HomeMy WebLinkAboutCORRESPONDENCE - RFP - 8068 ENHANCED TRAVEL CORRIDOR MASTER PLAN FOR WEST ELIZABETH (7)621 17th Street | #2301 | Denver, CO 80293 | (303) 296-4300 | Fax (303) 296-4300
www.fehrandpeers.com
September 21, 2015
Timothy Wilder
Service Development Manager
Transfort
twilder@fcgov.com
Subject: Proposal for Transfort Transit Network Analysis
Dear Mr. Wilder:
Fehr & Peers and TMD appreciate the opportunity to submit this proposal for a citywide transit
network analysis in Fort Collins. We understand that Transfort would like to expand the approach
of the transit network-related aspects of the West Elizabeth Enhanced Travel Corridor Plan to the
entire City of Fort Collins. Our scope of work is based on the project team’s conversations with
Transfort staff and our understanding of the City.
Attachment A includes our scope of work and Attachment includes our cost estimate. We can
complete the base scope of work without optional tasks for $85,000. We understand that the project
will be completed by the end of May 2016.
We appreciate the opportunity to continue work with Transfort and the City of Fort Collins. If you
have any questions please call me at 720.539.7238.
Sincerely,
FEHR & PEERS
Charles Alexander, PE, AICP
Associate
DN15-0488
Timothy Wilder
September 21, 2015
Page 2 of 8
ATTACHMENT A: SCOPE OF WORK
PROJECT PURPOSE & BACKGROUND
The purpose of this project is to identify causes of declining ridership on problematic routes and
implement changes in the system that improve the overall quality of service for customers on key
transit routes.
In 2014, Transfort restructured much of its system to support the start of MAX bus rapid transit
system in accordance with the 2009 Transfort Strategic Operating Plan. In particular, new feeder
routes and service were added to major east-west corridors, and many other Transfort routes were
changed to provide additional transit options. While system ridership continued to increase after
the changes, many of the adjusted routes have not met ridership productivity goals.
The study will include a broad analysis of the entire Transfort network, but also provide an in-depth
examination of key east-west routes including routes 7, 12, and 16, and the regional FLEX route.
These routes are the highest priority for improvement because they help form the essential
backbone of the MAX system and operate with reasonable frequencies and hours. This study will
also identify performance issues on other Transfort routes as needed.
Based on the existing conditions assessment, a new system service concept will be developed to
provide a framework for short and long term improvements. This service concept will replace service
concepts in the Transfort Strategic Operating Plan. The project will conclude with a final report
containing recommendations and implementation actions.
Project Objectives
• Identify and document causes of route underperformance through detailed assessments
using ridership, reliability, route design, market assessment, recovery efficiency, origin-
destination pattern analysis and other measures.
• Develop alternative service concepts and select a recommended service concept.
• Provide recommended route/system improvements.
• Update the Transfort Strategic Operating Plan with results of study.
• Expand existing public engagement opportunities in considering and implementing system
improvements.
Timothy Wilder
September 21, 2015
Page 3 of 8
• Provide a report on Transfort’s process and outcomes, and share lessons learned with other
transit agencies.
Project Area
The study will be conducted for the Transfort service area (which includes Fort Collins and areas
served by FLEX regional transit), and any potentially new areas to be served by Transfort in the
foreseeable future.
Next Steps
To commence work on this project as quickly as possible, we propose two phases of work. Phase 1
includes tasks relating to the system understanding and existing conditions assessment. Phase 2
includes an alternatives development charrette, alternatives assessment, development of a
recommended plan, plan finalization, and outreach.
Timothy Wilder
September 21, 2015
Page 4 of 8
PHASE 1 SCOPE OF WORK
Task 1.1: Kick-Off Meeting & Project Management (Fehr & Peers/TMD)
Transfort will manage the project and oversee the Fehr & Peers/TMD team’s work. As a part of this
task, the Fehr & Peers/TMD team will host a kick-off call with Transfort staff to clarify the scope of
work and schedule and to identify immediate next steps. TMD will have monthly conference calls
with Transfort to discuss project progress and next steps.
Deliverables:
• Kick-off meeting with Fehr & Peers/TMD team
• Monthly project updates with TMD
Task 1.2: Existing Conditions Assessment (Fehr & Peers/TMD)
Several components will make up the existing conditions assessment. First, a market assessment
will be conducted using socio-economic data, customer comments, and other market data.
Transfort staff will take to lead in formatting and aggregating data and TMD will be responsible for
analyzing and interpreting the data. Second, Transfort will develop profiles of route characteristics
and performance including productivity, ridership, reliability, and other elements; TMD will assist
Transfort with the route profiles by reviewing data and data formatting used in the route profiles.
To maximize efficiency, TMD will focus this review on the first two route profiles and provide
feedback to Transfort staff. Third, Fehr & Peers will complete an origin-destination pattern analysis
using “big data” sources such as in-vehicle navigation or cell phones (Fehr & Peers has budgeted
up to $1,500 for this data). Together with a network assessment, TMD will prepare an existing
conditions report that includes these items. TMD will coordinate on-site travel with the current trips
for the West Elizabeth mobility study.
Deliverables:
• Route profiles including route characteristics, performance and issues assessment
• Origin-destination pattern analysis
• Existing conditions report
Timothy Wilder
September 21, 2015
Page 5 of 8
PHASE 2 SCOPE OF WORK
Task 2.1: System and Route Improvements (Fehr & Peers/TMD)
Once the existing conditions assessment is complete, Fehr & Peers, TMD and Transfort will develop
alternative service concepts through a charrette public outreach process. Fehr & Peers will lead the
charrette and TMD will lead efforts with Transfort to develop the alternative service concepts. The
charrette will include a short, intensive-level effort that incorporates feedback from a variety of
stakeholders – local officials, community members, transit advocacy groups, Transfort operators,
road supervisors, dispatch, customer service, City staff, and others. TMD and Transfort will evaluate
these alternatives against goals outlined in the Transfort Strategic Operating Plan, and assessed
with a transit ridership model, Transfort service standards, and financial impact. Fehr & Peers has
budgeted up to 12 hours of staff time to address questions related to how the origin-destination
analysis performed in Task 1.2 is addressed by alternative service concepts. If additional Fehr &
Peers budget remains, Fehr & Peers will coordinate with Transfort and TMD regarding how to best
apply these funds towards this task. A preferred service concept and network plan will be selected
from the alternatives analysis. This service concept will be the foundation for short-term and long-
term service improvements.
Deliverables:
• Technical report containing alternatives review/assessment and preferred service concept
• TMD on-site trip for two nights covering the various charrette efforts and field work
Task 2.2: Public Outreach and Review (TMD)
Transfort will form a Technical Advisory Committee to review route performance data and
improvement recommendations. Transfort will also conduct public outreach as part of the effort, to
include public meetings and workshops, website communication, newsletters, social media and
other forms of outreach. For short term improvements, Transfort’s route change procedures, which
include public notification and outreach, will be implemented.
Deliverables:
• Outreach and notification materials (newsletter articles, workshop presentations, website
and social media postings) will be the responsibility of Transfort with input from TMD.
Timothy Wilder
September 21, 2015
Page 6 of 8
Task 2.3: Prepare Final Report (TMD)
TMD will prepare a draft report containing the aforementioned deliverables, a financial plan, and
an implementation phasing plan. Transfort will make the report available for comment by the public
at a public meeting and on the RideTransfort website. Transfort staff will also present the report to
relevant City boards and commissions, to transit advocacy groups, and to City Council at a work
session. After comments have either been addressed or incorporated into the draft report, TMD will
prepare the final report for the study. The final report will be available for download on the website
or hard copy upon request.
Transfort will maintain all electronic and hard copy files pertaining to the project and shall provide
CDOT with an electronic version of all reports, technical memos, backup data prior to completion
of the draft and final reports. Transfort shall maintain consistent quality control procedures.
All data, maps and other materials prepared or collected under this contract will become property
of Transfort, to be shared with interested Colorado transit providers. Upon completion of the final
report, Transfort will present major findings and lessons learned to the transit community at a
Colorado Association of Transit Agencies conference.
Deliverables:
• Draft project report
• Final project report
• Electronic version of all data and materials collected during the Transfort Route
Improvement Project
Timothy Wilder
September 21, 2015
Page 7 of 8
ATTACHMENT B: COST ESTIMATE
Phase 1 Cost Estimate
Name
Jeremy
Klop
Charlie
Alexander Carly Sieff Nell Conti
Kellie
Dolan
Russ
Chisholm
David
Murphy
Zodin Del
Rosario Associates Admin
Firm FP FP FP FP FP TMD TMD TMD TMD TMD
Role
Principal-
in-Charge
Project
Manager
Trans.
Planner
GIS
Specialist Admin
Transit
Lead
Transit
Support
Transit
Support
Transit
Support
Transit
Admin
Billing Rate $240 $170 $110 $135 $100 $200 $172 $106 $82 $109
1.1 Kick-Off Meeting & Project
Management
2 2 0 2 8 2 2 4 4 0 $3,388
1.2 Existing Conditions
Assessment
2 8 12 58 0 28 32 40 40 2 $29,849
Total Hours by Personnel 4 10 12 60 8 30 34 44 44 2
Subtotal Labor: $ 33,236.50
FP Expenses $ 1,763.50
TMD Expenses $ -
Expenses: $ 1,763.50
Phase 1 Total Cost $ 35,000.00
Task Totals
Timothy Wilder
September 21, 2015
Page 8 of 8
Phase 2 Cost Estimate
Name Jeremy
Klop
Charlie
Alexander Carly Sieff Nell Conti
Kellie
Dolan
Russ
Chisholm
David
Murphy
Zodin Del
Rosario Associates Admin
Firm FP FP FP FP FP TMD TMD TMD TMD TMD
Role Principal-
in-Charge
Project
Manager
Trans.
Planner
GIS
Specialist Admin
Transit
Lead
Transit
Support
Transit
Support
Transit
Support
Transit
Admin
Billing Rate $240 $170 $110 $135 $100 $200 $172 $106 $82 $109
2.1 System and Route
Improvements
4 8 0 8 0 44 44 52 80 2 $32,078
2.2 Public Outreach and Review 0 0 0 0 0 4 4 4 8 0 $2,569
2.3 Prepare Final Report 0 0 0 0 0 8 12 32 64 2 $12,526
Total Hours by Personnel 4 8 0 8 0 44 44 52 80 2
Subtotal Labor: $ 47,174.16
FP Expenses $ 688.12
TMD Expenses $ 2,137.72
Expenses: $ 2,825.84
Phase 2 Total Cost $ 50,000.00
Total Project Cost $ 85,000.00
Task Totals