsetooth & Timberline. A check is attached hereto in the amount of $ as Final Payment for all Work done, subject to the terms of the Contract Documents which are dated [Contract Date]. In conformance with the Contract Documents for this project, your obligations and guarantees will continue for the specified time from the following date:____________ _, 20__. Sincerely, OWNER: City of Fort Collins By: Title: ATTEST: Title: SECTION 00650 LIEN WAIVER RELEASE (CONTRACTOR) TO: City of Fort Collins, Colorado (OWNER) FROM: [Contractor] (CONTRACTOR) PROJECT: 8122 Landscaping at Horsetooth & Timberline 1. The CONTRACTOR acknowledges having received payment, except retainage from the OWNER for all work, labor, skill and material furnished, delivered and performed by the CONTRACTOR for the OWNER or for anyone in the construction, design, improvement, alteration, addition or repair of the above described project. 2. In consideration of such payment and other good and valuable consideration, the receipt and adequacy of which are hereby acknowledged, the CONTRACTOR voluntarily waives all rights, claims and liens, including but not limited to, mechanic's liens, Miller Act claims (40 U.S.C.A. 270 a and b), stop notices, equitable liens and labor and material bond rights which the CONTRACTOR may now or may afterward have, claim or assert for all and any work, labor, skill or materials furnished, delivered or performed for the construction, design, improvement, alteration, addition or repair of the above described project, against the OWNER or its officers, agents, employees or assigns, against any fund of or in the possession or control of the OWNER, against the project or against all land and the buildings on and appurtenances to the land improved by the project. 3. The CONTRACTOR affirms that all work, labor and materials, furnished, delivered or performed to or for the construction, design, improvement, alteration, addition or repair of the project were furnished, delivered or performed by the CONTRACTOR or its agents, employees, and servants, or by and through the CONTRACTOR by various Subcontractors or materialmen or their agents, employees and servants and further affirms the same have been paid in full and have released in full any and all existing or possible future mechanic's liens or rights or claims against the project or any funds in the OWNER'S possession or control concerning the project or against the OWNER or its officers, agents, employees or assigns arising out of the project. 4. The CONTRACTOR agrees to defend and hold harmless the OWNER, the lender, if any, and the Surety on the project against and from any claim hereinafter made by the CONTRACTOR'S Subcontractors, materialmen, employees, servants, agents or assigns against the project or against the OWNER or its officers, employees, agents or assigns arising out of the project for all loss, damage and costs, including reasonable attorneys fees, incurred as a result of such claims. 5. The parties acknowledge that the description of the project set forth above constitutes and adequate description of the property and improvements to which this Lien Waiver Release pertains. It is further acknowledged that this Lien Waiver Release is for the benefit of and may be relied upon by the OWNER, the lender, if any, and Surety on any labor and material bonds for the project. Signed this day of , 20__. CONTRACTOR: [CONTRACTOR] By: Title: ATTEST: Secretary STATE OF COLORADO ) )ss. COUNTY OF LARIMER ) Subscribed and sworn to before me this day of 20__, by . Witness my hand and official seal. Notary Public My Commission Expires: SECTION 00660 CONSENT OF SURETY TO: City of Fort Collins, Colorado (hereinafter referred to as the "OWNER") CONTRACTOR: [Contractor] PROJECT: 8122 Landscaping at Horsetooth & Timberline CONTRACT DATE: [Date] In accordance with the provisions of the Contract between the OWNER and the CONTRACTOR as indicated above, for . (Surety) on bond of hereby approves of the Final Payment to the CONTRACTOR, and agrees that Final Payment to the CONTRACTOR shall not relieve the Surety Company of any of its obligations to the OWNER, as set forth in the said Surety Company's Bond. IN WITNESS WHEREOF, the Surety Company has hereunto set its hand this day of , 20____ . (Surety Company) By: ATTACH: Power of Attorney and Certificate of Authority of Attorney(s)-in-Fact. SECTION 00670 APPLICATION FOR EXEMPTION CERTIFICATE Special Notice Contractors who have completed this application in the past, please note the following changes in procedure: The Department will no longer issue individual Certificates of exemption to subcontractors. Only prime contractors will receive a Contractor’s Exemption Certificate on exempt projects. Upon receipt of the Certificate, the prime contractor should make a copy for each subcontractor involved in the project and complete it by filling in the subcontractor’s name and address and signing it. The original Certificate should always be retained by the prime contractor. Copies of all Certificates that the prime contractor issued to subcontractors should be kept at the prime contractor’s place of business for a minimum of three years and be available for inspection in the event of an audit. Once an 89# has been assigned to you, please use the next five numbers following it for any applications submitted for future projects. This should be your permanent number. For instance, if you were assigned 89-12345-0001, every application submitted thereafter should contain 89-12345 on the application. The succeeding numbers will be issued by the Department of Revenue. DO NOT enter what you believe to be the next in sequence as this may delay processing of your application. SECTION 00700 GENERAL CONDITIONS SECTION 00800 SUPPLEMENTARY CONDITIONS SECTION 00800 SUPPLEMENTARY CONDITIONS Conditions of the Contract These Supplementary Conditions amend or supplement the General Conditions of the Construction Contract (EJCDC General Conditions 1910-8, 1990 edition with City of Fort Collins modifications) and other provisions of the Contract Documents as indicated below. SC-5.4.8 Limits of Liability A. Add the following language at the end of paragraph 5.4.8. The limits of liability for the insurance required by the paragraph numbers of the General Conditions listed below are as follows: 5.4.1 and 5.4.2 Coverage A - Statutory Limits Coverage B - $100,000/$100,000/$500,000 5.4.3 and 5.4.5 Commercial General Liability policy will have limits of $1,000,000 combined single limits (CSL). This policy will include coverage for Explosion, Collapse, and Underground coverage unless waived by the Owner. 5.4.6 The Comprehensive Automobile Liability Insurance policy will have limits of $1,000,000 combined single limits (CSL). 5.4.9 This policy will include completed operations coverage/product liability coverage with limits of $1,000,000 combined single limits (CSL). SC-12.3 Add the following language to the end of paragraph 12.3. Contractor will include in the project schedule zero (0) days lost due to abnormal weather conditions. SECTION 00900 ADDENDA, MODIFICATIONS AND PAYMENT 00950 Contract Change Order 00960 Application for Payment SECTION 00950 CHANGE ORDER NO. PROJECT TITLE: 8122 Landscaping at Horsetooth & Timberline CONTRACTOR: [Contractor] PROJECT NUMBER: 8122 DESCRIPTION: 1. Reason for change: 2. Description of Change: 3. Change in Contract Cost: 4. Change in Contract Time: ORIGINAL CONTRACT COST $ .00 TOTAL APPROVED CHANGE ORDER .00 TOTAL PENDING CHANGE ORDER .00 TOTAL THIS CHANGE ORDER .00 TOTAL % OF THIS CHANGE ORDER % TOTAL C.O.% OF ORIGNINAL CONTRACT % ADJUSTED CONTRACT COST $ .00 (Assuming all change orders approved) ACCEPTED BY: DATE: Contractor's Representative ACCEPTED BY: DATE: Project Manager REVIEWED BY: DATE: Title: APPROVED BY: DATE: Title: APPROVED BY: DATE: Purchasing Agent over $30,000 cc: City Clerk Contractor Engineer Project File Architect Purchasing Section 00960 APPLICATION FOR PAYMENT PAGE 1 OF 4 OWNER: City of Fort Collins PROJECT: APPLICATION NUMBER: APPLICATION DATE: PERIOD BEGINNING: ENGINEER: CONTRACTOR: PERIOD ENDING: PROJECT NUMBER: CHANGE ORDERS Application is made for Payment as shown below in connection with Contract NUMBER DATE AMOUNT The present status of the account for this Contract is as follows: 1 2 Original Contract Amount: 3 Net Change by Change Order: Current contract Amount: $0.00 Total Completed and Stored to Date: Less Previous Applications: Amount Due this Application - Before Retainage: $0.00 Less Retainage: Net Change by Change Order $0.00 AMOUNT DUE THIS APPLICATION: $0.00 CERTIFICATION: The undersigned CONTRACTOR certifies that all obligations of CONTRACTOR incurred in connection with the Work have been satisfied as required in Paragraph 14.3. of the General Conditions of the Contract. The above Amount Due This Application is requested by the CONTRACTOR. Date: By: Payment of the above Amount Due This Application is recommended by the ENGINEER. Date: By: Payment of the above Amount Due This Application has been reviewed by the OWNER'S Project Manager. Date: By: Payment of the above Amount Due This Application is approved by the OWNER. Date: By: CONTRACT AMOUNTS APPLICATION FOR PAYMENT PAGE 2 OF 4 Work Completed Work Completed Work Completed Stored Bid This Month Previous Periods To Date Materials Total Item This Earned Percent Number Description Quantity Units Unit Price Amount Qty. Amount Qty. Amount Qty. Amount Period To Date Billed $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 TOTALS $0.00 $0.00 $0.00 $0.00 $0.00 CHANGE ORDERS APPLICATION FOR PAYMENT PAGE 3 OF 4 Work Completed Work Completed Work Completed Stored Bid This Month Previous Periods To Date Materials Total Item This Earned Percent Number Description Quantity Units Unit Price Amount Qty. Amount Qty. Amount Qty. Amount Period To Date Billed $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 TOTALS CHANGE ORDERS $0.00 $0.00 $0.00 $0.00 $0.00 PROJECT TOTALS $0.00 $0.00 $0.00 $0.00 $0.00 STORED MATERIALS SUMMARY PAGE 4 OF 4 On Hand Received Installed On Hand Item Invoice Previous This This This Number Number Description Application Period Period Application $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 TOTALS $0.00 $0.00 $0.00 $0.00 PROJECT AND STANDARD SPECIAL PROVISIONS Horsetooth Road / Timberline Road Landscaping Bid No. 8122 Prepared for: City of Fort Collins Engineering Department 281 North College Avenue Fort Collins, CO 80522-0580 (970) 221-6605 April 28, 2015 PROJECT SPECIAL PROVISIONS COLORADO DEPARTMENT OF TRANSPORTATION CITY OF FORT COLLINS, COLORADO HORSETOOTH RD/TIMBERLINE ROAD OPERATIONAL IMPROVEMENT PROJECT FEDERAL AID PROJECT NO. AQC M455-010 (19307) PROJECT SPECIAL PROVISIONS The General Conditions of the Construction Contract and the Colorado Department of Transportation’s (CDOT) Standard Specifications for Road and Bridge Construction, 2011 Edition, control construction of this project. Where there are conflicts between the two, the more stringent shall control. The following Special Provisions supplement or modify the CDOT Standard Specifications and take precedence over the Standard Specifications and plans. Item Date Page Index Pages (January 29, 2015) 3 Notice to Bidders (January 29, 2015) 5 Commencement and Completion of Work (January 29, 2015) 6 Contract Goal (Combined) (January 29, 2015) 8 OJT Contract Goal (January 29, 2015) 9 Revision of Section 101 - Definitions of Terms (January 29, 2015) 10 Revision of Section 102 - Project Plans and Other Data (January 29, 2015) 11 Revision of Section 105 - Control of Work (January 29, 2015) 12 Revision of Section 105 – Claims for Contract Adjustment (January 29, 2015) 15 Revision of Section 106 - Control of Material (January 29, 2015) 16 Revision of Section 107 – Insurance (January 29, 2015) 20 Revision of Section 107 - Environmental Controls (January 29, 2015) 21 Revision of Section 107 – Legal Relations and Responsibility To Public (January 29, 2015) 23 Revision of Section 108 - Prosecution and Progress (January 29, 2015) 24 Revision of Section 108 – Limitation of Operations (January 29, 2015) 27 Revision of Section 201 – Clearing and Grubbing (January 29, 2015) 28 Revision of Section 202 – Removal of Inlet (January 29, 2015) 29 Revision of Section 202 - Removal of Pipe (January 29, 2015) 30 Revision of Section 202 - Removal of Sidewalk (January 29, 2015) 31 Revision of Section 202 - Removal of Curb and Gutter and Median Cover (January 29, 2015) 32 Revision of Section 202 - Removal of Concrete Pavement (January 29, 2015) 33 Revision of Section 202 - Removal of Asphalt Mat (January 29, 2015) 34 Revision of Section 207 – Topsoil (Special) (January 29, 2015) 35 Revision of Section 208 – Erosion Control (January 29, 2015) 37 Revision of Section 210 – Reset Water Meter (January 29, 2015) 38 Revision of Section 210 – Reset Fire Hydrant (January 29, 2015) 39 Revision of Section 210 – Modify Manhole (January 29, 2015) 40 Revision of Section 210 – Modify Structure (January 29, 2015) 41 Revision of Section 212 – Tree Retention and Protection (January 29, 2015) 42 Revision of Section 304 - Aggregate Base Course (January 29, 2015) 47 COLORADO DEPARTMENT OF TRANSPORTATION CITY OF FORT COLLINS, COLORADO HORSETOOTH RD/TIMBERLINE ROAD OPERATIONAL IMPROVEMENT PROJECT FEDERAL AID PROJECT NO. AQC M455-010 (19307) PROJECT SPECIAL PROVISIONS Item Date Page Revision of Section 403 - Hot Mix Asphalt (January 29, 2015) 48 Revision of Section 403 – Hot Mix Asphalt (Warranty) (January 29, 2015) 51 Revision of Section 412 Portland Cement Concrete Pavement (January 29, 2015) 59 Revision of Section 412 - Fast Track Portland Cement Concrete Pavement (January 29, 2015) 60 Revision of Section 412 – Portland Cement Concrete Pavement (Warranty) (January 29, 2015) 62 Revision of Section 604 – Inlet (Special) (January 29, 2015) 63 Revision of Section 605 – Subsurface Drains (Special) (January 29, 2015) 64 Revision of Section 608 – Sidewalks (January 29, 2015) 65 Revision of Section 608 - Concrete Curb Ramp (January 29, 2015) 67 Revision of Section 609 – Curb and Gutter (January 29, 2015) 69 Revision of Section 610 – Median Cover Material (January 29, 2015) 70 Revision of Section 619 – Water Service (January 29, 2015) 71 Revision of Section 619 – Water Lines (January 29, 2015) 72 Section 621 – Detour Pavement (January 29, 2015) 73 Revision of Section 623 – Plastic Pipe (Irrigation Sleeve) (January 29, 2015) 75 Revision of Section 625 - Construction Surveying (January 29, 2015) 76 Revision of Section 627 - Pavement Marking (January 29, 2015) 78 Revision of Section 630 – Construction Zone Traffic Control (January 29, 2015) 79 Revision of Section 630 – Impact Attenuator (Temporary) (January 29, 2015) 81 Revision of Section 630 – Temporary Traffic Signal (January 29, 2015) 83 Force Account Items (January 29, 2015) 84 Traffic Control Plan-General (January 29, 2015) 85 Utilities (January 29, 2015) 87 NOTICE TO BIDDERS Pursuant to subsections 102.04 and 102.05, it is recommended that bidders on this project review the work site and plan details with an authorized City representative. Prospective bidders shall contact one of the following listed authorized City representatives at least 12 hours in advance of the time they wish to go over the project. Project Manager - Dan Woodward, Civil Engineer Phone: (970) 416-4203 Cell Phone: (603) 370-7967 Project Manager - Tim Kemp, Civil Engineer Phone: (970) 416-2719 Cell Phone: (970) 219-9762 Project Inspector - Craig Farver, Senior Construction Inspector Cell Phone: (970) 222-0854 The above referenced individuals are the only representatives of the City with authority to provide any information, clarification, or interpretation regarding the plans, specifications, and any other contract documents or requirements. Questions received from bidders along with City responses will be posted as an addendum online at the City of Fort Collins Buy Speed Webpage, www.fcgov.com/eprocurement as they become available. All questions shall be directed to the City contacts listed above no later than 7:00 A.M. one week prior to the bid opening. Questions and answers shall be used for reference only and shall not be considered part of the Contract. REVISION OF SECTION 101 DEFINITIONS OF TERMS Technical Specifications related to construction materials and methods for the work embraced under this Contract shall consist of the “Colorado Department of Transportation, State of Colorado, Standard Specifications for Road and Bridge Construction” dated 2011. Certain terms utilized in the Specifications referred to in the paragraph above shall be interpreted to have different meanings within the scope of this Contract. A summary of redefinitions follows: Where reference is made in the plans and specifications to Owner, Department, Chief Engineer, Resident Engineer, Project Engineer, Engineer, and Inspection and Testing Agency it is understood to mean the City of Fort Collins, Colorado or the City’s representative. Where reference is made in the plans and specifications to Surveyor it is understood to mean provided by the City of Fort Collins with City of Fort Collins crews, but acting as a subcontractor to the project. The sections shown on the following pages are revisions to the Technical Specifications for this project. REVISION OF SECTION 102 PROJECT PLANS AND OTHER DATA Section 102 of the Standard Specifications is hereby revised for this project as follows: Subsection 102.05 shall include the following: A copy of the bid may be obtained as follows: 1. Download the Proposal/Bid from the BuySpeed Webpage, www.fcgov.com/eprocurement 2. Come by Purchasing at 215 North Mason St. 2nd floor, Fort Collins, and request a copy of the Bid The low responsive, responsible bidder may obtain from the City of Fort Collins at no cost; 3 sets of 11x17 plans, 1 full size set, and 3 sets of special provisions REVISION OF SECTION 105 CONTROL OF WORK Section 105 of the Standard Specifications is hereby revised for this project as follows: Subsection 105.10 shall include: Traffic Closures and Operations The Contractor will submit a Traffic Control Plan as outlined in Section 630 of the project specifications. All construction phasing plans, traffic control plans, and requests for closures must be coordinated with the City of Fort Collins Traffic Department and approved by the City. Single lane closures and “lane drops” on both Horsetooth and Timberline Road will be allowed at the approval of the City, after September 14, 2015. Prior to September 14, 2015 the Contractor will need to coordinate any lane closures in conjunction with the roadway contract work through the City. Multiple lane closures, due to either contract or non-contract work within the project area, will not be allowed. Work within the medians on both Horsetooth and Timberline Road may not begin without concurrence from the City and an approved traffic control plan. Traffic Coordination The Contractor shall coordinate with the City Traffic Engineer for all traffic control activities. This shall include, but not be limited to, closure of any City Streets, closure of any partial intersection movements, lane reductions, and detours. City Traffic Control Contact: Syl Mireles Phone: (970)221-6815 Email: smireles@fcgov.com Each Contractor involved shall assume all liability, financial or otherwise, in connection with the Contract and shall protect and save harmless the Owner from any and all damages or claims that may arise because of inconvenience, delay , or loss because of the presence and operations of Contractors working within the limits of the same or adjacent project. Contractor is responsible to coordinate with private utilities. Any work to be performed by private utilities shall be identified in Contractor’s schedule. Delays due to coordination issues will be the responsibility of the contractor. Coordination with Property Owners and Tenants The City of Fort Collins is committed to maintaining a positive working relationship with the businesses and residents in the project area. Every effort will be made to maintain pedestrian and bicycle flow and to accommodate special events and holidays for businesses, pedestrians, parking, and vehicle traffic. The Contractor shall be responsible to coordinate all work activities with private property owners and tenants along the project corridor. Access shall be maintained at all times. The Contractor shall be responsible for communicating accurate scheduling information to the project team to assure proper notification of businesses and residents. In particular, any proposed disruption or closure to an existing access must be communicated to the property Owners and tenants with as much notice as possible. The minimum notice that will be allowed for any proposed access change is 48 hours. The Contractor shall ensure that adequate alternate access is in place for vehicles and pedestrians and any property-specific access needs are addressed prior to any change in existing access. The Contractor shall coordinate his method of maintaining these accesses with the City of Fort Collins Traffic Operations Department. REVISION OF SECTION 105 CONTROL OF WORK Coordination with Traffic Engineer and Traffic Control Supervisor The Contractor shall coordinate with the Owner’s Traffic Engineer for all traffic control activities. Requests for initial Setup of the major project phases (road closures) must be made 3 weeks prior to projected set up. Allow up to 5 days for advanced warning signs. Requests for minor traffic control set ups (lane drops, etc.) must be made 72 hours in advance of set up. Increased Traffic Control costs caused by delays assessed to the Contractor will be the responsibility of the Contractor. Delete subsection 105.12 and replace with the following: Coordination with other contractors Extensive coordination with the contractor performing the roadway work is expected. The Contractor will cooperate and coordinate with existing contract work in the area so that conflicts are minimized, duplication of work is minimized, unnecessary traffic impacts are minimized, and progress is expedited. The City, County, CDOT, and local utilities including but not limited to Xcel Energy and CenturyLink may contract for and perform other or additional work on or near the Work of the project. When separate contracts are let within the limits of the project, each Contractor shall conduct the Work without interfering or hindering the progress or completion of the work performed by other contractors. Contractors working on the same project shall cooperate with each other as directed. REVISION OF SECTION 105 CONTROL OF WORK Subsection 105.13 shall include: Surveying Coordination A. The Owner will provide any required construction surveying for the project. City Survey Crews will perform the surveying required. B. The Contractor must submit a survey request form to the City Surveyors a minimum of 72 hours prior to needing surveying. C. If the requested surveying cannot be accomplished in the time frame requested by the Contractor, the survey personnel shall notify the Contractor with the date on which the requested work will be completed. D. Should a sudden change in the Contractor’s operations or schedule require the survey personnel to work overtime, the Contractor shall pay the additional overtime expense. E. The Contractor shall protect all survey monuments and construction stakes. If it is unavoidable to remove a survey monument or construction stakes, the Contractor is responsible for notifying the Surveyor and allowing enough time for the monuments or stakes to be relocated. The Contractor will be responsible for the cost of restaking construction stakes and for the cost of re-establishing a destroyed monument. F. The Contractor shall be responsible for transferring the information from the construction staked to any necessary forms and for constructing all pipelines, drainage ways, pavements, inlets, walls, and other structures in accordance with the information on the stakes and grade sheets supplied by the Owner. REVISION OF SECTION 105 CLAIMS FOR CONTRACT ADJUSTMENT Section 105 of the Standard Specifications is hereby revised for this project as follows: Subsections 105.22, 105.23 and 105.24 shall be revised as follows: The Colorado Department of Transportation will not participate in the resolution process for any claims filed by the Contractor. REVISION OF SECTION 106 CONTROL OF MATERIAL Section 106 of the Standard Specifications is hereby revised for this project as follows: Subsection 106.01 shall include: Substitutions and Product Options A. Description: 1. This section describes the procedure required by the Contractor for product substitutions. 2. Requests for Substitution: a. Base all bids on materials, equipment and procedures specified. b. Certain types of equipment and kinds of material are described in specifications by means of trade names and catalog numbers, and/or manufacturer’s names. Where this occurs, it is not intended to exclude from consideration such types of equipment and kinds of material bearing other trade names, catalog numbers and/or manufacturer’s names, capable of accomplishing purpose of types of equipment or kinds of material specifically indicated. c. Other types of equipment and kinds of material may be acceptable to the Owner and Engineer. d. Types of equipment, kinds of material and methods of construction, if not specifically indicated must be approved in writing by Engineer and the Owner. 3. Submission of Requests for Substitution: a. After Notice to Proceed, the Owner / Engineer will consider written requests for substitutions of products, materials, systems or other items. b. The Engineer reserves the right to require substitute items to comply color and pattern- wise with base specified items, if necessary to secure “design intent”. c. Submit six (6) copies of request for substitution. Include in request: 1) Complete data substantiating compliance of proposed substitute with Contract Documents. 2) For products: i. Product identification, including manufacturer’s name. ii. Manufacturer’s literature, marked to indicate specific model, type, size, and options to be considered: Product description; performance and test data; reference standards; difference in power demand; dimensional differences for specified unit. iii. Name and address of similar projects on which product were used date of installation and field performance data. REVISION OF SECTION 106 CONTROL OF MATERIAL 3) For construction methods: i. Detailed description of proposed method. ii. Drawings illustrating methods. 4) Itemized comparison of proposed substitution with product or method specified. 5) Data relating to changes in construction schedule. 6) Relation to separate contracts. 7) Accurate cost data on proposed substitution in comparison with product or method specified. d. In making request for substitution, or in using an approved substitute item, Supplier / Manufacturer represents: 1) He has personally investigated proposed product or method, and has determined that it is equal or superior in all respects to that specified and that it will perform function for which it is intended. 2) He will provide same guarantee for substitute item as for product or method specified. 3) He will coordinate installation of accepted substitution into work, to include building modifications if necessary, making such changes as may be required for work to be complete in all aspects. 4) He waives all claims for additional costs related to substitution which subsequently become apparent. 4. Substitutions: Request sufficiently in advance to avoid delay in construction. 5. Contractor’s Option: a. For products specified only by reference standards, select any product meeting standards by any manufacturer indicate selected type in submission. b. For products specified by naming several products or manufacturers, select any product and manufacturer named, indicate selected type in submission. c. For products specified by naming one or more products, but indicating option of selecting equivalent products by stating “or equivalent” after specified product, Contractor must submit request, as required for substitution, for any product not specifically named. 6. Rejection of Substitution or Optional Item: Substitutions and/or options will not be considered if they are indicated or implied on shop drawings, or project data submittals, without formal request submitted in accordance with this section. REVISION OF SECTION 107 INSURANCE Section 107.18 is hereby revised to read: For this project all insurance certificates shall name the City of Fort Collins as an additionally insured party. REVISION OF SECTION 107 ENVIRONMENTAL CONTROLS Section 107 of the Standard Specifications is hereby modified to include the following: Environmental Controls The work of this section consists of obtaining permits and providing environmental controls consistent with regulatory permits through the duration of the work required under this project. A. Dust Control Application: 1. The Contractor shall execute work by methods to minimize raising dust from construction operations. 2. The Contractor shall provide and apply dust control at all times, including evenings, holidays and weekends, as required to abate dust nuisance on and about the site that is a direct result of construction activities. The use of non-approved chemicals, oil, or similar palliatives will not be allowed. Dust control agents may be used only after prior approval of the Owner. The Contractor shall be required to provide sufficient quantities of equipment and personnel for dust control sufficient to prevent dust nuisance on and about the site. 3. The Owner will have authority to order dust control work whenever in its opinion it is required, and there shall be no additional cost to the Owner. The Contractor shall be expected to maintain dust control measures effectively whether the Owner or Engineer specifically orders such Work. B. Preservation of Natural Features: Confine operations as much as possible. Exercise special care to maintain natural surroundings in an undamaged condition. Within the work limits, barricade trees and natural features to be preserved. C. Housekeeping: Keep project neat, orderly, and in a safe condition at all times. Store and use equipment, tools, and materials in a manner that does not present a hazard. Immediately remove all rubbish. Do not allow rubbish to accumulate. Provide on-site containers for collection of rubbish and dispose of it at frequent intervals during progress of work. D. Disposal 1. Disposal of Waste (Unsuitable) Materials: All material determined by the Engineer to be waste will be disposed of in approved landfill in a manner meeting all regulations. Dispose of waste materials, legally, at public or private dumping areas. Do not bury wastes inside of the limits of construction. All costs for dump fees, permits, etc., shall be borne by the Contractor. 2. Disposal of Garbage and Other Construction Materials: Provide sanitary containers/dumpsters and haul away contents such that no overflow exists. 3. Excess excavation shall become the property of the Contractor and shall be legally disposed of by him outside the limits of construction to an approved disposal site. Excess excavated material suitable for backfill shall not be disposed of until all backfill operations are complete. 4. The Contractor is to immediately inform Engineer of any hazardous materials encountered during construction. Dispose of waste materials legally at private or public facilities. E. Burning: No burning of debris will be permitted. REVISION OF SECTION 107 ENVIRONMENTAL CONTROLS F. Noise Control: All mechanical equipment shall be equipped with the best available mufflers to reduce noise. The Contractor shall be responsible for obtaining any necessary permits and shall limit noise to the permitted levels. Noise level monitoring shall be performed by the Contractor as necessary to show that the permitted levels are not being exceeded. Permission from Owner must be obtained prior to the operation of any machinery and/or vehicles between the hours of 6 p.m. and 7 a.m. G. Erosion and Sediment Control: It shall be the responsibility of the Contractor to prepare and obtain an approved Erosion and Sediment Control Plan from the Owner. H. Permits: 1. All work must be performed in accordance with all applicable regulatory permits. 2. The Contractor shall be responsible for obtaining all other necessary permits associated with the Work. REVISION OF SECTION 107 LEGAL RELATIONS AND RESPONSIBILITY TO PUBLIC Section 107 of the Standard Specifications is hereby revised for this project as follows: Subsection 107.01 shall include the following: All hauls traveling to or from Martin Marietta Materials, Inc. (MMM) located at 1800 North Taft Hill Road, Fort Collins, Colorado shall enter and exit the site from the North to CR 54G. No vehicle shall be driven or moved on any private or public highway, street, road or right of way if the vehicle is transporting aggregate material or asphalt paving material unless the load is covered by a tarp or other cover in a manner that prevents the load from escaping the vehicle and which minimizes fumes and emissions. Aggregate material means any rock, clay, silts, gravel, limestone, dimension stone, marble and shale; except that aggregate material does not include wet concrete or other materials not susceptible to blowing. Asphalt paving material means any material formed by mixing aggregate and asphalt cement and includes hot mix asphalt, warm mix asphalt, and bituminous concrete. Subsection 107.25 shall include the following: This work consists of the proper treatment and disposal of ground water collected from dewatering operations during excavation activities. The Contractor shall obtain a construction dewatering permit from the Colorado Department of Public Health and Environment (CDPHE). A completed application must be submitted to CDPHE at least 30 days prior to dewatering operations. Dewatering operations shall be conducted in a manner that avoids pollution and erosion. Water from dewatering operations shall not be directly discharged into any state waters including wetlands, irrigation ditches, canals, or storm sewers, unless allowed by a permit. Discharge into sanitary sewers will not be allowed unless written permission is obtained from the owner or controlling authority and a copy of this approval is submitted to the Engineer. Unless prohibited by law or otherwise specified in the Contract, the water from dewatering operations shall be contained in basins for dissipation by infiltration or evaporation, shall be hauled away from the project for disposal in accordance with applicable laws and regulations, or shall be land applied to approved non-wetland vegetated areas. Depending upon the quality of the water, land application of water to vegetated areas may require a written concurrence or permit from CDPHE and from the owner of the facility. Based on guidelines and criteria from CDPHE, the Contractor shall determine the quality of the water, obtain applicable concurrences or permits, and furnish copies of the concurrences or permits obtained to the Engineer. REVISION OF SECTION 108 PROSECUTION AND PROGRESS Section 108 of the Standard Specifications is hereby revised as follows: Commencement and Completion of Work The Contractor shall commence work under the Contract following the issuance of the "Notice to Proceed." The Contractor shall complete all work in accordance with the Contract by November 16, 2015. Stockpiling of materials before the beginning date is subject to the Engineer's approval. If such approval is given, stockpiled material will be paid for in accordance with Sections l09 and 626. Prior to August 15, 2015 the Contractor may begin staging materials and equipment as space allows and may begin work in areas that are ready, as approved by the City. It is anticipated that work in the project area will not be able to start until August 15, 2015, at which time areas on the outside corners of the intersection will be ready to begin work. Work in the medians will follow after that and the Contractor may not begin work in these areas without approval from the City. It is anticipated that the Contractor will be able to work within the medians by September 14, 2015. Impacts to vehicular traffic patterns will not be allowed prior to September 14, 2015. Pedestrian and bike traffic may be impacted during this time with an approved detour and traffic control plan. See Section 105 and Section 630 for traffic control limitations. Subsection 108.03 shall include the following: The progress schedule shall consist of a Critical Path Method (CPM) schedule prepared using the Microsoft Project software and submitted in hard and electronic formats. The Contractor shall be responsible for planning, scheduling, coordinating, and reporting the progress of the work. Significant coordination with the current roadway contractor will be required. The City will comment on the Contractors initial schedule submittal for coordination of the completion of the work. Salient features to be shown on the Contractor's progress schedule are:  Mobilization  Erosion Control  Irrigation Systems  Grading/earthwork (LID system on NW corner)  Plantings/boulder placement  Art Foundations  Sod and mulch placement  Construction Traffic Control Project Meetings A. Pre-Construction Conference: A Pre-Construction Conference will be held after Notice of Award and before the Notice to Proceed, the date, time and location will be determined after Notice of Award. The conference shall be attended by: 1. Contractor and Contractor’s Superintendent 2. Contractor’s Subcontractors 3. Engineer 4. Owner 5. Contractor performing roadway work under Bid No. 8098 (the City will coordinate this) 6. Others as requested by the Contractor, Owner, or Engineer. Unless previously submitted to the Owner, the Contractor shall bring to the conference a tentative schedule of the construction project, include in the schedule shop drawings and other submittals as required. Any submittals requiring long lead times and therefore must be expedited shall be submitted at the pre-construction conference, or as soon thereafter as possible. The purpose of the conference is to designate responsible personnel and establish a working relationship. Matters requiring coordination will be discussed and procedures for handling such matters established. The agenda will include: 1. Contractor’s tentative Schedule 2. Permit applications and submittals, including Dewatering Permit (as required), Erosion and Sediment Control Plan, and Traffic Control Plan 3. Transmittal, review and distribution of Contractor’s submittals 4. Processing applications for payment 5. Maintaining record documents 6. Critical work sequencing 7. Field decision and change orders 8. Use of premises, office and storage areas, staging area, security, housekeeping, and Owner’s needs 9. Contractor’s assignment of safety and first aid B. Construction Progress Meetings: Progress meetings will be conducted as needed throughout the project as determined by the Owner. These meetings shall be attended by the Owner, the Engineer, the Contractor’s representative and any others invited by these people. The Engineer will conduct the meeting and the Engineer will arrange for keeping the minutes and distributing the minutes to all persons in attendance. The agenda of these project meetings will include construction progress, the status of submittal reviews, and the status of information requests, critical work sequencing, review of strategies for connections into existing facilities, status of field orders and change orders, and any general business. The Contractor will prepare a “two week look ahead” schedule to facilitate coordination of work items. REVISION OF SECTION 108 PROSECUTION AND PROGRESS Modifications to Time of Completion in the Approved Schedule The date of beginning and the time for completion of the work are essential conditions of the Contract Documents and the work embraced shall be commenced on a date specified in the Notice to Proceed. The Contractor will proceed with the work at such rate of progress to ensure full completion within the contract time. It is expressly understood and agreed, by and between the Contractor and the Owner that the contract time for the completion of the work described herein is a reasonable time, taking into consideration the climatic and other factors prevailing in the locality of the work. Every effort shall be made by the Contractor to complete the project within the "Contract Time" shown in the proposal. The "Contract Time" anticipates "Normal" weather and climate conditions in and around the vicinity of the Project site during the times of year that the construction will be carried out. Extensions of time based upon weather conditions shall be granted only if the Contractor demonstrates clearly that such conditions were "unusually severe," would not have been reasonably anticipated, and that such conditions adversely affected the Contractor’s work and thus required additional time to complete the work. The following specifies the procedure for the determination of time extensions for unusually severe weather. The listing below defines the anticipated number of calendar days lost to adverse weather for each month and is based upon National Oceanic and Atmospheric Administration (NOAA) or similar data for the geographic location of the project. Monthly Anticipated Calendar Days Lost to Adverse Weather Conditions JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC (7) (4) (4) (4) (6) (3) (4) (2) (3) (3) (2) (5) The above schedule of anticipated adverse weather will constitute the base line for monthly (or portion thereof) weather time evaluations. Upon acknowledgment of the Notice to Proceed and continuing throughout the contract on a monthly basis, actual adverse weather days and the impact of adverse weather days that delay the work will be recorded on a day-to-day basis. It is assumed that the work will be carried out Mondays through Fridays (holidays accepted) unless an approved construction schedule or written authorization from the Owner indicates otherwise. The number of days of delayed work due to adverse weather or the impact thereof will then be compared to the monthly adverse weather schedule above. An actual adverse weather day must prevent work for 50 percent or more of the Contractor’s workday, delay work critical to the timely completion of the project, and be documented by the Contractor. The City Representative observing the construction shall determine on a daily basis whether or not work can proceed or if work is delayed due to adverse weather or the effects thereof. The Contractor shall notify the Engineer in writing of any disagreement as to whether or not work can proceed on a given date, within 2 calendar days of that date. The Owner will use the above written notification in determining the number of calendar days for which work was delayed during each month. At the end of each month, if the number of work days for which work was delayed due to adverse weather exceeds that shown in the above schedule, a Change Order will be executed which increases the Contract Time. The number of work days delayed due to adverse weather or the impact thereof will then be converted to Calendar Days based on the contract completion day and date. This conversion assumes a 5-day work week, Mondays through Fridays, holidays excepted; should the Contractor have authorization to work weekends and/or holidays, and then the method of conversion of workdays to calendar days would take this into consideration. The contract time period will then be increased by the number of calendar days calculated above and a new contract completion day and date will be set. REVISION OF SECTION 108 PROSECUTION AND PROGRESS The Contractor’s schedule must reflect the above-anticipated adverse weather delays on all weather- dependent activities. While extensions of time shall be granted for "unusually severe" weather or climate conditions, the Owner shall make no monetary compensation for any costs to the Contractor arising out of such delays. The Contractor shall comply with the portions of the Contract Documents relating to his project schedule and amendments thereto which result from the "unusually severe" weather condition. Breakdowns in equipment or lack of performance by the Contractor will not be considered justification for an extension of time. Liquidated damages will be assessed as delineated elsewhere. The Contractor shall not be charged with liquidated damages or any excess cost when the delay in completion of the work is due to the following, and the Contractor has promptly given written notice of such delay to the Owner or Engineer. 1. To any preference, priority, or allocation order duly issued by the Owner. 2. To unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to, acts of God, or of the public enemy, acts of the Owner, acts of another Contractor in the performance of a contract with the Owner, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and abnormal and unforeseeable weather as provided above. 3. To any delays of Subcontractors occasioned by any of the causes specified in paragraphs 1 and 2, above. REVISION OF SECTION 108 LIMITATION OF OPERATIONS Section 108 of the Standard Specifications is hereby revised as follows: Subsection 108.05 shall include the following: Work Hours: Work hours are 7 AM to 6 PM, Monday through Friday. Extended hours and weekend work are anticipated and will be permitted with written approval from the Project Manager. Night time work shall be permitted with written approval from Project Manager. Work shall be permitted on holidays with written approval from the Project Manager. Work requests beyond working hours must be submitted to the Project Manager a minimum of (5) working days prior to the request date. Night and weekend work will be allowed with 5 days prior notice to the Project Manager. All costs associated with nighttime work will be incidental to the work. Demolition work will not be permitted before 7 AM or after 6 PM. Subsection 108.08 shall include the following:  Substantial Completion o Substantial Completion is defined by:  All parkways, plantings, rock placements, medians and island construction are complete and in their final locations  All earthwork, irrigation systems, drainage features, art foundations and railings are complete and functioning and in their final locations.  Off-peak hour lane closures (9:30 AM to 11:30 AM and 1:30 PM to 3:30 PM) will be permitted for minor work required to reach final completion. o Substantial Completion will be completed by November 16, 2015. In accordance with the “Schedule of Liquidated Damages” in Section 108.09, Liquidated Damages per Calendar Day will be $600.00 per day.  Final Completion o Final Completion is defined by:  All final grading, clean up, and punch list items completed, and all processing of change orders complete.  All project record documents shall be turned over to the owner  The work must be ready for final payment and acceptance.  Off-peak hour lane closures (9:30 AM to 11:30 AM and 1:30 PM to 3:30 PM) will be permitted for minor work required to reach final completion. o Final completion will be within fifteen (15) calendar days of substantial completion date. In accordance with the “Schedule of Liquidated Damages” in Section 108.09, Liquidated Damages per Calendar Day will be $600.00 per day. Section 207 of the Standard Specifications is hereby revised for this project as follows: MATERIALS 207.02 shall include the following: Wetland topsoil is not required. It is anticipated that there will be a stockpile of topsoil on-site to be used. Topsoil for this project shall be provided as follows: A. Median Topsoil – Imported or on-site topsoil with 3 cu. yds. compost B. Shrub & Perennial Bed Topsoil - Imported or on-site topsoil with 3 cu. yds. compost C. Tree Lawn Topsoil – Imported or on-site topsoil with 3 cu. yds. compost D. Planter Mix Topsoil – Imported topsoil with 3 cu. yds. compost Topsoil - Shall have the following characteristics: A. Imported topsoil or manufactured topsoil from off-site sources. 1. Additional Properties of Imported or Manufactured Topsoil: Screened and free of stones one inch (1”) or larger in any dimension; free of roots, plants, sod, clods, clay lumps, pockets of coarse sand, paint, paint washout, concrete slurry, concrete layers or chunks, cement, plaster, building debris, oils, gasoline, diesel fuel, paint thinner, turpentine, tar, roofing compound, acid, and other extraneous materials harmful to plant growth; free of obnoxious weeds and invasive plants including quackgrass, Johnsongrass, poison ivy, nutsedge, nimblewill, Canada thistle, bindweed, bentgrass, wild garlic, ground ivy, perennial sorrel, and bromegrass; not infested with nematodes, grubs, other pests, pest eggs, or other undesirable organisms and disease-causing plant pathogens; friable and with sufficient structure to give good tilth and aeration. Continuous, air-filled, pore- space content on a volume/volume basis shall be at least fifteen (15) percent when moisture is present at field capacity. Soil shall have a field capacity of at least fifteen (15) percent on a dry weight basis. B. Samples for Verification: 1. Soil Analysis: Submit copies of proposed topsoil test results from Colorado State University Soils Laboratory or other approved, accepted, accredited testing agency. Submit copies of cover letter / results with recommendations for supplemental fertilizer applications prior to planting. Topsoil shall be amended with fertilizers, as required, by crop type, in accordance with laboratory Soil Analysis Report to provide satisfactory amended topsoil for planting. See Section 212. Ten (10) days before Notice to Proceed, Contractor shall submit a weed mitigation plan to the Engineer for approval. This plan shall include a graphic time line showing milestone and completion dates of herbicide treatment, topsoil stockpiling and topsoil spreading time lines. Soil Conditioner (Compost) Soil Conditioner / organic amendment shall be Class 1 as defined by the Rocky Mountain Region Organics Council. CONSTRUCTION REQUIREMENTS Subsection 207.03 Topsoil Materials and Depths: A. Median Topsoil – Shall be placed at locations over the new median liner to the compacted depth as described on the drawings. B. Shrub & Perennial Bed Topsoil – Shall be placed at locations over the new subgrade to a minimum depth of 6”. C. Tree Lawn Topsoil - Shall be placed at locations over the new subgrade to a minimum depth of 6”. D. Planter Mix Topsoil - Shall be placed within the planters as described in the detail on the drawings. Soil and Finished Grade Preparation A. Sub-grades: Loosen sub-grade to a minimum depth of: 1. Tree Lawn Topsoil - Six-inches (6”) over existing subgrade. Remove stones and clods larger than one-inch (1”) in any dimension and sticks, roots, rubbish, and other extraneous matter and legally dispose of them off Owner's property. Repeat cultivation in areas where equipment, used for hauling and spreading topsoil, has re-compacted subsoil. Owner’s Representative shall be notified if this cannot occur due to existing conditions. B. Finish / Fine Grading: Grade disturbed planting areas to a smooth, uniform surface plane with loose, uniformly fine texture. Grade to within plus or minus one-half (1/2) inch of finish elevation. Roll and rake, remove ridges, and fill depressions to meet finish grades. Limit finish grading to areas that can be planted in the immediate future. 1. Reduce elevation of planting soil to allow for soil thickness of sod or aggregate material. C. Moisten prepared tree lawn areas before planting if soil is dry. Water thoroughly and allow surface to dry before planting. Do not create muddy soil. D. Before planting, restore areas if eroded or otherwise disturbed after finish grading. METHOD OF MEASUREMENT Subsection 207.04 - Revise to include the following: BASIS OF PAYMENT Subsection 207.05: The accepted quantities measured as provided above will be paid for at the contract unit price for each of the pay items listed below that appear in the bid schedule. Payment will be made under: Pay Item: Pay Unit Top Soil Placement Cubic Yard Payment for topsoil shall include soil loosening, soil procurement, placement, and all soil amendments required to produce satisfactory soil for planting. REVISION OF SECTION 212 SEEDING, FERTILIZER AND SODDING Section 212 of the Standard Specifications is hereby revised for this project as follows: DESCRIPTION 212.01 This work consists of soil preparation, application of fertilizer, soil conditioners, or both, and furnishing and placing seed and sod. The work shall be in accordance with the Contract and accepted horticultural practices. MATERIALS 212.02 Seed, Soil Conditioners, Fertilizers, and Sod shall include the following: (a) Soil Conditioners and Fertilizer. 1. Fertilizer: Fertilizer (plant nutrients) shall conform to the applicable State fertilizer laws. It shall be uniform in composition, dry, and free flowing, and shall be delivered to the site in the original, unopened containers, each bearing the manufacturer’s guaranteed analysis. Fertilizer which becomes caked or damaged will not be accepted. 2. Soil Conditioner (Compost): Material shall be A-1 Organic, Colorado Compost, or equivalent approved seven (7) days prior to bidding. Compost shall meet the following specifications: A totally organic product (Mountain peat is not acceptable in the amendment) that has been aerobically and naturally processed without the addition of coarse wood chips, in such a manner as to maintain a consistent temperature of 140 degrees Fahrenheit or greater for a period of time sufficient to create the following characteristics, measured by dry weight: Maximum allowable organic matter: 60% Organic matter to nitrogen ratio 25:1 to 30:1 pH: 6.5 to 7.5 Salts: 2.0 to 3.0 mmhos. Less that 40% inorganic matter. Less than 5% soil, dirt, or sand. Maximum particle size of ½” diameter. Eradication of all harmful weed seeds, pathogens, and bacteria. A well decomposed earthy smell (non-offensive). Soil Amendment shall be applied at the rate of 3 cu. yds. / 1,000 sq.ft. Compost shall be weed-free, organic compost derived from a variety of feed stocks including agricultural, biosolids, forestry, food, leaf and yard trimmings, manure, tree wood with no substances toxic to plants. Material shall be aerobically composted in a facility permitted by the Colorado Department of Public Health and Environment (CDPHE) to produce or sell compost in accordance with House Bill (HB) 1181. The Contractor shall submit a copy of this permit to the Engineer for approval and the project REVISION OF SECTION 212 SEEDING, FERTILIZER AND SODDING records. The compost shall be tested in accordance with the U.S. Composting Council’s Test Methods for Examining of Composting and Compost (TMECC) manual. The compost manufacturer shall be a participating member of in the U.S. Composting Council’s Seal of Testing Assurance Program (STA). The Contractor shall provide a participation certificate and test data on a Compost Technical Data Sheet. (b) Sod. Sod shall be nursery grown and 99 percent weed free. Species shall be as shown on the plans. Other sod types may be used only if approved in writing by the Engineer. The one percent allowable weeds shall not include any undesirable perennial or annual grasses or plants defined as noxious by current State statute. Soil thickness of sod cuts shall not be less than ¾ inch nor more than 1 inch. Sod shall be cut in uniform strips with minimum dimensions of 18 inches in width and 48 inches in length. The Contractor shall submit a sample of the sod proposed for use, which shall serve as a standard. Any sod furnished, whether in place or not, that is not up to the standard of the sample may be rejected. Sod that was cut more than 24 hours prior to installation shall not be used. Each load of sod shall be accompanied by a certificate from the grower stating the type of sod and the date and time of cutting. CONSTRUCTION REQUIREMENTS Deleted subsection 212.04 Lawn Grass Seeding 212.05 Sodding, shall include the following: (a) Soil Preparation. Preparatory to sodding, the ground shall be tilled or hand worked into an even and loose sod bed to a depth of 4 inches, and irregularities in the ground surface shall be removed. Sticks, stones, debris, clods, asphalt, concrete, and other material more than 2 inches in any dimension shall be removed. Any depressions or variances from a smooth grade shall be corrected. Areas to be sodded shall be smooth before any sodding is done. (b) Sodding. The sod shall be laid by staggering joints with all edges touching. On slopes, the sod shall run approximately parallel to the slope contours. Where the sod abuts a drop inlet, the subgrade shall be adjusted so that the sod shall be 1 ½ inch below the top of the inlet. Within one hour after the sod is laid and fertilized it shall be watered. After watering the sod shall be permitted to dry to the point where it is still wet enough for effective rolling. It shall then be rolled in two directions with a lawn roller weighing at least 150 pounds. (c) Fertilizing and Soil Conditioning. Prior to laying sod, the 4 inches of subsoil underlying the sod shall be treated by tilling in fertilizer, soil conditioner, or both. The rate of application shall be as designated in the Contract. Fertilizer called for in the soils analysis shall be worked into the top 6 inches of soil at the rate specified in the contract. Biological nutrient, culture or humic acid based material called for on the plans shall be applied uniformly onto the soil surface. Organic REVISION OF SECTION 212 SEEDING, FERTILIZER AND SODDING amendments shall be applied uniformly over the soil surface and incorporated into the top 6 inches of soil. After laying, the sod shall be fertilized with a fertilizer having an available nutrient analysis of 20-10-5 at the rate of 200 pounds per acre. Fertilizer shall not be applied when the application will damage the sod. METHOD OF MEASUREMENT 212.07 shall be revised as follows: The quantity of sod to be measured will be the actual number of square feet, including soil preparation, water, fertilizer, and sod, completed and accepted. The quantity of organic amendment (compost) will be the actual quantity of compost (CY) delivered to the site, as verified by delivery/weight tickets furnished by contractor. The Contractor shall furnish the Engineer with fertilizer analysis and bag weight tickets prior to placing any fertilizer. Sod or fertilizer placed by the Contractor without the Engineer’s approval will not be paid for. Measurement for acres will be by slope distances. BASIS OF PAYMENT 212.08 shall include the following: The accepted quantities of soil conditioning and sod will be paid for at the contract unit price for each of the pay items listed below that appear in the bid schedule. Payment will be made under: Pay Item Pay Unit Sod Square Foot Soil preparation, water, and fertilizer, incorporated into the seeding sodding or soil conditioning will not be paid for separately but shall be included in the work. Payment for Soil Conditioning (compost) is considered subsidiary to Item 212 Sod and includes delivery of material to the project site, spreading at the application specified rates, and incorporation into the areas to be sodded and seeded, and additional planting areas as indicated on the Drawings. Adjusting or readjusting fertilizing equipment will not be paid for separately but shall be included in the work. REVISION OF SECTION 213 MULCHING Section 213 of the Standard Specifications is hereby revised for this project as follows: DESCRIPTION Subsection 213.01 shall be revised as follows: This work consists of furnishing and placing wood mulch in planting beds and plant saucers, cobble mulch in planting beds, furnishing and installing metal landscape border for the separation of planting beds, and furnishing and installing pea-gravel in tree grates in accordance with the Contract or as directed. Mulching for seeded areas shall be accomplished by the hydraulic method using wood cellulose fiber mulch. MATERIALS Subsection 213.02 shall include the following: Mulching (Special) (Medium Bark Mulch). Shredded wood mulch (weed barrier not required) - free from deleterious materials and suitable as a top dressing of trees and shrubs, consisting of the following: Inorganic Mulch (Special) (River Cobble). Clean, washed, round, tan in color, 3” to 6” blend. Inorganic Mulch (Special) (Rock Chips). Clean, washed, round, tan in color, 3/4” maximum diameter. Inorganic Mulch (Special) (Buff Sandstone Rip Rap). Clean, washed, angular, tan in color, 4” to 12” blend. Inorganic Mulch (Special) (Buff Sandstone Boulders). Angular, naturally broken buff sandstone boulders, 1/2 – 2 ton each. Inorganic Mulch (Special) (River Rock Boulders). Clean, washed, round, buff to brown in color, 1/4 – 1 ton each. Landscape Weed Barrier Fabric. Materials for weed barrier shall be a non-woven geotextile material suitable for this purpose such as Mirafi 140, Typar 3341, or Polyspun 300 or approved equivalent. Submit brand name and model number/name of proposed weed barrier to be used. Metal Landscape Border. The metal landscape border shall consist of a strip of metal 4” tall with roll-top edge, such as steel conforming to ASTM A 1011 or approved equal. CONSTRUCTION REQUIREMENTS Subsection 213.03 shall include the following: Mulching (Special) (Shredded Wood Mulch). Prior to placing mulch and planting in mulch beds, apply Roundup herbicide to weeds and allow beds to sit for seven (7) days. Place wood mulch in shrub beds and tree planting rings in turf areas. Place mulch to a four-inch (4”) depth. Gently REVISION OF SECTION 213 MULCHING brush mulch off of shrubs once installed. Take care in placement not to damage newly planted materials. Do not place mulch directly against stem of plants. Inorganic Mulch (Special) (Type 1 Rock Mulch). This mix contains 75% Rock Chips (3/4” Rock Chips) and 25% River Cobble (3”-6” Blend) Place river cobble over finish grade first, then overlay Rock Chips to a three-inch minimum depth in locations indicated on the drawings. Do not place mulch directly against stem of plants. Inorganic Mulch (Special) (Type 2 Rock Mulch) This mix contains 50% River Cobble (3”-6” Blend) and 50% Buff Sandstone Rip Rap (4”-12” Blend) Place Rip Rap over weed barrier fabric on finish grade first, then overlay River Cobble to a three-inch minimum depth in locations indicated on the drawings. Do not place mulch directly against stem of plants. Inorganic Mulch (Special) (Buff Sandstone Boulders). Place boulders before laying weed barrier fabric or placing mulch. Bury boulder minimum 6” into grade. Inorganic Mulch (Special) (River Rock Boulders). Place boulders before laying weed barrier fabric or placing mulch. Bury boulder minimum 1/3 into grade. Landscape Weed Barrier Fabric. Weed barrier shall be installed in areas where River Cobble and Rock Chips are placed. Where individual weed barrier sheets abut they shall overlap a minimum of four-inches (4”) and be secured with 11 gauge, six-inch (6”) long staples at 18" inches O.C. along the joint. Metal Landscape Border. Metal Landscape border shall be installed along the lines and at the grades shown on the plans by an approved method that will not damage the border. Ends of metal landscape border shall overlap the next adjacent section a minimum of 6 inches. Metal landscape border shall be anchored with wire tie-downs at intervals of approximately 2 feet. Wire tie-downs shall be 9 gage wire at least 14 inches long. Metal landscape border shall be inserted into the ground by driving against the wire tiedowns; ground may be moistened to ease entrance into the ground. Driving on edge of metal landscape border will not be permitted except when the edge is properly shielded. Metal landscape border may be bent for sharp angles, and overlapped at closure of perimeter. Subsection 213.04 shall include the following: The quantity of weed barrier, wood mulch and inorganic mulch will not be measured but shall be the quantity designated in the Contract, except measurements will be made for revisions requested by the Engineer, or for discrepancies of plus of minus five percent (5%) of the total quantity designated in the Contract. Subsection 213.05 shall include the following: Payment will be made under: Pay Item Pay Unit Mulching (Special) (Medium Bark Mulch) Cubic Yard REVISION OF SECTION 213 MULCHING Inorganic Mulch (Special) (River Cobble) Ton Inorganic Mulch (Special) (Rock Chips) Ton Inorganic Mulch (Special) (Buff Sandstone Rip Rap) Ton Inorganic Mulch (Special) (Buff Sandstone Boulders) Ton Inorganic Mulch (Special) (River Rock Boulders) Ton Landscape Weed Barrier Fabric Square Yard Metal Landscape Border (4” roll top) Linear Foot REVISION OF SECTION 214 PLANTING Section 214 of the Standard Specifications is hereby revised for this project as follows: Subsection 214.01 shall be revised as follows: This work consists of furnishing and planting trees, shrubs, and other plant material, hereinafter referred to as “plants”. The work also consists of a Landscape Maintenance Period. See Section 213 for wood mulch, inorganic mulch and weed barrier fabric. Subsection 214.02 shall include the following: Plant List. A plant list is provided on the drawings. Quantities shown on the list are for information only. Contractor shall be responsible for verifying quantity takeoffs as shown on the drawings. In the event of a discrepancy between quantities shown on the plant list and quantities depicted on the plans, the quantities depicted on the plans shall govern. Guying and Staking. Material includes 14AWG wire with 1/2" dia. x12" long PVC sleeves and stake protection cap per each metal stake. In Subsection 214.04 - Delete the first paragraph and item (a) and replace them with the following: The Contractor shall be responsible for the following: The Landscape Establishment Period begins upon receipt of the written “Notice of Substantial Landscape Completion” from the Engineer. Substantial Landscape Completion occurs when all plant materials in the Contract have been planted and all work under Sections 212, 213, 214 and 623 has been performed, except for the Section 214 pay item, Landscape Maintenance. If the Notice of Substantial Landscape Completion is issued during the spring planting season, the Landscape Establishment Period begins immediately and lasts for a period of 24 months. If the Notice of Substantial Landscape Completion is issued at any other time, the Landscape Establishment Period begins at the start of the next spring planting season and lasts for a period of 24 months. After planting on the project is complete, a plant inspection shall be held including the Contractor, Owner and the Landscape Architect to determine acceptability of plant material. During inspection, an inventory of rejected material will be made, and corrective and necessary cleanup measures will be determined. From the time of installation, during construction, and throughout the Landscape Establishment Period, the Contractor shall maintain all plant material, sodded and seeded areas in a healthy and vigorous growing condition, and ensure the successful establishment of vegetation. During the Landscape Establishment Period, the Contractor shall water, cultivate, and prune the plants, and repair, replace or readjust guy material. The Contractor shall also remove weeds from plant beds REVISION OF SECTION 214 PLANTING and saucers and maintain specified depths of mulching material throughout the year and as directed by the City. The contractor will fertilize via a root feeder during the spring of each growing season. Dead, dying or rejected material shall be removed each month during the Landscape Establishment Period as directed. Plant replacement shall be performed during the spring planting seasons at the beginning and end of the Landscape Establishment Period. Plant replacement stock shall be planted in accordance with the Contract and is subject to all requirements specified for the original material. Plant replacement shall be at the Contractor’s expense. Subsection 214.04 Delete paragraphs 5. and 6. and replace with the following: The trees planted by the Contractor shall be watered minimally twice per month at the rate of twenty (20) gallons per tree per watering for the months May through October during the Landscape Establishment Period, or as needed, and the trees shall also be watered once per month at the rate of twenty (20) gallons per tree for the months November through April during the Landscape Establishment Period, or as needed. The shrubs, grasses and perennials planted by the Contractor shall be watered minimally twice per month at the rate of two (2) gallons per shrub per watering event for the months May through October during the Landscape Establishment Period, or as needed, and the shrubs, grasses and perennials shall also be watered once per month at the rate of two (2) gallons per plant for the months November through April during the Landscape Establishment Period, or as needed. METHOD OF MEASUREMENT Subsection 214.05 shall include the following: Soil material for tree, shrub, ornamental grass backfill mix, guy, webbing, tree stakes, protective caps and PVC pipe sleeve and wrap for trees, tree pruning, will not be measured and paid for separately but shall be included in the work. Subsection 214.06: Delete the fifth paragraph and replace with the following - Water used for the Landscape Establishment Period will not be measured and paid or separately but shall be included in the work. Watering of trees and shrubs after receipt of the Notice of Substantial Landscape Completion will not be measured and paid for separately but shall be included in the work. The first watering during the planting of trees and shrubs will not be paid for separately, but shall be included in the price of the work. All water used to meet contract requirements will not be measured and paid for separately but shall be included in the work. Subsection 214.06: Delete the seventh paragraph including item (1) and (2), and the last paragraph of the subsection. Payment will be made under: Pay Item Pay Unit Deciduous Tree (2” caliper) Each Shrub (5 Gallon Container) Each Ornamental Grass (1 Gallon Container) Each Perennial (1 Gallon Container) Each Landscape Maintenance (24 months) Lump Sum REVISION OF SECTION 605 BIORETENTION SAND MEDIA Section 605 of the Standard Specifications is hereby revised for this project as follows: Subsection 605.01 shall include the following: This work consists of installing bioretention sand media, including pea gravel, as permanent water quality treatment, in accordance with these specifications and in accordance with the lines and grades shown in the plans. Subsection 605.02 shall include the following: Materials for bioretention sand media shall meet the following requirements: A. Bioretention Sand Media (BSM) shall be uniformly mixed, uncompacted, free of stones, stumps, roots, or other similar objects larger than two inches. No other materials or substances shall be mixed or dumped within the bioretention area that may be harmful to plant growth or prove a hindrance to the facility’s function and maintenance. B. BSM shall be free of plant or seed material of non-native, invasive species, or weeds. C. Fully mixed BSM shall be tested prior to installation and meet the following criteria: 1. P-Index of less than 30 2. pH of 5.5-6.5. Should pH fall outside of the acceptable range, it may be modified with lime (to raise) or iron sulfate plus sulfur (to lower). The lime or iron sulfate must be mixed uniformly into the BSM prior to use in the bioretention facility. 3. Cation Exchange Capacity (CEC) greater than 10 4. Phosphorous (Phosphate, P2O5) not to exceed 69 ppm 5. BSM that fails to meet the minimum requirements shall be replaced at the Contractor’s expense. D. BSM shall be delivered fully mixed in a drum mixer. Onsite mixing of piles will not be allowed. Mixing of the BSM to a homogeneous consistency shall be done to the satisfaction of the Owner. E. BSM shall contain the following individual materials: 1. Sand - BSM shall consist of 60-70% sand by volume meeting ASTM C-33. 2. Shredded Paper - BSM shall consist of 5-10% shredded paper by volume. i. Shredded paper shall be loosely packed, approximate bulk density of 50-100 lbs/CY. ii. Shredded paper shall consist of loose leaf paper, not shredded phone books, and shall be thoroughly and mechanically mixed to prevent clumping. 3. Topsoil - BSM shall consist of 5-10% topsoil by volume. i. Topsoil shall be classified as sandy loam, loamy sand, or loam per USDA textural triangle with less than 5% clay material. ii. Onsite, native material shall not be used as topsoil. iii. Textural analysis shall be performed on topsoil, preferably at its source, prior to including topsoil in the mix. Topsoil shall be free of subsoil, debris, weeds, foreign matter, and any other material deleterious to plant health. iv. Topsoil shall have a pH range of 5.5 to 7.5 and moisture content between 25-55%. v. Contractor shall certify that topsoil meets these specifications. 4. Leaf Compost - BSM shall consist of 10-20% leaf compost by volume. i. Leaf compost shall consist of Class 1 organic leaf compost consisting of aged leaf mulch resulting from biological degradation and transformation of plant-derived materials under controlled conditions designed to promote aerobic decomposition. ii. The material shall be well composted, free of viable weed seeds and contain material of a generally humus nature capable of sustaining growth of vegetation, with no materials toxic to plant growth. iii. Compost shall be provided by a local US Composting Council Seal of Testing Assurance (STA) member. A copy of the provider’s most recent independent STA test report shall be submitted to and approved by the Owner prior to delivery of BSM to the project site. iv. Compost material shall also meet the following criteria: a. 100 percent of the material shall pass through a 1/2 inch screen b. PH of the material shall be between 6.0 and 8.4 c. Moisture content shall be between 35 and 50 percent d. Maturity greater than 80 percent (maturity indicator expressed as percentage of germination/vigor, 80+/80+) e. Maturity indicator expressed as Carbon to Nitrogen ration < 12 f. Maturity indicator expressed as AmmoniaN/NitrateN Ratio <4 g. Minimum organic matter shall be 40 percent dry weight basis h. Soluble salt content shall be no greater than 5500 parts per million or 0-5 mmhos/cm i. Phosphorus content shall be no greater than 325 parts per million j. Heavy metals (trace) shall not exceed 0.5 parts per million k. Chemical contaminants: meet or exceed US EPA Class A standard, 40 CFR 503.13, Tables 1 & 3 levels l. Pathogens: meet or exceed US EPA Class A standard, 40 CFR 503.32(a) levels Pea gravel shall be clean and graded, washed river run gravel, ASTM C33, size no. 7. Pea gravel shall be free of plant material. Subsection 605.05 shall include the following: Pea gravel shall be placed to the thickness shown in the plans, without compaction. BSM shall be spread in even layers, not to exceed 9 inches in depth. BSM shall not be compacted. Subsection 605.07 shall include the following: Bioretention Sand Media will be measured by the square foot of material installed and accepted, including the pea gravel, aggregate base, and sand layer. Subsection 605.08 shall include the following: Payment will be made under: Pay Item Pay Unit Surface Sand Filter LF Payment shall be full compensation for all work and materials required to complete the bioretention sand media including REVISIONS OF SECTION 623 IRRIGATION SYSTEM Section 623 of the Standard Specifications is hereby revised for this project as follows: Subsection 623.04 shall include the following: Contractor shall install a Rain Bird ESP-LXD-LMM-LXMMPED W/IQ NCC-GP Control system as specified in the irrigation plans & details per City of Fort Collins standards. Coordinate with City of Fort Collins as required. Attach wire markers to the ends of control wires inside the controller unit housing. Label wires with the identification number (see drawings) of the remote control valve to which the control wire is connected. Subsection 623.09 shall include the following: The irrigation dripline shall have factory installed pressure-compensating, inline emitters installed every 12-24 inches. The flow rate from each installed inline emitter shall be 0.26, 0.4, 0.6 or 0.9 gallons per hour when inlet pressure is between 8.5 & 60 psi. The inline diaphragm shall have a pressure regulating diaphragm with a spring action allow it to self-rise if there is a plug at the outlet hole. The bend radius shall be 3-inches whether bending the tubing with the bend of the coil or against it. The inlet shall be raised off the inside tube wall to minimize dirt intrusion. Subsection 623.10 shall include the following: Plastic and Copper water lines listed below shall be paid for under section 619. Subsection 623.10 (a) shall include the following: Identify all pipe with the following indelible markings: (a) Manufacturer’s Name. (b) Nominal pipe size. (c) Schedule of class. (d) Pressure rating (e) NSF (National Sanitation Foundation) seal of approval. (f) Date of extrusion. Delete subsection 623.10 (b) and replace with the following: (b) Lateral Line Pipe. Lateral line pipe shall be Class 200 PVC manufactured from virgin polyvinyl chloride (PVC) compound in accordance with ASTM standards D2241 and D1784, cell classification 12454-B, Type I, Grade I. Fittings shall be standards weight Schedule 40 injection molded PVC conforming to ASTM D1784 and D2466, cell classification 12454-B. Subsection 623.10 (c) replace with the following: Drip irrigation laterals to pots, use UV radiation resistant polyethylene pipe manufactured from Prime Union Carbide G-resin 7510 Natural 7 manufactured by Union Carbide or a Union Carbide Licensee with a minimum of 2% carbon black, and minimum nominal pipe ID dimension of 0.810" for 3/4 inch pipe, or approved equal. Delete Subsections 623.10 (d), and 623.10 (e). Subsection 623.10 shall include the following: (f) Copper pipe: Pressure supply line from point-of-connection through backflow preventer shall be Type "K" rigid conforming to ASTM Standard B88. Use wrought copper or cast bronze fittings, soldered or threaded per the installation details. Use a 95% tin and 5% antimony solder. (g) Joint Cement and Primer –Weldon P-70 Primer and Weldon 711 Gray Glue or Weldon 725 Wet and Dry Glue will be allowed, or approved equal. (h) Irrigation Roadway and sidewalk sleeves. Lateral line pipe shall be Class 200 PVC manufactured from virgin polyvinyl chloride (PVC) compound in accordance with ASTM standards D2241 and D1784, cell classification 12454-B, Type I, Grade I. Delete Subsections 623.1 (c), 623.11 (d), and 623.11 (e). Delete Subsection 623.11 (f) and replace with the following: (f) Mainline Isolation Valves. Gate valves for 3/4-inch through 2-1/2-inch Pipe – Brass construction; solid wedge, IPS threads, and non-rising stem with square operating nut. Delete Subsection 623.13. Subsection 623.23 First Sentence shall read as follows: “After installation of…for leaks after a minimum 120 PSI static pressure…for four hours in a hydro static test.” Subsection 623.23 shall include the following: The contractor shall conduct pressure tests in the presence of the Engineer or Engineer’s representative. The Contractor shall give 72 hour notice prior to testing. The test is acceptable if no loss of pressure is evident during the test period. The Contractor shall retest system until test pressure can be maintained for the duration of the test. Subsection 623.26 shall include the following: The Contractor shall provide a valve sequencing chart for each automatic controller installed. Charts shall not be prepared until as-builts plans have been approved by the Engineer. Charts shall be installed on the automatic controller door with photo reduction prints of the as-builts plans. Reduction prints shall be kept to the largest size possible to retain full legibility. A readable print of the as-built plans shall be provided showing the area covered by the automatic controller. The area of coverage of each control valve shall be identified using a distinctly different pastel color, drain over the entire area of coverage. In Subsection 623.30, second paragraph, delete item (4) and replace with the following: (4) Two of each Type of Valve box Subsection 623.30 shall include the following: One set of special tools required for removal, disassembling and adjusting each type of sprinkler head and valve installed. Two sets keys for each automatic controller enclosure. In Subsection 623.32, delete the second and third paragraphs. Under Subsection 623.33, add the following items: Payment shall be a lump sum for all irrigation work. The following shall be added to the specifications: PART 1: GENERAL 1.1 SCOPE Furnish all labor, materials, supplies, equipment, tools and transportation, and perform all operations in connection with and reasonably incidental to the complete installation of the irrigation system, and guarantee/warranty as shown on the drawings, the installation details, and as specified herein. Items of work specifically included are: A. Procurement of all applicable licenses, permits, and fees. B. Coordination of Utility Locates (“Call Before You Dig”). C. Verification of existing static pressure. D. Verification of existing available flow rate. E. Connection of electrical power supply to the irrigation control system. F. The contractor is responsible for maintaining all plant material on existing irrigation systems impacted by construction during project. G. Maintenance period. H. Irrigation Warranty I. Sleeving for irrigation pipe and wire. 1.2 WORK NOT INCLUDED Items of work specifically excluded or covered under other sections are: A. Payment of all development, plant investment, or any other fees and permits associated with the purchase and installation of the tap. B. Excavation, installation, and backfill of tap into municipal water line. C. Excavation, installation, and backfill of water meter and vault. D. Provision of electrical power supply to the irrigation control system. 1.3 RELATED WORK A. Division 1 - General Requirements: B. Division 2 - Site Work: 1) Section 02920 - Fine Grading and Soil Preparation. 2) Section 02931 - Seeding. 3) Section 02932 - Sodding. 4) Section 02950 - Trees, Plants and Ground Cover. 1.4 SUBMITTALS A. Submit samples under provisions of contract documents. B. Deliver four (4) copies of all required submittals to the Owners’ Representative within 15 days from the date of Notice to Proceed. C. Materials List: Include pipe, fittings, mainline components, water emission components, control system components. Quantities of materials need not be included. D. Manufacturers' Data: Submit manufacturers' catalog cuts, specifications, and operating instructions for equipment shown on the materials list. E. Shop Drawings: Submit shop drawings called for in the installation details. Show products required for proper installation, their relative locations, and critical dimensions. Note modifications to the installation detail. F. Project Record Drawings: Submit project record (as-built) drawings to Owner prior to commencement of maintenance period. 1.5 RULES AND REGULATIONS A. Work and materials shall be in accordance with the latest edition of the National Electric Code, the Uniform Plumbing Code as published by the Western Plumbing Officials Association, and applicable laws and regulations of the governing authorities. B. When the contract documents call for materials or construction of a better quality or larger size than required by the above-mentioned rules and regulations, provide the quality and size required by the contract documents. C. If quantities are provided either in these specifications or on the drawings, these quantities are provided for information only. It is the Contractor's responsibility to determine the actual quantities of all material, equipment, and supplies required by the project and to complete an independent estimate of quantities and wastage. 1.6 TESTING A. Notify the Owners’ Representative three days in advance of testing. B. Pipelines jointed with rubber gaskets or threaded connections may be subjected to a pressure test at any time after partial completion of backfill. Pipelines jointed with solvent-welded PVC joints shall be allowed to cure at least 24 hours before testing. C. Subsections of mainline pipe may be tested independently, subject to the review of the Owners’ Representative. D. Furnish clean, clear water, pumps, labor, fittings, and equipment necessary to conduct tests or retests. E. Hydrostatic Pressure Test: 1) Subject mainline pipe to a hydrostatic pressure equal to 120 PSI for two hours. Test with mainline components installed. A 2 PSI pressure variation is allowed. 2) Backfill to prevent pipe from moving under pressure. Expose couplings and fittings. 3) Leakage will be detected by visual inspection. Replace defective pipe, fitting, joint, valve, or appurtenance. Repeat the test until the pipe passes test. a. Cement or caulking to seal leaks is prohibited. F. Operational Test: 1) Activate each remote control valve in sequence from controller. The Owners’ Representative will visually observe operation, water application patterns, and leakage. 2) Replace defective remote control valve, solenoid, wiring, or appurtenance to correct operational deficiencies. 3) Replace, adjust, or move water emission devices to correct operational or coverage deficiencies. 4) Replace defective pipe, fitting, joint, valve, sprinkler, or appurtenance to correct leakage problems. Cement or caulking to seal leaks is prohibited. 5) Repeat test(s) until each lateral passes all tests. G. Signal Wire: 1) Test for leaks to ground per manufacturer's recommendations. Test results must meet or exceed manufacturer's guidelines for acceptance. 2) Replace defective wire, underground splices, or appurtenances. Repeat the test until the manufacturer's guidelines are met. 1.7 CONSTRUCTION REVIEW The purpose of on-site reviews by the Owners’ Representative is to periodically observe the work in progress and the Contractor's interpretation of the construction documents and to address questions with regards to the installation. A. Scheduled reviews such as those for irrigation system layout or testing should be scheduled with the Owners’ Representative as required by these specifications. B. Impromptu reviews may occur at any time during the project. C. Final review will occur at the completion of the irrigation system installation and Record (As- Built) Drawing submittal. 1.8 GUARANTEE/WARRANTY AND REPLACEMENT The purpose of this guarantee/warranty is to insure that the Owner receives irrigation materials of prime quality, installed and maintained in a thorough and careful manner. A. For a period of two years from commencement of the formal maintenance period, guarantee/warranty irrigation materials, equipment, and workmanship against defects. Fill and repair depressions. Restore landscape or structural features damaged by the settlement of irrigation trenches or excavations. Repair damage to the premises caused by a defective item. Make repairs within seven days of notification from the Owners’ Representative. B. Contract documents govern replacements identically as with new work. Make replacements at no additional cost to the contract price. C. Guarantee/warranty applies to originally installed materials and equipment and replacements made during the guarantee/warranty period. PART 2: MATERIALS 2.1 QUALITY Use materials which are new and without flaws or defects of any type, and which are the best of their class and kind. 2.2 SUBSTITUTIONS Pipe sizes referenced in the construction documents are minimum sizes, and may be increased at the option of the Contractor. 2.3 SLEEVING A. Install separate sleeve beneath paved areas to route each run of irrigation pipe or wiring bundle. B. Sleeving material beneath pedestrian pavements shall be PVC Class 200 pipe with solvent welded joints. C. Sleeving beneath drives and streets shall be PVC Class 200 pipe with solvent welded joints. D. Sleeving diameter: as indicated on the drawings and installation details or equal to twice that of the pipe or wiring bundle. 2.4 PIPE AND FITTINGS A. Mainline Pipe and Fittings: 1) Use rigid, unplasticized polyvinyl chloride (PVC) 1120, 1220 National Sanitation Foundation (NSF) approved pipe, extruded from material meeting the requirements of Cell Classification 12454-A or 12454-B, ASTM Standard D1784, with an integral belled end. 2) Use Class 200, SDR-21, rated at 200 PSI, conforming to the dimensions and tolerances established by ASTM Standard D2241. Use PVC pipe rated at higher pressures than Class 200 in the case of small nominal diameters which are not manufactured in Class 200. a. Use solvent weld pipe for mainline pipe with a nominal diameter less than 3-inches or where a pipe connection occurs in a sleeve. Use Schedule 40, Type 1, PVC solvent weld fittings conforming to ASTM Standards D2466 and D1784. Use primer approved by the pipe manufacturer. Solvent cement to conform to ASTM Standard D2564. B. Lateral Pipe and Fittings: 1) For drip irrigation laterals, use UV radiation resistant polyethylene pipe manufactured from Prime Union Carbide G-resin 7510 Natural 7 manufactured by Union Carbide or a Union Carbide Licensee with a minimum of 2% carbon black, and minimum nominal pipe ID dimension of 0.810" for 3/4 inch pipe, or approved equal Use PVC/compression line fittings compatible with the drip lateral pipe. C. Specialized Pipe and Fittings: 1) Assemblies calling for pre-fabricated double swing joints shall utilize LASCO Unitized swing joints or approved equal. Swing joints shall be rated at 315 psi, and use O-ring and street elbow construction. 2) Low Density Polyethylene Hose: a. Use pipe specifically intended for use as a flexible swing joint. Inside diameter: 0.490+0.010 inch. Wall thickness: 0.100+0.010 inch. Color: Black. b. Use spiral barb fittings supplied by the same manufacturer as the hose. 3) Assemblies calling for threaded pipe connections shall utilize PVC Schedule 80 nipples and PVC Schedule 80 threaded fittings. 4) Joint sealant: Use only Teflon-type tape pipe joint sealant on plastic threads. Use non-hardening, nontoxic pipe joint sealant formulated for use on water-carrying pipes on metal threaded connections. D. Marking Tape: 1) Mainline Pipe - Christy underground I.D. tape TA-DT-12-P-NPW, or approved equal. 2.5 MAINLINE COMPONENTS A. Main System Shutoff Valve: As per local practice and in compliance with local code, or approved equal. B. Winterization Assembly: As per local practice and in compliance with local code, or approved equal. C. Backflow Prevention Assembly: As presented in the installation details. D. Master Valve Assembly: As presented in the installation details. E. Isolation Gate Valve Assembly: As presented in the installation details. Install a separate valve box over a 3-inch depth of 3/4-inch gravel for each assembly. F. Quick Coupling Valve Assembly: Double swing joint arrangement as presented in the installation details. 2.6 DRIP IRRIGATION COMPONENTS A. Remote Control Valve (RCV) Assembly for Drip Laterals: As presented in the installation details. Use wire connectors and waterproofing sealant to join control wires to solenoid valves. Use standard Christy I.D. tags with hot-stamped black characters on a yellow background. Install a separate valve box over a 3-inch depth of 3/4-inch gravel for each assembly. Adjust flow control per manufacturer’s recommendations prior to use. B. Drip Emitter Assembly: 1) Barb-mounted, vortex and/or pressure compensating emitter device as presented in the installation details. The device shall be Rain Bird Xeri-bug XB-10-PC series. 2) Install emitter types and quantities on the following schedule: a. Ground cover plant: 1 single outlet emitter each or 1 single outlet emitter per square foot of planting area, whichever is less. b. Shrub: 2 single outlet emitters each. c. Tree: 4 single outlet emitters each or 1 multi-outlet emitter each (with 4 outlets open). 3) Use 1/4-inch diameter flexible plastic tubing to direct water from emitter outlet to emission point. Length of emitter outlet tubing shall not exceed five feet. Secure emitter outlet tubing with tubing stakes. C. Flush Cap Assembly: As presented in the installation details or approved equal. Locate at the end of each drip irrigation lateral pipe. Install a separate valve box over a 3-inch depth of 3/4- inch gravel for each assembly. D. Operation Indicator Assembly: As presented in the installation details. Locate at the end(s) of each drip valve run in a conspicuous place to confirm operation of drip zone. Stake securely to keep upright and visible when operating. 2.7 CONTROL SYSTEM COMPONENTS A. Irrigation Controller Unit: 1) As presented in the drawings and installation details, no approved equal 2) Primary surge protection arrestors: Model LPP-K, manufactured by Rain Bird Sprinkler Manufacturing Corporation, Glendora, California. 3) Valve output surge protection arrestors: Model LPV-K, manufactured by Rain Bird Sprinkler Manufacturing Corporation, Glendora, California. 4) Lightning protection: 8-foot copper-clad grounding rod. 5) Wire markers: Pre-numbered or labeled with indelible non-fading ink, made of permanent, non-fading material. B. Instrumentation: 1) As presented in the drawings and installation details. 2) Rain Sensor: RSD-CEx as manufactured by Rain Bird. 3) Flow Sensor: Per Legend as manufactured by Rain Bird. C. Control Wire: 1) Use #14 AWG wires for signal to valves, or approved equal. Install per Rain Bird specifications 2) Splices: Use wire connector with waterproof sealant. Wire connector to be of plastic construction consisting of two (2) pieces, one piece which snap locks into the other, 3M DBY-6, King DBYN-600, Blazing BVS, or approved equal. 3) Encase wiring not located near PVC irrigation pipe in PVC Schedule 40 electrical conduit. 4) Warning tape: Inert plastic film highly resistant to alkalis, acids, or other destructive chemical components likely to be encountered in soils. Three inches wide, colored yellow, and imprinted with "CAUTION: BURIED ELECTRIC LINE BELOW." 2.8 OTHER COMPONENTS A. Tools and Spare Parts: Provide operating keys, servicing tools, test equipment, other items, and spare parts indicated in the General Notes of the drawings. PART 3: EXECUTION 3.1 INSPECTIONS AND REVIEWS A. Site Inspections: 1) Verify site conditions and note irregularities affecting work of this section. Report irregularities to the Owners’ Representative prior to beginning work. 2) Beginning work of this section implies acceptance of existing conditions. 3) Contractor will be held responsible for coordination between landscape and irrigation system installation. 4) Landscape material locations shown on the Landscape Plan shall take precedence over the irrigation system equipment locations. If irrigation equipment is installed in conflict with the landscape material locations shown on the Landscape Plan, the Contractor will be required to relocate the irrigation equipment, as necessary, at Contractor’s expense. B. Utility Locates ("Call Before You Dig"): 1) Arrange for and coordinate with local authorities the location of all underground utilities. 2) Repair any underground utilities damaged during construction. Make repairs at no additional cost to the contract price. C. Irrigation System Layout Review: Irrigation system layout review will occur after the staking has been completed. Notify the Owners’ Representative two days in advance of review. Modifications will be identified by the Owners’ Representative at this review. 3.2 LAYOUT OF WORK A. Stake out the irrigation system. Items staked include: sprinklers, pipe, control valves, manual drains, controller, and isolation valves. B. Install all mainline pipe and mainline components inside of project property lines. 3.3 EXCAVATION, TRENCHING, AND BACKFILLING A. Excavate to permit the pipes to be laid at the intended elevations and to permit work space for installing connections and fittings. B. Minimum cover (distance from top of pipe or control wire to finish grade): 1) 24-inch over mainline pipe and over electrical conduit. 2) 26-inch over control wire. 3) 18-inch over lateral pipe to sprinklers and bubblers. 4) 8-inch over drip lateral pipe in turf. 5) 3-inch minimum mulch cover over drip lateral pipe in planting beds downstream of drip system zone control valves. PVC UV radiation resistant lateral pipe shall be installed directly on the soil surface under landscape fabric. C. Backfill only after lines have been reviewed and tested. D. Excavated material is generally satisfactory for backfill. Backfill shall be free from rubbish, vegetable matter, frozen materials, and stones larger than 2-inches in maximum dimension. Remove material not suitable for backfill. Backfill placed next to pipe shall be free of sharp objects which may damage the pipe. Stones larger than 1-inch maximum dimension are not permitted in first (deepest) 6-inches of backfill. E. Backfill unsleeved pipe and sleeves in either of the following manners: 1) Backfill and puddle the lower half of the trench. Allow to dry 24 hours. Backfill the remainder of the trench in 6-inch layers. Compact to density of surrounding soil. 2) Backfill the trench by depositing the backfill material equally on both sides of the pipe in 6- inch layers and compacting to the density of surrounding soil. F. Enclose pipe and wiring beneath roadways, walks, curbs, etc. in sleeves. Minimum compaction of backfill for sleeves shall be 95% Standard Proctor Density, ASTM D698- 78. Conduct one compaction test for each sleeved crossing. Costs for such testing and any necessary retesting shall be borne by the Contractor. Use of water for compaction around sleeves, "puddling", will not be permitted. G. Dress backfilled areas to original grade. Incorporate excess backfill into existing site grades. Dispose of excess backfill off site. H. Where utilities conflict with irrigation trenching and pipe work, contact the Owners’ Representative for trench depth adjustments and alignment. 3.4 SLEEVING AND BORING A. Install sleeving at a depth which permits the encased pipe or wiring to remain at the specified burial depth. B. Extend sleeve ends six inches beyond the edge of the paved surface. Cover pipe ends and mark with stakes. Mark concrete with a chiseled "Z" at sleeve end locations. C. Bore for sleeves under obstructions which cannot be removed. Employ equipment and methods designed for horizontal boring. 3.5 ASSEMBLING PIPE AND FITTINGS A. General: 1) Keep pipe free from dirt and pipe scale. Cut pipe ends square and debur. Clean pipe ends. 2) Keep ends of assembled pipe capped. Remove caps only when necessary to continue assembly. B. Mainline Pipe and Fittings: 1) Use only strap-type friction wrenches for threaded plastic pipe. 2) PVC Solvent Weld Pipe: a. Use primer and solvent cement. Join pipe in a manner recommended by the manufacturer and in accordance with accepted industry practices. b. Cure for 30 minutes before handling and 24 hours before allowing water in pipe. c. Snake pipe from side to side within the trench. 3) Fittings: The use of cross type fittings is not permitted. C. Lateral Pipe and Fittings: 1) Use only strap-type friction wrenches for threaded plastic pipe. 2) UV Radiation Resistant Polyethylene Pipe: a. Join pipe in the manner recommended by manufacturer and in accordance with accepted industry practices. b. Snake pipe from side to side within the trench, on the soil surface, and hold in place with tubing stakes spaced every five feet. 3) Fittings: The use of cross type fittings is not permitted. D. Specialized Pipe and Fittings: 1) Copper Pipe: a. Buff surfaces to be joined to a bright finish. Coat with solder flux. b. Solder so that a continuous bead shows around the joint circumference. 2) Insert a dielectric union wherever a copper-based metal (copper, brass, bronze) and an iron-based metal (iron, galvanized steel, stainless steel) are joined. 3) Pre-fabricated double swing joints: Install per manufacturer's recommendations. 4) Low Density Polyethylene Hose: Install per manufacturer's recommendations. 5) PVC Threaded Connections: a. Use only factory-formed threads. Field-cut threads are not permitted. b. Use only Teflon-type tape. c. When connection is plastic-to-metal, the plastic component shall have male threads and the metal component shall have female threads. 6) Make metal-to-metal, threaded connections with Teflon-type tape applied to the male threads only. 3.6 INSTALLATION OF MAINLINE COMPONENTS A. Main System Shut Off Valve: Install where indicated on the drawings. B. Winterization Assembly: Install where indicated on the drawings. C. Backflow Prevention Assembly: Install where indicated on the drawings. Install assembly so that its elevation, orientation, access, and drainage conform to the manufacturer's recommendations and applicable health codes. D. Master Valve Assembly: Install where indicated on the drawings. E. Isolation Gate Valve Assembly: 1) Install where indicated on the drawings. 2) Locate at least 12-inches from and align with adjacent walls or edges of paved areas. F. Quick Coupling Valve Assembly: Install where indicated on the drawings. 3.7 INSTALLATION OF DRIP IRRIGATION COMPONENTS A. Remote Control Valve (RCV) Assembly for Drip Laterals: 1) Flush mainline pipe before installing RCV assembly. 2) Locate as shown on the drawings. Wire connectors and waterproof sealant shall be used to connect control wires to remote control valve wires. Connectors and sealant shall be installed as per the manufacturer's recommendations. 3) Install only one RCV to valve box. Locate at least 12-inches from and align with nearby walls or edges of paved areas. Group RCV assemblies together where practical. B. Drip Emitter Assembly: 1) Locate as shown on the drawings and installation details. 2) Flush lateral pipe before installing emitter assembly. 3) Cut emitter outlet distribution tubing square. 4) Use tools and techniques recommended by the manufacturer. Make openings for barb-mounted emitters with the emitter manufacturer's hole- punching tool. C. Flush Cap Assembly: Install at the end of each drip irrigation lateral pipe as shown on the installation details. D. Operation Indicator Assembly: Install at the end(s) of each drip valve run in a conspicuous place to confirm operation Stake securely to keep upright and visible when operating. E. Pressure Adjustment Procedure: 1) Determine which emitter has the least outlet pressure; this is the critical emitter. 2) Set discharge pressure of RCV such that the critical vortex emitter has a pressure of 15 PSI + 2 PSI and/or the critical pressure compensating emitter has a pressure of 25 PSI + 5 PSI. Measure with pressure gauge attached to critical emitter. 3) Identify the critical emitter for remaining zone valves. 3.8 INSTALLATION OF CONTROL SYSTEM COMPONENTS A. Irrigation Controller Unit: 1) The location of the controller unit as depicted on the drawings is approximate; the Owners’ Representative will determine the exact site location. 2) Enclosure: The control unit pedestal enclosure shall be powder coated to blend in with surroundings. Contact Owner for preferred color of controller pedestal enclosure. 3) Lightning protection: Ground rods are to have a minimum diameter of 5/8” and a minimum length of 10 feet. These are to be driven into the ground in a vertical position or an oblique angle not to exceed 45 degrees at a location 10 feet from the electronic equipment, the ground plate, or the wires and cables connected to said equipment, as shown in the irrigation details. The rod is to be stamped with the UL logo. A 6 AWG solid bare copper wire (about 12 feet long) shall be connected to the ground rod by the installer using a Cadweld GR1161G ”One-Shot” welding kit [Paige Electric part number 1820037.] This wire shall be connected to the electronic equipment ground lug as shown in the detail above. 4) Lightning protection: Provide on all remote control valve wiring as recommended by the manufacturer. Provide other components such as ground rod, grounding wire, etc., to manufacturer's recommendations. 5) Install primary surge protection arrestors on incoming power lines. 6) Attach wire markers to the ends of control wires inside the controller unit housing. Label wires with the identification number (see drawings) of the remote control valve to which the control wire is connected. 7) Install a 120-volt, 20 amp switched and grounded 3-prong receptacle with GFCI inside the controller unit housing. 8) Connect control wires to the corresponding controller terminal. B. Instrumentation: 1) Install sensors per the installation details and manufacturer's recommendations. Install at locations shown on the drawings. 2) Install electrical connections between irrigation controller and sensors per manufacturer's recommendations. C. Control Wire: 1) Bundle control wires where two or more are in the same trench. Bundle with pipe wrapping tape spaced at 10-foot intervals. 2) Provide a 24-inch excess length of wire in an -inch diameter loop at each 90 degree change of direction, at both ends of sleeves, and at 100-foot intervals along continuous runs of wiring. Make wiring loop by turning control wire 5 turns around 1-inch pipe. Coil 24-inch length of wire within each remote control valve box. 3) If a control wire must be spliced, make splice with wire connectors and waterproof sealant, installed per the manufacturer's instructions. Locate splice in a valve box which contains an irrigation valve assembly, or in a separate 6-inch round valve box. Use same procedure for connection to valves as for in-line splices. 4) Unless noted on plans, install wire parallel with and under PVC mainline pipe. If wire is installed adjacent to section of metal pipe, separate wire from pipe minimum of 6-inches and install wire in PVC conduit. 5) Encase wire not installed with PVC mainline pipe in electrical conduit. 3.9 INSTALLATION OF OTHER COMPONENTS A. Tools and Spare Parts: 1) Prior to the Pre-Maintenance Review, supply to the Owner operating keys, servicing tools, test equipment, and any other items indicated on the drawings. 2) Prior to Final Review, supply to the Owner the spare parts indicated in the General Notes on the drawings. B. Other Materials: Install other materials or equipment shown on the drawings or installation details to be part of the irrigation system, even though such items may not have been referenced in these specifications. 3.10 PROJECT RECORD (AS-BUILT) DRAWINGS A. Maintain on-site and separate from documents used for construction, one complete set of contract documents as Project Documents. Keep documents current. Do not permanently cover work until as-built information is recorded. B. Record pipe and wiring network alterations. Record work which is installed differently than shown on the construction drawings. Record accurate reference dimensions, measured from at least two permanent reference points, of each irrigation system valve, each backflow prevention device, each controller or control unit, each sleeve end, each stub-out for future pipe or wiring connections, and other irrigation components enclosed within a valve box. C. Prior to Final Review, purchase from the Owners’ Representative a electronic copy of the drawings. Duplicate information contained on the project drawings maintained on site. Label each sheet "Record Drawing". Completion of the Record Drawings will be a prerequisite for the Final Review. 3.11 MAINTENANCE A. Upon completion of Final Review, maintain irrigation system for a duration of 30 calendar days. Make periodic examinations and adjustments to irrigation system components so as to achieve the most desirable application of water. B. Contractor shall set up and attend at least one meeting with the City and final Operator (if different than the City) of the system to turn over current as-built drawings, extra equipment, tools, irrigation schedules and information needed for the proper operation of the irrigation system. The City and final Operator(if different than the City) may request a second meeting before the maintenance period is over to resolve any questions and issues that arise. The initial meeting shall occur no later than seven (7) days into the maintenance period. C. Following completion of the Contractor's maintenance period, the Owner will be responsible for maintaining the system in working order during the remainder of the guarantee/warranty period, for performing necessary minor maintenance, for trimming around sprinklers, for protecting against vandalism, and for preventing damage during the landscape maintenance operation. 3.12 IRRIGATION WARRANTY A. Contractor is responsible to make sure the system is fully functional from Notice to Proceed until Final Acceptance, including while the project is under construction. This responsibility shall remain intact through Final Acceptance. Final Acceptance cannot occur between October and May, Final Acceptance of the irrigation system cannot occur until the complete system can be tested and verified. 3.13 CLEAN-UP A. Upon completion of work, remove from the site all machinery, tools, excess materials, and rubbish. 23 REVISION OF SECTION 630 CONSTRUCTION ZONE TRAFFIC CONTROL Section 630 of the Standard Specifications is hereby revised for this project as follows: Subsection 630.01 shall include the following: All devices, signs, and temporary safety fencing (both orange plastic and chain link) necessary for the construction zone traffic control shall be included in the lump sum line item “Construction Zone Traffic Control”. A Secondary line item for flagging has been included in the project under the line item “Flagging”. This line item is intended for flagging for the construction zone traffic control for the project. Subsection 630.10 shall include the following after the first paragraph: The Contractor’s Superintendent and all others serving in a similar supervisory capacity shall have completed a CDOT-approved two-day Traffic Control Supervisor training as offered by the CCA. The one-day ATSSA Traffic Control Technician (TCT) training along with the two-day ATSSA Traffic Control Supervisor training will serve as an alternate. If the alternate is chosen, the Contractor shall provide written evidence that at least an 80 percent score was achieved in both of the two training classes. The certifications of completion or certifications of achievement for all appropriate staff shall be submitted to the Engineer at the preconstruction conference. If the Traffic Control Supervisor is replaced during the project, the Engineer shall be given a minimum of one (1) week notice and qualifications shall be submitted for approval of the Traffic Control Supervisor’s replacement. Subsection 630.10(a) shall include the following: For this project, a MHT shall be prepared and submitted for approval to the City Traffic Division by 12:00 noon, two working days prior to the commencement of work for simple lane closures. (Note: MHT’s for work done on Monday and Tuesday shall be submitted the previous Friday by 9:00 a.m.). Facsimiles of plans shall not be allowed. No phase of the construction shall start until the MHT has been approved. Failure to have an approved MHT shall constitute cause for the City to stop work, as well as the Contractor's forfeiture of payment for all work and materials at that location, with no adjustment in the contract time. Subsection 630.14 shall include the following: Additional flagging requested by others, including City Departments and utility representatives, must be approved by the Engineer prior to performing the work. Subsection 630.16 shall be revised as follows: The Contractor shall supply and pay all costs associated with the traffic control for this project. 24 REVISION OF SECTION 630 CONSTRUCTION ZONE TRAFFIC CONTROL The accepted quantities will be paid for at the contract unit price for each of the pay items listed below: Pay Item Pay Unit Flagging Hour Construction Zone Traffic Control Lump Sum Individual traffic control devices, labor required to erect and maintain traffic control in accordance with approved MHT’s, Traffic Control Supervisor, Traffic Control Management, and Traffic Control Inspection will not be measured and paid for separately, but shall be included in Construction Traffic Control, Lump Sum. The flaggers shall be provided with communication devices (no cell phones) when required. These devices will not be measured and paid for separately, but shall be included in the Work. The cost of batteries, electricity and/or fuel for all lighting or warning devices shall not be paid for separately but shall be considered subsidiary to the item and shall be included in the Work. Sandbags will not be measured and paid for separately, but shall be included in the Work. The Contractor may provide larger construction traffic signs than those typically used in accordance with the MUTCD, if approved; however, no additional payment will be made for the larger signs. The City shall not be responsible for any losses or damage due to theft or vandalism. Work Hours: Work hours are 7 AM to 6 PM, Monday through Friday. Extended hours and weekend work are anticipated and will be permitted with written approval from the Project Manager. Night time work shall be permitted with written approval from Project Manager. Work shall be permitted on holidays with written approval from the Project Manager. Work requests beyond working hours must be submitted to the Project Manager a minimum of (5) working days prior to the request date. Night and weekend work will be allowed with 5 days prior notice to the Project Manager. All costs associated with nighttime work will be incidental to the work. Work Zone Phasing: The Contractor shall submit Construction Phasing Plans to the City, for approval, prior to the start of construction. Work must be coordinated and phased in a logical manner with the current roadway contract work. The City will help facilitate coordination with other contractors. The Contractor is required to submit a traffic control plan to the city for approval. See Section 105 for more information regarding lane closures and construction coordination. Drawing Name: Revisions 1603 Oakridge Drive Fort Collins, CO 80525 (970) 223-7577 fax (970) 223-1827 Landscape Architecture Urban Design Graphic Design Checked by: NORTH 0 SCALE: Project: Client: Sheet Date: Sheet Number: Project Number: Drawn by: Designed by: MBM MBM RS COVER SHEET CS 03.20.15 1324 HORSETOOTH AND TIMBERLINE CITY OF FORT COLLINS CS COVER SHEET LANDSCAPE GRADING PLANS G1 GRADING PLAN G2 GRADING PLAN G3 GRADING PLAN G4 GRADING SECTIONS LANDSCAPE PLAN L1 LANDSCAPE PLAN L2 LANDSCAPE PLAN L3 LANDSCAPE PLAN L4 LANDSCAPE PLAN L5 LANDSCAPE DETAILS SITE DETAILS D1 SITE DETAILS D2 SITE DETAILS D3 FOUNDATION DETAILS IRRIGATION PLAN IR1.0 GENERAL NOTES AND LEGEND IR2.0 ELV W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W AUTOMATION WAY HORSETOOTH ROAD 1G, 1F, 1E 1E, 1G 1F, 2E 1D, 1B 1D, 1C 1C, 2D 1F, 2E BOULDERS INSTALLED DURING ROADWAY WORK, RE: CIVIL BOULDERS INSTALLED DURING ROADWAY WORK, RE: CIVIL ELV ELV ? ? ? ? ? W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W HORSETOOTH ROAD HORSETOOTH ROAD 1A, 1B 1B, 1D 2D, 1C 1C, 1A 1A 1A, 1B 1C, 1D 2E, 1F 1E 2E, 1G ELV ELV ? ? ? ? W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W HORSETOOTH ROAD 1A 1A,1C 1C,1B 1B,1C 1A 1C,1B 2G,2F,2E 2G,2F,2E 1B 2A 2G,2F,2E 1G,2F,2E 1B,1C 2F,1E 1E,1F,1G 2A BOULDERS INSTALLED DURING ROADWAY WORK, RE: CIVIL 1B ? ? W W W W W W W W W W W W W W W W W W W W W W W W W TIMBERLINE ROAD ELV ELV W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W 1A 1A 1C 1C 1A 1A 1C 1A 1A 2F,1E 1C,1B 2G,2F,2E 1G,1F,2E BOULDER INSTALLED DURING ROADWAY WORK, RE: CIVIL ELV ? ? ? ? W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W TIMBERLINE ROAD BIGHORN ROAD 1F,1G 2G,2F,1E 4B,2A 3A,4B 2G,2F,1E 2G,2F,2E 2G,2F,2E 1B,1C,1D 2C,1D 1E,1F,1G BOULDERS INSTALLED 6" MULCH CURB AND GUTTER 6" MULCH MEDIAN CURB CURB AND GUTTER 9" MULCH MEDIAN CURB CURB AND GUTTER 18" FINISH GRADE SHALL MEET TOP OF BOULDER BOULDER RETAINING WALL, SEE DETAIL 4 SHEET D1 MULCH MEDIAN CURB CURB AND GUTTER 18" MULCH MEDIAN CURB CURB AND GUTTER FINISH GRADE SHALL MEET TOP OF BOULDER BOULDER RETAINING WALL, SEE DETAIL 4 SHEET D1 Drawing Name: Revisions 1603 Oakridge Drive Fort Collins, CO 80525 (970) 223-7577 fax (970) 223-1827 Landscape Architecture Urban Design Graphic Design Checked by: NORTH 0 SCALE: Project: Client: Sheet Date: Sheet Number: Project Number: Drawn by: Designed by: SEE DETAIL MBM MBM RS GRADING SECTIONS G4 03.20.15 1324 HORSETOOTH AND TIMBERLINE CITY OF FORT COLLINS MEDIAN SECTION 3 3 SCALE: 3/4" = 1'-0" ELV W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W AUTOMATION WAY 7 NE LT 10 CA IN 10 GE RO 7 PA VI 5 PY CA 11 RH AA 13 GE RO 5 HE PA 5 HE PA 9 CH NA 4 QU RO 2 UL JA 10' TYP. HORSETOOTH ROAD 10 CH NA ELV ELV ? ? ? ? ? W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W HORSETOOTH ROAD 1 TI CO ELV ELV ? ? ? ? W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W 2 QU MA 1 TI CO 1 PY CA 1 AM CA 9 AS TU 5 QU CS 10 PO SN 10 LI SP 14 CA IN 16 NE LT 5 PY CA 11 PA VI 5 HE PA 10 LI SP 11 BO GR 10 CO VE 10 RH AA 5 PY CA 10' TYP. 10' TYP. 12 RH AA 15 AL MO ELV ELV W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W ELK ROAD 1 QU MA 9 AM CA 5 PY CA 8 BO GR 1 CO VE 11 PA VI 10 LI SP 8 PO SN 5 QU CS 14 AS TU 11 PA VI 14 AS TU 9 AM CA 5 PY CA 12 LI SP 14 PA VI 14 LI SP 9 HE PA 12 SE AJ 16 CA IN 16 RH AA 3 PY CA 17 AL MO 26 DE CE 10 PE AF TIMBERLINE ROAD ELV ? ? ? ? W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W ELV ? ? ? ? ? ? W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W 22 FE BB FOUNDATION A, TF 52.50 4 HE PA SCULPTURE, RE: ARTIST 3 BO GR D1 4 BOULDER RETAINING WALL EOC 52.20 BASE OF TREE 54.16 EFG 53.96 APPX INV 51.75 APPX INV 52.98 EFG 53.15 EFG 53.77 EOC 52.60 APPX FL 51.53 APPX FL 53.32 FOUNDATION B, TF 54.20 TB 54.20 LID SWALE SOIL SECTION BS 52.12 EOC 54.12 EOC 52.10 SCULPTURE, RE: ARTIST EOC 51.56 EFG 52.99 BASE OF TREE 52.66 BASE OF TREE 53.07 TB 53.50 4952 4953 36" TO 48" 6' MIN. 2 TIMES ROOTBALL DIA. MULCH PER PLAN SPECIFIED BACKFILL MATERIAL, WATER AND TAMP TO REMOVE AIR POCKETS CONSTRUCT WATERING RING AROUND SHRUB AT EDGE OF PLANTING PIT TO CONTAIN WATER TO A DEPTH OF 2" 2X ROOTBALL DIAMETER SCARIFY SIDES AND BOTTOM GENERAL TREE PLANTING NOTES 1. PRUNE ONLY CROSSOVER LIMBS, CO-DOMINANT LEADERS, AND BROKEN OR DEAD BRANCHES. SOME INTERIOR TWIGS AND LATERAL BRANCHES MAY BE PRUNED; HOWEVER, DO NOT REMOVE THE TERMINAL BUDS OF BRANCHES THAT EXTEND TO THE EDGE OF THE CROWN. 2. MARK NORTH SIDE OF THE TREE IN THE NURSERY AND ROTATE TREE TO FACE NORTH AT THE SITE WHENEVER POSSIBLE. TREES WHOSE NORTH ORIENTATION IS NOT CHANGED FROM THE NURSERY DO NOT NEED TO BE WRAPPED, EXCEPT TREES WITH VERY THIN BARK. 3. EACH TREE SHALL BE PLANTED SUCH THAT THE TRUNK FLARE IS VISIBLE AT THE TOP OF THE ROOT BALL. DO NOT COVER THE TOP OF THE ROOT BALL WITH SOIL. 4. SET TOP OF ROOT BALL FLUSH WITH GRADE OR 1"-2" HIGHER IN SLOWLY DRAINING SOILS. 5. DO NOT PLACE MULCH IN CONTACT WITH TREE TRUNK. 6. PLACE SPECIFIED MULCH IN TREE PLANTING RINGS TO THE DEPTH SPECIFIED, UNLESS OTHERWISE INICATED. 7. IN SEEDED AREAS, HOLD SEED BACK TO A MINIMUM 36" DIA. CIRCLE. FORM A 4" HIGH EARTH SAUCER BEYOND EDGE OF ROOT BALL. MULCH PLANTING PIT. 8. STAKE DECIDUOUS AND CONIFEROUS TREES. 9. TREE STAKES TO BE DRIVEN OUTSIDE OF ROOT BALL. 1" WIDE FABRIC WEBBING WITH GROMMETS & GALVANIZED WIRE OR CABLE, TWIST WIRE TO TIGHTEN. BREATHABLE PAPER OF FABRIC TREE WRAP APPLIED FROM TRUNK FLARE TO FIRST BRANCH. WRAP PAPER FROM BOTTOM UP WITH SUFFICIENT OVERLAP TO COVER BARK. USE MASKING TAPE TO SECURE. METAL 'T' STAKE WITH PROTECTIVE CAP. ADJUST TREE STAKE SO THAT TOP IS LEVEL WITH, OR JUST BELOW, FIRST BRANCHES. INSTALL 3' DIA. CEDAR WOOD MULCH RING AROUND BASE TO A DEPTH OF 4". TREES PLANTED IN SOD SHALL BE PLACED INSIDE A 36" DIA. ROLL TOP STEEL EDGING CIRCLE WITH WOOD MULCH, TREES PLANTED IN PLANTING AREAS SHALL HAVE A 36" DIA. CIRCLE WITH WOOD MULCH, NO EDGER BACKFILL MATERIAL REMOVE TWINE, ROPE, WIRE, AND BURLAP FROM ENTIRE ROOT BALL. TAMP SOIL AROUND ROOT BALL BASE FIRMLY WITH FOOT PRESSURE SO THAT ROOT BALL DOES NOT SHIFT UNEXCAVATED OR COMPACTED MOUND UNDER THE ROOT BALL TO PREVENT SETTLING. PROVIDE FERTILIZER PACKETS PLANT ROOT BALL SLIGHTLY ABOVE GRADE 6" RADIUS AROUND PERENNIALS AND ORNAMENTAL GRASSES TO BE MULCHED USING WOOD MULCH TO ALLOW FOR PLANT GROWTH NOTES: 1. BOULDERS SHALL BE INSTALLED PRIOR TO POURING ADJACENT CONCRETE. 2. BOULDERS SHALL BE (1) TON MIN. (APPX. 2' W x 4' L x 2' T). CONTRACTOR SHALL SUBMIT PHOTOS OF BOULDERS AT QUARRY FOR OWNER'S REPRESENTATIVE TO REVIEW AND APPROVE PRIOR TO DELIVERY ON SITE. INCLUDE A RULER IN THE PHOTO FOR SCALE. 3. LANDSCAPE ARCHITECT SHALL REVIEW AND APPROVE BOULDER LOCATIONS PRIOR TO PLACEMENT. LOCATIONS SHALL BE STAKED FOR REVIEW. 4. WHERE BOULDERS ARE ABUTTING, VERTICAL JOINTS BETWEEN BOULDERS SHALL NOT EXCEED 1". BURY BOULDERS 6" MIN. BELOW ADJACENT FINISHED GRADE 18" TOP OF BOULDER SHALL BE LEVEL WRAP WEED BARRIER FABRIC ON BACK SIDE OF BOULDER RETAINING WALL, OVERLAPPING ENDS 12" MIN. EXTEND WEED BARRIER FABRIC 6" UNDER BOULDER, 6" BEHIND BOULDER AS SHOWN. ADJACENT CONCRETE COMPACTED SUBGRADE PLANTING AREA 2" NOTES: 1. PLANTER SHALL BE: MANUFACTURER: KORNEGAY DESIGN MODEL: MUS-23 (23" T. X 46" DIA.) COLOR: DAVIS COLOR OMAHA TAN 2. REFER TO IRRIGATION DRAWINGS FOR LOCATION AND DEPTH OF SLEEVES FOR IRRIGATION PIPES. 3. OWNER'S REP. SHALL VERIFY PLANTER POT LOCATION AND ORIENTATION OF DRAINAGE HOLE PRIOR TO FINAL PLACEMENT OF PLANTER POT. 4. CONTRACTOR SHALL PROVIDE PLANTER POT DETAIL TO MANUFACTURER SO THAT DRAINAGE HOLE AND IRRIGATION LINE HOLE CAN BE LOCATED CORRECTLY. 3" 11 2" 2" PLANTER MIX TOPSOIL. HOLD PLANTING MIXTURE DOWN FROM TOP EDGE OF PLANTER POT, TYP. 1 1/4" DRAINAGE HOLE ON BOTTOM OF PLANTER POT TO BE CAST BY PLANTER POT MANUFACTURER. ALIGN WITH IRRIGATION STUB THROUGH CONCRETE FINISH SURFACE PLANTER POT, SEE LANDSCAPE PLAN FOR LOCATIONS. PLACE WEED BARRIER FABRIC BETWEEN PLANTING MIXTURE AND ROCK CHIPS, EXTEND WEED BARRIER FABRIC UP SIDES OF PLANTER POT, HOLD FABRIC DOWN FROM TOP OF PLANTER POT, TYP. IRRIGATION PIPE, TYP. RE: IRRIGATION DRAWINGS SUBGRADE, RE: CIVIL CONCRETE, SEE SITE PLAN 2" THICK LAYER OF 3/4" ROCK CHIPS FOR DRAINAGE WEED BARRIER FABRIC BASE PLATE, SEE DETAIL 1/8" MIN. RUBBER OR NYLON PAD BETWEEN BASE PLATE AND CONCRETE CONCRETE MOUNTING DETAIL (4) 1/2" X 6" STAINLESS STEEL WEJ ANCHORS, TYP., PAINT EXPOSED HARDWARE TO MATCH RAIL BASE PLATE DETAIL POST 3/4" DIA. BOLT HOLES 8" x 8" x 1/4" THICK ALUMINUM BASE 4" X 4" SQUARE ALUMINUM TUBE, 1/8" WALL THICKNESS, CAP TOP 3" SQUARE WEAVE WIRE MESH, ALUMINUM ALLOY, 0.25" WIRE DIAMETER, INTERCRIMP WEAVE 2" X 1" SQUARE ALUMINUM TUBE, 1/8" WALL THICKNESS BASE PLATE, SEE DETAIL CONCRETE MOUNTING, SEE DETAIL RAIL CURB. RE:CIVIL 8' O.C. TYP. 2" 3' MOUNTING BRACKETS, SEE DETAIL THIS SHEET 1' 1' 6" 6" PEDESTRIAN RAIL (STEEL)(SPECIAL) AND PEDESTRIAN RAILING (STEEL) GENERAL NOTES: 1. RAILINGS SHALL BE POWDERCOATED TEXTURED BLACK. 2. ALUMINUM CONNECTIONS SHALL BE MADE WITH A CONTINUOUS WELD AND CUTS SHALL FIT CONTOUR OF PIPE. GRIND WELDS SMOOTH LEAVING NO BURRS OR SHARP EDGES. 3. FABRICATOR/CONTRACTOR TO SUBMIT COLOR SAMPLES OF PROPOSED PAINT COLORS TO OWNER'S REPRESENTATIVE FOR REVIEW AND APPROVAL PRIOR TO FABRICATION OF RAIL PANELS. 4. FABRICATOR/CONTRACTOR TO SUBMIT MATERIAL SAMPLES OF PROPOSED MOUNTING HARDWARE (LOCK WASHERS/BOLTS/NUTS) TO OWNER'S REPRESENTATIVE FOR REVIEW AND APPROVAL PRIOR TO FABRICATION OF RAIL PANELS. 5. DETAILED AND DIMENSIONED SHOP DRAWINGS (INCLUDING THICKNESS, DIMENSIONS, MATERIALS, AND PROPOSED GRADES OF METAL) SHALL BE PROVIDED BY FABRICATOR/CONTRACTOR TO OWNER'S REPRESENTATIVE TO REVIEW AND APPROVE PRIOR TO FABRICATION. 6. THREADS OF BOLT SHALL BE SAWN OFF FLUSH WITH OUTSIDE EDGE OF NUT. 7. REFER TO LANDSCAPE PLAN FOR LOCATIONS OF RAILING. 8. RAILS AND TOP/BOTTOM PANEL FRAMES SHALL BE INSTALLED LEVEL, TYP. RAIL POSTS SHALL BE INSTALLED PLUMB, TYP. 9. CARRIAGE BOLTS WITH NUTS AND WASHERS SHALL BE TAMPER RESISTANT. 10. WHEN SECURED PANEL FRAME SHALL FEEL SOLID AND SHALL NOT SHAKE, WOBBLE, OR ROCK. 11. FIELD VERIFY LAYOUT DIMENSIONS PRIOR TO FABRICATION, TYP. 12. RAILING POSTS SHALL BE INSTALLED PLUMB. Foundation Plan - Lisa Cameron Art Customer: Lisa Cameron Art Project Number: 15-010 Robinson Engineering, Inc 319 South Grant Avenue Fort Collins, Colorado 80521 (970) 217-4960 Office (970) 797-2649 Fax RobEngInc@gmail.com Foundations for Sculptures to be located at Horsetooth Road and Timberline Road Fort Collins, Colorado 80525 Drawing Information: LCA Sculpture FNDs.ACAD February 11, 2015 Drawn by: Geoff Robinson Reviewed by: Foundation A Foundation B Foundation C Drawing Name: Revisions 1603 Oakridge Drive Fort Collins, CO 80525 (970) 223-7577 fax (970) 223-1827 Landscape Architecture Urban Design Graphic Design Checked by: NORTH 0 SCALE: Project: Client: Sheet Date: Sheet Number: Project Number: Drawn by: Designed by: 1/2" = 1' FOUNDATION DETAILS D3 03.20.15 1324 HORSETOOTH AND TIMBERLINE CITY OF FORT COLLINS M 14 A1 1" F 1 2 3 A 4 Drawing Name: Revisions 1603 Oakridge Drive Fort Collins, CO 80525 (970) 223-7577 fax (970) 223-1827 Landscape Architecture Urban Design Graphic Design Checked by: NORTH 0 SCALE: Project: Client: Sheet Date: Sheet Number: Project Number: Drawn by: Designed by: NTS EWP ECW ARZ GENERAL NOTES & LEGEND IR-1.0 03.20.2015 - HORSETOOTH AND TIMBERLINE CITY OF FORT COLLINS - - - A 1 2 3 3 3 3 3 1" 1" 1" 1" 4 4 18 MATCHLINE - SEE THIS SHEET Drawing Name: Revisions 1603 Oakridge Drive Fort Collins, CO 80525 (970) 223-7577 fax (970) 223-1827 Landscape Architecture Urban Design Graphic Design Checked by: NORTH 0 SCALE: Project: Client: Sheet Date: Sheet Number: Project Number: Drawn by: Designed by: 1"=20'-0" EWP ECW ARZ IRRIGATION PLAN IR-2.0 03.20.2015 - HORSETOOTH AND TIMBERLINE CITY OF FORT COLLINS 10 20 40 MATCHLINE - SEE THIS SHEET MATCHLINE - SEE SHEET IR-2.1 MATCHLINE - SEE SHEET IR-2.1 MATCHLINE - SEE SHEET IR-2.2 3 3 1" 3 3 1" MATCHLINE - SEE SHEET IR-2.0 MATCHLINE - SEE SHEET IR-2.0 MATCHLINE A - SEE THIS SHEET MATCHLINE A - SEE THIS SHEET Drawing Name: Revisions 1603 Oakridge Drive Fort Collins, CO 80525 (970) 223-7577 fax (970) 223-1827 Landscape Architecture Urban Design Graphic Design Checked by: NORTH 0 SCALE: Project: Client: Sheet Date: Sheet Number: Project Number: Drawn by: Designed by: 1"=20'-0" EWP ECW ARZ IRRIGATION PLAN IR-2.1 03.20.2015 - HORSETOOTH AND TIMBERLINE CITY OF FORT COLLINS 10 20 40 3 3 1" Drawing Name: Revisions 1603 Oakridge Drive Fort Collins, CO 80525 (970) 223-7577 fax (970) 223-1827 Landscape Architecture Urban Design Graphic Design Checked by: NORTH 0 SCALE: Project: Client: Sheet Date: Sheet Number: Project Number: Drawn by: Designed by: 1"=20'-0" EWP ECW ARZ IRRIGATION PLAN IR-2.2 03.20.2015 - HORSETOOTH AND TIMBERLINE CITY OF FORT COLLINS 10 20 40 MATCHLINE A - SEE THIS SHEET MATCHLINE A - SEE SHEET IR-2.0 MATCHLINE A - SEE THIS SHEET Drawing Name: Revisions 1603 Oakridge Drive Fort Collins, CO 80525 (970) 223-7577 fax (970) 223-1827 Landscape Architecture Urban Design Graphic Design Checked by: NORTH 0 SCALE: Project: Client: Sheet Date: Sheet Number: Project Number: Drawn by: Designed by: NTS EWP ECW ARZ IRRIGATION DETAILS IR-3.0 03.20.2015 - HORSETOOTH AND TIMBERLINE CITY OF FORT COLLINS - - - BACKFLOW PREVENTION UNIT 1 MASTER VALVE ASSEMBLY 2 ISOLATION GATE VALVE ASSEMBLY 5 QUICK COUPLING VALVE ASSEMBLY 6 REMOTE CONTROL DRIP VALVE ASSEMBLY 7 FLOW SENSOR ASSEMBLY 3 SINGLE OUTLET EMITTER ASSEMBLY 8 FERTILIZER INJECTION SYSTEM ASSEMBLY 4 Drawing Name: Revisions 1603 Oakridge Drive Fort Collins, CO 80525 (970) 223-7577 fax (970) 223-1827 Landscape Architecture Urban Design Graphic Design Checked by: NORTH 0 SCALE: Project: Client: Sheet Date: Sheet Number: Project Number: Drawn by: Designed by: NTS EWP ECW ARZ IRRIGATION DETAILS IR-3.1 03.20.2015 - HORSETOOTH AND TIMBERLINE CITY OF FORT COLLINS - - - TYPICAL TRENCHING DETAIL 14 DRIP FLUSH CAP ASSEMBLY 12 TYPICAL SLEEVING DETAIL 15 24" min. MULTIPLE OUTLET EMITTER ASSEMBLY FOR TREES IN BEDS 10 PEDESTAL MOUNT CONTROLLER ASSEMBLY 13 DRIP ASSEMBLY FOR TREES IN MEDIANS 9 DRIP SYSTEM OPERATION INDICATOR 11 24" ROOT WATERING SYSTEM FOR TREES IN TURF AND MEDIANS 16 13. RAILING SHALL FOLLOW ALIGNMENT OF RAILING CURB. 14. EXPOSED HARDWARE & FASTENERS SHALL BE PAINTED TO MATCH PEDESTRIAN RAILING. PANEL PATTERN 'C' PANEL PATTERN 'B' PANEL PATTERN 'A' ELEVATION 2" 2" 1.5" SQUARE WEAVE WIRE MESH, ALUMINUM ALLOY, 0.25" WIRE DIAMETER, INTERCRIMP WEAVE,CUT PER PATTERN 1" 1" 3' SEE RAILING FRAME SECTION DETAIL SEE RAILING FRAME SECTION DETAIL SECTION PLAN VIEW 8' O.C. TYP. A B B A A A A A A A B B B B B B C C C C C C C C SITE PANEL PATTERN LAYOUT HORSETOOTH ROAD TREE LAWN SIDEWALK THRIFT-RITE PROPERTY 2" x 1-3/4" x 1/4" THICK ALUMINUM BRACKET WITH 5/8" HOLES 13 4" 13 4" 2" 1" 2" MOUNTING BRACKET DETAIL ELEVATION PLAN VIEW 1/2" DIA. STAINLESS STEEL BOLT WITH LOCK WASHER; PAINT EXPOSED HARDWARE TO MATCH FENCE PANEL FENCE RAILING FENCE POST 1" 2" 2" 2" SQUARE ALUMINUM TUBE 1" 1.5" WELDED WIRE MESH 1" ALUMINUM FLAT BAR 3" WELDED WIRE MESH RAILING FRAME SECTION EQ. EQ. PROVIDE 1/8" X 3" GAPS IN CONTINUOUS WELD ON PARKING LOT SIDE FOR DRAINAGE STREET SIDE PARKING LOT SIDE CONTINUOUS WELD TOP RAIL BOTTOM RAIL Drawing Name: Revisions 1603 Oakridge Drive Fort Collins, CO 80525 (970) 223-7577 fax (970) 223-1827 Landscape Architecture Urban Design Graphic Design Checked by: NORTH 0 SCALE: Project: Client: Sheet Date: Sheet Number: Project Number: Drawn by: Designed by: SEE DETAIL MBM MBM RS SITE DETAILS D2 03.20.15 1324 HORSETOOTH AND TIMBERLINE CITY OF FORT COLLINS RAILING 1 SCALE: 1" = 1'-0" SECTION PLANTING AREA, RE: LANDSCAPE PLAN SMOOTH FACED RIVER ROCK BOULDER, SEE PLAN FOR SIZE BURY 1/3 OF THE BOULDER BELOW FINISH GRADE RIVER ROCK BOULDER NOTES: 1. BOULDER SIZE PER PLAN. CONTRACTOR SHALL SUBMIT PHOTOS OF BOULDERS AT QUARRY FOR OWNER'S REPRESENTATIVE TO REVIEW AND APPROVE PRIOR TO DELIVERY ON SITE. INCLUDE A RULER IN THE PHOTO FOR SCALE. 2. OWNER'S REPRESENTATIVE SHALL REVIEW AND APPROVE BOULDER LOCATIONS PRIOR TO PLACEMENT. LOCATIONS SHALL BE STAKED FOR REVIEW. 1/8" MIN. RUBBER OR NYLON PAD BETWEEN BOLLARD COLLAR BASE PLATE AND CONCRETE ELEVATION (4) 1/2" X 6" STAINLESS STEEL WEJ ANCHORS, TYP. PAINT EXPOSED HARDWARE TO MATCH BASE PLATE 1/2" DIA. STAINLESS BOLT W/ NUT & WASHER. PAINT EXPOSED HARDWARE TO MATCH COLLAR. 1/8" THICK ALUMINUM STABILIZING FINS SAW CUT BOTTOM OF STONE POST TO 5-1/4" SQUARE. SAW CUT 3/8" WIDE GROOVES 1" DEEP IN CROSS ON BOTTOM OF POST TO ALIGN WITH STABILIZING FINS IN COLLAR. CORE DRILL 5/8" HOLE ALIGNED WITH BOLT IN COLLAR. 6" x 6" BUFF SANDSTONE POST. TWO SIDES SHALL BE FLAT NATURAL SHEARED FACE, TWO SIDES SHALL BE NATURAL CLEFT FACE. SAW CUT TOP AND BOTTOM. 1/8" THICK ALUMINUM STABILIZING FINS 6" BOLLARD COLLAR, SEE DETAIL BELOW 3' SANDBLAST SHEARED POST FACE AND STAIN WITH BROWN LITHOCRETE. PATTERN SHALL BE SUPPLIED TO FABRICATOR. LAYOUT TO BE APPROVED BY OWNER'S REPRESENTATIVE PRIOR TO SANDBLASTING. 6" BOLLARD COLLAR TOP VIEW 1/4" THICK ALUMINUM BASE PLATE 10" 3/4" DIA. BOLT HOLES 6" 53 4" 5 1 2" 3 8" 1 1 2" 1" 51 4" 1 1 2" NOTES: 1. BOLLARDS SHALL BE INSTALLED PLUMB. 2. BOLLARD COLLAR TO BE POWDERCOATED TEXTURED BLACK. PROVIDE SAMPLE TO OWNER'S REPRESENTATIVE FOR REVIEW AND APPROVAL PRIOR TO FABRICATION. 3. DETAILED AND DIMENSIONED SHOP DRAWINGS (INCLUDING THICKNESS, DIMENSIONS, MATERIALS, AND PROPOSED GRADES OF METAL) SHALL BE PROVIDED BY FABRICATOR/CONTRACTOR TO OWNER'S REPRESENTATIVE TO REVIEW AND APPROVE PRIOR TO FABRICATION. 4. ALUMINUM CONNECTIONS SHALL BE MADE WITH A CONTINUOUS WELD. GRIND WELDS SMOOTH LEAVING NO BURRS OR SHARP EDGES. 5. FABRICATOR/CONTRACTOR TO SUBMIT MATERIAL SAMPLES OF PROPOSED MOUNTING HARDWARE (LOCK WASHERS/BOLTS/NUTS) TO OWNER'S REPRESENTATIVE FOR REVIEW AND APPROVAL PRIOR TO FABRICATION OF BOLLARD COLLAR. 6. DETAILED AND DIMENSIONED SHOP DRAWINGS (INCLUDING THICKNESS, DIMENSIONS, MATERIALS, AND PROPOSED GRADES OF METAL) SHALL BE PROVIDED BY FABRICATOR/CONTRACTOR TO OWNER'S REPRESENTATIVE TO REVIEW AND APPROVE PRIOR TO FABRICATION. 7. THREADS OF BOLT SHALL BE SAWN OFF FLUSH WITH OUTSIDE EDGE OF NUT. 8. REFER TO LANDSCAPE PLAN FOR LOCATIONS OF BOLLARDS. 9. WHEN SECURED BOLLARD AND STONE POST SHALL FEEL SOLID AND SHALL NOT SHAKE, WOBBLE, OR ROCK. 10. FIELD VERIFY LAYOUT DIMENSIONS PRIOR TO FABRICATION, TYP. 11. EXPOSED HARDWARE & FASTENERS SHALL BE PAINTED TO MATCH BOLLARD COLLAR. 12. FIELD SAMPLE: PREPARE SANDBLAST SAMPLE TO INDICATE RANGE OF SANDBLAST DEPTHS OF 1/8", 1/4" AND 1/2" DEPTHS FOR PRELIMINARY SELECTION BY LANDSCAPE ARCHITECT. 13. PROVIDE RANGE OF BROWN LITHOCRETE STAIN SAMPLES ON FIELD SAMPLE FOR PRELIMINARY SELECTION BY LANDSCAPE ARCHITECT. 1" 1" 1/4" THICK ALUMINUM COLLAR 6" 10" COMPACTED SUBGRADE NOTES: 1. BOULDER SIZE PER PLAN. CONTRACTOR SHALL SUBMIT PHOTOS OF BOULDERS AT QUARRY FOR OWNER'S REPRESENTATIVE TO REVIEW AND APPROVE PRIOR TO DELIVERY ON SITE. INCLUDE A RULER IN THE PHOTO FOR SCALE. 2. OWNER'S REPRESENTATIVE SHALL REVIEW AND APPROVE BOULDER LOCATIONS PRIOR TO PLACEMENT. LOCATIONS SHALL BE STAKED FOR REVIEW. BURY 1/3 OF BOULDER BELOW ADJACENT FINISHED GRADE MULCH TOP OF BOULDER SHALL BE LEVEL 1' 1' 1' 1' ALIGN SIDEWALK 3:1 MAX SIDE SLOPE 3:1 MAX SIDE SLOPE LID SWALE SOIL SECTION, SEE DETAIL 7 THIS SHEET TOP OF FOUNDATION 54.50 EDGE OF CONCRETE, APPX. 53.10 SCULPTURE, RE: ARTIST BOTTOM OF SWALE APPX. 52.12 EXISTING FINISHED GRADE APPX. 53.96 FEATHER SWALE SLOPE INTO EXISTING GRADE 12" THICK LAYER OF BIORETENTION SAND MEDIA (SEE BIORETENTION SAND MEDIA SPECIFICATION FROM CITY OF FORT COLLINS, SEE SECTION 605) 6" THICK LAYER OF PEA GRAVEL DIAPHRAM 6" THICK LAYER CDOT NO. 4 AGGREGATE UNDISTURBED SOIL 2' Drawing Name: Revisions 1603 Oakridge Drive Fort Collins, CO 80525 (970) 223-7577 fax (970) 223-1827 Landscape Architecture Urban Design Graphic Design Checked by: NORTH 0 SCALE: Project: Client: Sheet Date: Sheet Number: Project Number: Drawn by: Designed by: SEE DETAIL MBM MBM RS SITE DETAILS D1 03.20.15 1324 HORSETOOTH AND TIMBERLINE CITY OF FORT COLLINS BOULDER RETAINING WALL 4 PLANTER POT 3 SCALE: 3/4" = 1'-0" RIVER ROCK BOULDER 1 SANDSTONE BOLLARD 6 SCALE: 1" = 1'-0" SANDSTONE BOULDER SCALE: 1" = 1'-0" 2 SCALE: 1" = 1'-0" BOLLARD LAYOUT SCALE: 1" = 1'-0" SWALE CROSS SECTION 5 SCALE: 1/2" = 1'-0" LID SWALE SOIL SECTION 7 SCALE: 1" = 1'-0" 6" RADIUS MULCH PER PLAN INSTALL CEDAR WOOD MULCH RING TO EXTENTS OF AROUND BASE TO A DEPTH OF 4". Drawing Name: Revisions 1603 Oakridge Drive Fort Collins, CO 80525 (970) 223-7577 fax (970) 223-1827 Landscape Architecture Urban Design Graphic Design Checked by: NORTH 0 SCALE: Project: Client: Sheet Date: Sheet Number: Project Number: Drawn by: Designed by: NTS MBM MBM RS PLANT NOTES & DETAILS L5 03.20.15 1324 HORSETOOTH AND TIMBERLINE CITY OF FORT COLLINS PLANTING 1 SCALE: NTS Deciduous Trees Symbol Botanical Name Common Name Size Root Quantity GL TR Gledistia triacanthos inermis 'Skyline' Skyline Honeylocust 2" Cal. BB 3 GY DI Gymnocladus dioicus 'Expresso' Expresso Kentucky Coffeetree 2" Cal. BB 2 PY CA Pyrus calleryana Chanticleer Pear 2" Cal. BB 46 QU CS Quercus 'Crimson Spire' Crimson Spire Oak 2" Cal. BB 18 QU MA Quercus macrocarpa Bur Oak 2" Cal. BB 4 QU RO Quercus robur English Oak 2" Cal. BB 8 TI CO Tilia cordata 'Greenspire' Greenspire Littleleaf Linden 2" Cal. BB 9 UL JA Ulmus japonica x U. wilsoniana 'Morton' Accolade Elm 2" Cal. BB 19 Deciduous Shrubs CH NA Chrysothamnus nauseosus nauseosus Dwarf Blue Rabbitbrush 5 Gal. Cont. 42 CO AF Cornus sericia 'Arctic Fire' Arctic Fire Dogwood 5 Gal. Cont. 8 PO SN Potentilla fruticosa 'Davurica' Prairie Snow Potentilla 5 Gal. Cont. 55 RH AA Rhus trilobata 'Autumn Amber' Creeping Three Leaf Sumac 5 Gal. Cont. 79 Ornamental Grasses BO GR Boutela gracilis 'Bonde Ambition' Blonde Ambition Grama Grass 1 Gal. Cont. 100 DE CE Dechampsia caespitosa Tufted Hair Grass 1 Gal. Cont. 134 FE BB Festuca clauca 'Boulder Blue' Boulder Blue Fescue 1 Gal. Cont. 71 PA VI Panicum virgatum 'Shenandoah' Red Switch Grass 1 Gal. Cont. 128 PLANT LIST Perennials AL MO Allyssum montanum Mountain Basket of Gold 1 Gal. Cont. 85 AS TU Asclepias tuberosa Butterfly Weed 1 Gal. Cont. 104 CA IN Callirhoe involucrata Poppy Mallow 1 Gal. Cont. 120 CO VE Coreopsis verticillata 'Zagreb' Threadleaf Coreopsis 1 Gal. Cont. 58 GE RO Geranium 'Rozanne' Blue Cranesbill 1 Gal. Cont. 92 HE PA Hesperaloe parviflora False Red Yucca 1 Gal. Cont. 67 LI SP Liatris spicata 'Floristan Violet' Purple Gayfeather 1 Gal. Cont. 89 NE LT Nepeta 'Little Trudy' Little Trudy Catmint 1 Gal. Cont. 85 PE AF Persicaria affinis Himalayan Border Jewel 1 Gal. Cont. 110 PE ST Penstemon strictus Rocky Mountain Penstemon 1 Gal. Cont. 72 SE AJ Sedum 'Autumn Joy' Stonecrop 1 Gal. Cont. 63 GENERAL NOTES 1. Tree lawns and park shall be sodded with Reivelle Bluegrass Sod. 2. A free permit will be required from the City Forester before any trees are planted in, pruned or removed from the public right-of-way. 3. Tree utility separations shall be as follows - Ten feet between trees and water or sewer mains - Six feet between trees and water sewer service lines - Four feet between trees and gas lines 4. Street tree separations shall be as follows: - Forty feet between shade trees and street lights - Fifteen feet between ornamental trees and street lights - Twenty feet between trees and traffic control signs 5. Turf areas shall be irrigated with an automatic pop-up irrigation system. Shrub beds and trees to be irrigated with an automatic drip (trickle) irrigation system. The irrigation plan shall be reviewed and approved by the City of Fort Collins prior to the issuance of a building permit. 6. The soil in all landscape areas, including parkways and medians, shall thoroughly loosened to a depth of not less than eight (8) inches and soil amendment shall be thoroughly incorporated into the soil of all landscape areas to a depth of at least six (6) inches by tilling, discing or other suitable method, at a rate of at least three (3) cubic yards of soil amendment per one thousand (1,000) square feet of landscape area. GRASS AND PERENNIAL SHRUB PLANTING 2 SCALE: NTS DECIDUOUS TREE PLANTING 3 SCALE: NTS TB 53.85 FOUNDATION B, TF 53.70 4954 APPX. EOC 53.10 FOUNDATION A, TF 54.50 A EFG 53.97 B C C C C C B A B B A A B B B A B A A A HORSETOOTH ROAD 4954 4953 4952 EDGER EXISTING STONE WALL TO REMAIN 5 CO AF EXISTING PLANTINGS TO REMAIN 5 PO SN 14 PA VI 7 PE ST 4 RH AA 11 AS TU EXISTING EDGER TO BE REMOVED 4 PO SN 7 PA VI 8 NE LT 6 SE AJ 9 AS TU 14 PA VI 3 CO AF 5 NE LT 5 CH NA 10 DE CE 7 DE CE 6 RH AA 5 CO VE 9 GE RO 3 HE PA 5 AL MO 10 BO GR 6 GE RO 5 HE PA 4 RH AA 8 BO GR TIMBERLINE ROAD 1E, 2F, 2G 1E,2F,2G D1 4 SALVAGE (6) SIX EXISTING BOULDERS TO CREATE NEW BOULDER RETAINING WALL AT BASE OF EXISTING TREE RESOD TO EXTENTS OF DISTURBANCE FROM REMOVAL OF EXISTING PLAZA TIE NEW EDGER INTO EDGE OF EXISTING PLANTING BED TIE NEW EDGER INTO EDGE OF EXISTING PLANTING BED FILL PLANTING AREA WITH WOOD MULCH D1 5 A B SCULPTURE, RE: ARTIST 3E,2F,3G FOUNDATION C, TF 53.70 FOUNDATION C, TF 5420 TOP OF BERM 54.58 13 BO GR 19 FE BB BASE OF TREE 54.75 6 PA VI 3 HE PA EDGER 5 BO GR 3 HE PA 4A, 3B 15 FE BB 5 BO GR 15 FE BB CONCRETE PAN, RE: CIVIL CONCRETE PAN, RE: CIVIL 5 CO VE D1 7 Drawing Name: Revisions 1603 Oakridge Drive Fort Collins, CO 80525 (970) 223-7577 fax (970) 223-1827 Landscape Architecture Urban Design Graphic Design Checked by: NORTH 0 SCALE: Project: Client: Sheet Date: Sheet Number: Project Number: Drawn by: Designed by: 1"=10' MBM MBM RS DETAIL LANDSCAPE PLANS L4 03.20.15 1324 HORSETOOTH AND TIMBERLINE CITY OF FORT COLLINS 5' 10' 20' LEGEND SOD WOOD MULCH EXISTING TREES TO REMAIN TYPE 1 ROCK MULCH TYPE 2 ROCK MULCH EFG EXISTING FINISH GRADE EOC EDGE OF CONCRETE TF TOP OF FOUNDATION TB TOP OF BOULDER BS BOTTOM OF SWALE FL FLOWLINE GRADING KEY 1. FINISH GRADING SHALL BE APPROVED BY OWNER, ARTIST AND LANDSCAPE ARCHITECT PRIOR TO INSTALLATION OF ART FOUNDATIONS. 2. PROVIDE 12 TONS 4"-12" BUFF SANDSTONE RIP RAP ON SITE FOR ARTIST INSTALLATION. COORDINATE WITH ARTIST ON LOCATION OF STAGING AREA. ANY ADDITIONAL STONE NOT USED BY THE ARTIST SHALL BE INSTALLED IN PLANTING AREAS. NOTES W W W W W W W W W W W W TIMBERLINE ROAD BIGHORN ROAD 9 BO GR 12 AS TU 5 HE PA 10 CO VE 3 PY CA 5 HE PA 9 RH AA 3 UL JA 9 DE CE 14 GE RO 19 CA IN 6 PE AF 5 HE PA 12 SE AJ 9 PE ST 23 CA IN 13 GE RO 21 AL MO 21 DE CE 18 PE AF MATCHLINE - SEE SHEET L1 Drawing Name: Revisions 1603 Oakridge Drive Fort Collins, CO 80525 (970) 223-7577 fax (970) 223-1827 Landscape Architecture Urban Design Graphic Design Checked by: NORTH 0 SCALE: Project: Client: Sheet Date: Sheet Number: Project Number: Drawn by: Designed by: 1"=20' MBM MBM RS LANDSCAPE PLANS L3 03.20.15 1324 HORSETOOTH AND TIMBERLINE CITY OF FORT COLLINS 10' 20' 40' MATCHLINE - SEE THIS SHEET MATCHLINE - SEE THIS SHEET L1 L1 L2 L3 L3 L2 L2 KEYMAP SCALE: 1" = 300' LEGEND SOD WOOD MULCH EXISTING TREES TO REMAIN TYPE 1 ROCK MULCH TYPE 2 ROCK MULCH 20 DE CE 23 PE AF 6 CH NA 8 SE AJ 7 AS TU 16 GE RO 9 PE ST 10 SE AJ 16 AL MO 9 AS TU 3 GL TR 18 DE CE 16 PE AF 14 PE AF 30' TYP. HORSETOOTH ROAD 5 TI CO 1 TI CO 11 PA VI ? ? W W W W W W W W W W W W W W W W W W W W W W W W W TIMBERLINE ROAD 2 GY DI 3 QU RO 4 PO SN 2 PY CA 12 PE ST 10 AM CA 5 QU CS 1 QU MA 12 LI SP 10 PO SN 5 PY CA 18 CA IN 15 SE AJ 3 QU CS 7 RH AA 11 GE RO 9 DE CE 18 NE LT A B SEE SHEET L4 FOR PLAZA DETAIL ELV ELV W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W 1 QU RO 12 PE ST 7 CO VE 7 AM CA 19 NE LT 2 UL JA 14 DE CE 23 PE AF 9 BO GR 9 AS TU 7 PO GD 11 AL MO 11 BO GR 12 CH NA 14 CO VE MATCHLINE - SEE SHEET L1 Drawing Name: Revisions 1603 Oakridge Drive Fort Collins, CO 80525 (970) 223-7577 fax (970) 223-1827 Landscape Architecture Urban Design Graphic Design Checked by: NORTH 0 SCALE: Project: Client: Sheet Date: Sheet Number: Project Number: Drawn by: Designed by: 1"=20' MBM MBM RS LANDSCAPE PLANS L2 03.20.15 1324 HORSETOOTH AND TIMBERLINE CITY OF FORT COLLINS 10' 20' 40' MATCHLINE - SEE SHEET L1 KEYMAP SCALE: 1" = 300' LEGEND SOD WOOD MULCH EXISTING TREES TO REMAIN TYPE 1 ROCK MULCH TYPE 2 ROCK MULCH MATCHLINE A - SEE THIS SHEET MATCHLINE A - SEE THIS SHEET L1 L1 L2 L3 L3 L2 L2 2 UL JA 11 PA VI 9 PO SN 11 PA VI 21 LI SP 7 HE PA 10 AS TU 9 CA IN 6 NE LT 7 UL JA 11 CA IN 6 NE LT 4 PY CA 9 AM CA 3 HE PA 10' TYP. HORSETOOTH ROAD 1 TI CO 6 CO VE 10 PE ST 3 UL JA 13 PE ST 5 CO VE 8 BO GR 3 PY CA 5 PO SN TIMBERLINE ROAD TIMBERLINE ROAD D2 RAILING, 1 APPX. 192 LF RAILING CURB, RE: CIVIL D1 3 PLANTER POT D1 (2) SANDSTONE BOLLARDS 6 D1 3 PLANTER POT D1 (2) SANDSTONE BOLLARDS 6 D1 3 PLANTER POT D1 (2) SANDSTONE BOLLARDS 6 4952 4953 4954 4954 4953 4952 SEE SHEET L4 FOR CORNER DETAIL SEE SHEET L4 FOR CORNER DETAIL MATCHLINE - SEE THIS SHEET Drawing Name: Revisions 1603 Oakridge Drive Fort Collins, CO 80525 (970) 223-7577 fax (970) 223-1827 Landscape Architecture Urban Design Graphic Design Checked by: NORTH 0 SCALE: Project: Client: Sheet Date: Sheet Number: Project Number: Drawn by: Designed by: 1"=20' MBM MBM RS LANDSCAPE PLANS L1 03.20.15 1324 HORSETOOTH AND TIMBERLINE CITY OF FORT COLLINS 10' 20' 40' MATCHLINE - SEE THIS SHEET MATCHLINE - SEE SHEET L2 MATCHLINE - SEE SHEET L2 MATCHLINE - SEE SHEET L3 L1 L1 L2 L3 L3 L2 L2 KEYMAP SCALE: 1" = 300' LEGEND SOD WOOD MULCH EXISTING TREES TO REMAIN TYPE 1 ROCK MULCH TYPE 2 ROCK MULCH MEDIAN SECTION 1 1 MEDIAN SECTION 2 SCALE: 1/2" = 1'-0" 2 SCALE: 1/2" = 1'-0" MEDIAN SECTION 4 4 SCALE: 1/2" = 1'-0" MEDIAN SECTION 5 5 SCALE: 1/2" = 1'-0" DURING ROADWAY WORK, RE: CIVIL Drawing Name: Revisions 1603 Oakridge Drive Fort Collins, CO 80525 (970) 223-7577 fax (970) 223-1827 Landscape Architecture Urban Design Graphic Design Checked by: NORTH 0 SCALE: Project: Client: Sheet Date: Sheet Number: Project Number: Drawn by: Designed by: 1"=20' MBM MBM RS GRADING PLANS G3 03.20.15 1324 HORSETOOTH AND TIMBERLINE CITY OF FORT COLLINS 10' 20' 40' G1 G1 G2 G3 G3 G2 G2 MATCHLINE - SEE SHEET G1 MATCHLINE - SEE THIS SHEET MATCHLINE - SEE THIS SHEET KEYMAP SCALE: 1" = 300' LEGEND WOOD MULCH BUFF SANDSTONE BOULDERS A - 1 - 1.25 TON (APPX. 2' W. x 4' L. x 2' T.) B - 0.75 - 1 TON (APPX. 2' W. x 3' L. x 2' T.) C - 0.5 - 0.75 TON (APPX. 2' W. x 2' L. x 2' T.) D - 0.25 - 0.5 TON (APPX. 1.5' W. x 1.5' L. x 1.5' T.) RIVER ROCK BOULDERS E - 2' DIAMETER F - 1.5' DIAMETER G - 1' DIAMETER TYPE 1 ROCK MULCH TYPE 2 ROCK MULCH 3B,2A 1B,1C 1E,1F 1E,1F,1G 1B 1B 1G,1E,1F 1B 1B 1G,1E,1F 1B A B ELV ELV W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W 1E,1F,1G 1G,3F,1E 2G,2F,2E 2B,2A,1C BOULDERS INSTALLED DURING ROADWAY WORK, RE: CIVIL TRANSITION GRADE FROM DOUBLE CURB TO SINGLE CURB BETWEEN MEDIAN CURB BOULDERS MATCHLINE - SEE SHEET G1 Drawing Name: Revisions 1603 Oakridge Drive Fort Collins, CO 80525 (970) 223-7577 fax (970) 223-1827 Landscape Architecture Urban Design Graphic Design Checked by: NORTH 0 SCALE: Project: Client: Sheet Date: Sheet Number: Project Number: Drawn by: Designed by: 1"=20' MBM MBM RS GRADING PLANS G2 03.20.15 1324 HORSETOOTH AND TIMBERLINE CITY OF FORT COLLINS 10' 20' 40' MATCHLINE - SEE SHEET XX MATCHLINE - SEE THIS SHEET MATCHLINE A - SEE THIS SHEET MATCHLINE A - SEE THIS SHEET G1 G1 G2 G3 G3 G2 G2 KEYMAP SCALE: 1" = 300' LEGEND WOOD MULCH BUFF SANDSTONE BOULDERS A - 1 - 1.25 TON (APPX. 2' W. x 4' L. x 2' T.) B - 0.75 - 1 TON (APPX. 2' W. x 3' L. x 2' T.) C - 0.5 - 0.75 TON (APPX. 2' W. x 2' L. x 2' T.) D - 0.25 - 0.5 TON (APPX. 1.5' W. x 1.5' L. x 1.5' T.) RIVER ROCK BOULDERS E - 2' DIAMETER F - 1.5' DIAMETER G - 1' DIAMETER TYPE 1 ROCK MULCH TYPE 2 ROCK MULCH 1G,1F BOULDERS INSTALLED DURING ROADWAY WORK, RE: CIVIL 2E 1E,1F,1G 2E,1F 2G,1F 1E,1F TIMBERLINE ROAD TIMBERLINE ROAD TRANSITION GRADE FROM DOUBLE CURB TO SINGLE CURB BETWEEN MEDIAN CURB BOULDERS BOULDERS INSTALLED DURING ROADWAY WORK, RE: CIVIL TRANSITION GRADE FROM DOUBLE CURB TO SINGLE CURB BETWEEN MEDIAN CURB BOULDERS BOULDER INSTALLED DURING ROADWAY WORK, RE: CIVIL 4952 4953 4954 4954 4953 4952 SEE SHEET L4 FOR CORNER DETAIL SEE SHEET L4 FOR CORNER DETAIL MATCHLINE - SEE THIS SHEET Drawing Name: Revisions 1603 Oakridge Drive Fort Collins, CO 80525 (970) 223-7577 fax (970) 223-1827 Landscape Architecture Urban Design Graphic Design Checked by: NORTH 0 SCALE: Project: Client: Sheet Date: Sheet Number: Project Number: Drawn by: Designed by: 1"=20' MBM MBM RS GRADING PLANS G1 03.20.15 1324 HORSETOOTH AND TIMBERLINE CITY OF FORT COLLINS 10' 20' 40' MATCHLINE - SEE THIS SHEET MATCHLINE - SEE SHEET G2 MATCHLINE - SEE SHEET G2 MATCHLINE - SEE SHEET G3 G1 G1 G2 G3 G3 G2 G2 KEYMAP SCALE: 1" = 300' LEGEND WOOD MULCH BUFF SANDSTONE BOULDERS A - 1 - 1.25 TON (APPX. 2' W. x 4' L. x 2' T.) B - 0.75 - 1 TON (APPX. 2' W. x 3' L. x 2' T.) C - 0.5 - 0.75 TON (APPX. 2' W. x 2' L. x 2' T.) D - 0.25 - 0.5 TON (APPX. 1.5' W. x 1.5' L. x 1.5' T.) RIVER ROCK BOULDERS E - 2' DIAMETER F - 1.5' DIAMETER G - 1' DIAMETER TYPE 1 ROCK MULCH TYPE 2 ROCK MULCH IRRIGATION PLAN IR2.1 IRRIGATION PLAN IR2.2 IRRIGATION PLAN IR3.0 IRRIGATION DETAILS IR3.1 IRRIGATION DETAILS Owner: CITY OF FORT COLLINS 281 N College Ave Fort Collins, CO 80524 Contact: Tim Kemp e-mail: tkemp@fcgov.com Ph: 970-416-2719 Civil Engineer: MULLER ENGINEERING COMPANY 777 S Wadsworth Blvd Suite 4-100 Lakewood, CO 80226 Contact: Nancy Lambertson e-mail: nlambertson@mullereng.com Ph: 303.988.4939 Landscape Architect: BHA DESIGN, INC. 1603 Oakridge Drive Fort Collins, CO 80525 Contact: Roger Sherman e-mail: rsherman@bhdesign.com Ph: 970.223.7577 Irrigation Design: HINES IRRIGATION CONSULTANTS 323 W. Drake Road Suite 204 Fort Collins, CO 80525 Contact: Edward Wranosky e-mail: edw@hinesirrigation.com Ph: 970.282.1800 Artist: Lisa Cameron Russell Artworks LLC 4524 Skyline Drive Fort Collins, CO 80526 Contact: Lisa Cameron Russell e-mail: lisa@lisajcameron.com Ph: 970.227.7155 HORSETOOTH AND TIMBERLINE LANDSCAPE PACKAGE URBAN DESIGN, LANDSCAPING & IRRIGATION TEAM DIRECTORY INDEX VICINITY MAP PROJECT AREA