HomeMy WebLinkAboutCHANGE ORDER - RFP - 7084 CONSULTING ENGINEERING SERVICES (10)CHANGE ORDER NO. 1
PROJECT TITLE: Spring Crock Stream Rehabilitation and Enhancement 50% Design
CONSULTANT: Ayres Associates
PROJECT NUMBER: P09146713
DESCRIPTION:
1. Reason for change: Contract completion date change
2. Description of Change: contract completion date of 4-30-15 has been exceeded and needs to
be extended.
3. Change in Contract Cost: no change in contract cost
4. Change in Contract Time: change contract completion date to 12-31-15
ORIGINAL CONTRACT COST
51,480.00
TOTAL APPROVED CHANGE ORDERS
0.00
TOTAL PENDING CHANGE ORDERS
0.00
TOTAL THIS CHANGE ORDER
0.00
TOTAL % OF THIS CHANGE ORDER
0%
TOTAL C.O.% OF ORIGINAL CONTRACT
0%
ADJUSTED CONTRACT COST
(Assuming all Chan e orders approved)
ACCEPTED BY:
Contractor's Representative
ACCEPTED BY: -Contractor's
Specii Projects Manager
REVIEWED BY:
Chief Engineer
APPROVED BY:
Water Field Services & Ops Manager
T ff2w
Purchasing Agent over $60,000
cc: Project File
Contractor
Purchasing
Fossil Creek Stream Rehab
September 2014
00950.1
$ 51,480.00
DATE:S D
DATE:-(
DATE:_ F ,07
DATE:
DATE:
Contract Change Order