HomeMy WebLinkAboutCHANGE ORDER - RFP - APP HORSETOOTH & TIMBERLINE INTERSECTIONCHANGE ORDER NO.1
PROJECT TITLE: Horsetooth & Timberline Intersection
CONTRACTOR: Lisa J Cameron Artworks, LLC
PROJECT NUMBER:
PURCHASE ORDER NO.: 9151988
DESCRIPTION: APP Project
1. Reason for change: Artist needs extension to project
.
2. Description of Change: This extends the time line for the project.
3. Change in Contract Cost: None
4. Change in Contract Time: The new contract deadline is October 31, 2015 (If this Change
Order is not signed and completed, the deadline will remain August 31, 2015.)
ORIGINAL CONTRACT COST $22,500__
TOTAL APPROVED CHANGE ORDERS ________
TOTAL PENDING CHANGE ORDERS ________
TOTAL THIS CHANGE ORDER _-----____
TOTAL % OF ORIGINAL CONTRACT, THIS C.O.: ____%
TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S: ____%
ADJUSTED CONTRACT COST $_N/A____
(Assuming all change orders approved)
ACCEPTED BY:__________________________________________ DATE:______________
Artist
ACCEPTED BY:__________________________________________ DATE:______________
Project Manager
REVIEWED BY:__________________________________________ DATE:______________
Title:
APPROVED BY:__________________________________________ DATE:______________
Purchasing Agent over $15,000
cc: Purchasing
DocuSign Envelope ID: E03D610F-898E-43B9-ABAE-74F4746E0D7C
8/14/2015
8/17/2015