Horsetooth and Timberline
Intersection Improvement Project
Federal Aid Project No. AQC M455-010
PRE-BID CONFERENCE
Monday April 6, 2015
11:00 AM – 12:00 PM
215 N. Mason Street
215 Training Room 2E
City of Fort Collins
Engineering Department
Capital Improvements Program
2
INTRODUCTIONS
• Engineering Capital Projects:
• Tim Kemp – Project Manager 416-2719
• Dan Woodward – Project Manager 416-4203
• Craig Farver – Construction Inspector 222-0854
• Purchasing:
• John Stephen – Senior Buyer 221-6777
3
ATTENDANCE
• Please be sure to register
• Bid Opening
• When: April 21, 2015 3:00 PM
• Where: 215 N. Mason Street (2nd Floor)
4
VICINITY MAP
• CMAQ Funding
• Double left turn
lanes on TL
• Right turn lanes
• Ped crossing
improvements
• Median with future
landscaping
5
IMPORTANT CONTRACT DATES
• Award Contract
• Date
• Partnering and Pre Construction Meeting
• Mandatory meetings prior to start of construction
• Dates to be determined after contract award
• Construction Start Date
• One Hundred Eighty (180) calendar days
• Substantial Completion
• One Hundred Sixty-Five (165) calendar days
• Final Completion
• Fifteen (15) calendar days
6
SUMMARY OF WORK
• Reconstruction of approximately 1,700 feet of Horsetooth Road
and approximately 1,700 feet of Timberline Road
• Addition of dual left turn lanes on north and south legs
• Addition of right turn lanes with pork chop islands on north, west
and east legs
• Reconstruction/installation of medians
• Concrete paving, curb/gutter, sidewalk, parkway installation
• Traffic control, temporary striping provided by Contractor
• Signal relocation, surveying, final signing and striping provided by
City
7
CDOT LOCAL AGENCY PROJECT
UDBE goal for this project: 9%
OJT goal for this project: 640 hours
Contractors to be on CDOT’s prequalified list
Bid proposal must include:
– CDOT 606 Anti-Collusion Affidavit
– CDOT 714 UDBE Assurance
Bids will not be accepted if they do not have these forms
Fuel Cost Adjustment option
Low bidder to receive:
Form 605, Form 621, Form 715 and Form 718
These forms must be returned by 4:30 pm the following day
Monthly payments will not be processed until all documentation required by CDOT
for federally funded projects has been submitted to the City
8
PROJECT OVERVIEW
• Phasing
• Maintain current through lanes and turn lanes through May
31, 2015. May merge bike lanes with travel lanes
• From June 1, 2015 through August 15, 2015, maintain two
(2) northbound and two (2) southbound lanes on Timberline
Road
• Horsetooth Road – may close east leg and west leg
separately or may request a full closure of
Horsetooth
• Timberline Road – May eliminate left turns during
Horsetooth closure
• No later than August 16, 2015 Contractor shall have at
least the following movements open:
• All right turn lanes
• Two (2) through lanes in each direction on Timberline
Road and Horsetooth Road
• At least one (1) left turn lane in each direction
9
PROJECT OVERVIEW
• Full closure of Horsetooth permitted – 8 weeks for west leg and
overlapping 4 weeks for east leg
– If a full closure is requested, must maintain 4 lanes on TL
and complete the following by Aug 15, 2015:
– “OK” to remove existing medians on Timberline and fill with
temporary pavement
Horsetooth Road
• All utility work
• All earthwork outside new
curbline
• All median work
• All HMA except top lift
• All Concrete Pavement within
roadway
• All Sidewalk and Curb Ramp
• All Curb and Gutter
Timberline Road
• All utility/grading/earthwork
work outside existing curbline
• All Curb and Gutter along
east/west side of roadway
• All Sidewalk and Curb Ramp
• All Concrete Pavement outside
of existing travel way
10
PROJECT OVERVIEW
• West leg closure permitted with four (4) week duration
11
PROJECT OVERVIEW
• East leg closure permitted with four (4) week duration
12
PROJECT OVERVIEW
• Coordination with other utilities
• Contractor responsible to acquire all appropriate
permits and submit required documentation
• SWMP – permit and inspections
• CDOT Form 205 for each subcontractor
• TCS Diaries, Payrolls
• No designated staging area provided
• All material testing conducted through City’s on-call
contractor (CTL Thompson) and coordinated through
City Inspector (Craig Farver)
13
PROJECT OVERVIEW
• Partnering session prior to construction
• Plans include:
– Tabulation of Removals, Resets and Adjustments
– Tabulation of Surface Quantities
– Tabulation of Concrete Items
– Tabulation of Driveways
– Tabulation of Drainage Structures
– Tabulation of Signs and Pavement Markings
14
HIGHLIGHTS FROM GENERAL CONDITIONS
AND GENERAL REQUIREMENTS
• SUPERINTENDENTS
• The General Contractor SHALL employ a full time Superintendent whose
sole responsibility is to monitor and coordinate all facets of the work
• LIQUIDATED DAMAGES
• SUBSTANTIAL COMPLETION
• The contractor will need to meet substantial completion requirements
within ONE HUNDRED SIXTY-FIVE (165) CALENDAR DAYS from
start of contract as defined in Notice to Proceed. Substantial
Completion is defined as all roadway improvements complete, traffic
following in the lane arrangements shown on the plans for finished
roadway, all sidewalk and enhanced crosswalks complete, completion
of the medians, and all erosion control installed/functioning. If the
Contractor goes past the 165 calendar day substantial completion time
count, damages in the amount of THREE THOUSAND THREE
HUNDRED ($3,3000.00) for each calendar day will be assessed.
• FINAL ACCEPTANCE
• Final acceptance must be met within FIFTEEN (15) CALNEDAR DAYS
of Substantial Completion. Liquidated damages in the amount of
THREE THOUSAND THREE HUNDRED ($3,300.00) for each
calendar day will be charged if this schedule has not been met.
15
HIGHLIGHTS FROM GENERAL CONDITIONS
AND GENERAL REQUIREMENTS
• WARRANTY
• All workmanship and material issues will be resolved during
the correction period prior to final acceptance as per
CDOT.
• Hot Mix Asphalt Warranty Bond for $150,000
• 2 year Concrete warranty
• CONSTRUCTION TIME
– One hundred eighty (180) calendar days from start of
contract as defined in Notice to Proceed
• Standard Hours of Operation
• 7:00 AM thru 6:00 PM - Monday thru Friday.
• Given the scope of the proposed improvements, the
City will allow extended working hours and weekends
• Extended Hours requests must be made in writing
a minimum of 5 days prior to the request date
16
HIGHLIGHTS FROM GENERAL CONDITIONS
AND GENERAL REQUIREMENTS
• PROJECT MEETINGS
• Once a week at the construction office, time to be determined.
• Agree to quantities weekly
• Monthly payments confirm acceptance of quantities by the
Contractor. ALL quantity disputes MUST be resolved prior to
monthly progress payments.
• PROGRESS AND SCHEDULE REVISIONS
• Prior to construction, initial schedule must be submitted and
approved
• Schedules shall be updated weekly
• The Contractor may be required to submit additional
schedules depending on the progress of the project.
• RECORD DRAWING PLAN SET
• Contractor will be required to keep record drawings
17
HIGHLIGHTS FROM GENERAL CONDITIONS
AND GENERAL REQUIREMENTS
• HAUL ROUTES
• Arterial and Collector streets only. Contractor will
not be allowed to use residential streets to access
the site with trucks hauling materials.
• SITE CLEAN-UP
• The construction work shall be kept and
accomplished in a neat, clean and orderly fashion
• Tracking pads and street sweeping will need to be
used in order to minimize tracking and meet EPA
storm water quality requirements
• Dust control will be required if necessary
18
HIGHLIGHTS FROM SPECIFICATIONS
19
SECTION 201 – CLEARING AND GRUBBING
• Clearing and Grubbing – LS
• Includes removal of the following
– Bushes and shrubs as identified by Engineer
or Assistant City Forester (Ralph Zentz)
• All removed debris becomes the property of
Contractor
• Debris to be removed from project site, not buried
on-site
20
SECTION 202 - REMOVALS
Removal of Tree – EA
21
SECTION 202 – TREE REMOVAL
• City Forestry Department responsible for
identifying trees to be removed outside those
specified in plans
• City Forestry Contact
Ralph Zentz
970-221-6302
22
SECTION 202 - REMOVALS
Removal of Inlet – EA
23
SECTION 202 - REMOVALS
• Removal of Manhole – EA
• Removal of Valve – EA
• Removal of Pipe – LF
24
SECTION 202 - REMOVALS
Removal of Concrete
Median Cover Material
– SY
Removal of Sidewalk –
SY
Removal of Curb and
Gutter – LF
25
SECTION 202 - REMOVALS
Removal of Concrete
Curb Ramp – SY
Removal of Concrete
Pavement – SY
Removal of Asphalt
Mat – SY
26
SECTION 202 - REMOVALS
Removal of Asphalt
Mat (Planing) – SY
Removal of Pavement
Marking – SF
27
SECTION 202 - REMOVALS
• Sawcutting for all pay items is incidental to the
work and not paid separately
Removal of Traffic Signal Equipment – LS
• Signal Pole Caissons – 4 EA
28
TRAFFIC SIGNAL COORDINATION
• City will install all new traffic signal equipment,
contractor to install conduit and pull boxes
• Contractor to install temp signal, city to maintain
operations
• City Traffic Signal Contact:
Britney Sorenson
970-222-5533
bsorenson@fcgov.com
29
TRAFFIC SIGNAL COORDINATION
• Contractor shall coordinate with City Traffic
Department to meet the following goals
– Traffic Department work is expedited
– Duplication of work is minimized
– Impacts to traffic are minimized
30
STREET LIGHT COORDINATION
• City Light and Power crews will remove and install
all street lighting, associated electric utilities, and
fiber optic vaults
• City Light and Power Contact:
– Rob Irish
31
STREET LIGHT COORDINATION
• Contractor shall coordinate with City Light and
Power Department to meet the following goals
– Light and Power work is expedited
– Duplication of work is minimized
– Impacts to traffic are minimized
32
SECTION 203 - EARTHWORK
• Unclassified Excavation – CY
• Muck Excavation – CY
• Proof Rolling – HOUR
• Backhoe – HOUR
• Combination Loader – HOUR
• Potholing – HOUR
– City potholing and utility survey during design does
not preclude contractors from being required to do
their own potholing
– City pothole info is shown in the plans for
information only
33
SECTION 206, 207
• 206 – Filter Material (Class A) – CY
– Underdrain installed in medians, Section 605
• 207 – Topsoil (Special) – CY
34
SECTION 208 – EROSION CONTROL
• Erosion Log – LF
• Aggregate Bag – LF
• Concrete Washout Structure – EA
• Storm Drain Inlet Protection – EA
• Vehicle Tracking Pad – EA
• Removal and Disposal of Sediment (Labor) – HOUR
• Removal and Disposal of Sediment (Equipment) – HOUR
• Sweeping (Sediment Removal) – HOUR
• Erosion Control Supervisor – DAY
35
SECTION 210 – RESET STRUCTURES
• Reset Water Meter – EA
• Reset Fire Hydrant – EA
• Reset Pull Box – EA
• Adjust Manhole – EA
• Modify Manhole – EA
• Modify Structure – EA
• Adjust Valve Box – EA
36
SECTION 213 - LANDSCAPE
• Landscape Boulder – EA
SECTION 304 – Pavement Section
• Aggregate Base Course (Class 6) – TON
37
SECTION 403 – HOT MIX ASPHALT
• Hot Mix Asphalt (Patching) (Asphalt) – TON
• Hot Mix Asphalt (Grading S) (75) (PG 64-22) – TON
• Hot Mix Asphalt (Grading SX) (100) (PG 64-22) – TON
• Pavement section
SECTION 420 – GEOTEXTILE
• Geotextile (Pavement) – SY
38
SECTIONS 412, 601, 603, 608, 609 –
CONCRETE
• 412 – Concrete Pavement (6 Inch) – SY
• 412 – Concrete Pavement (9 Inch) – SY
• 412 – Concrete Pavement (9 Inch) (Special) – SY
• 412 – Concrete Pavement (9 Inch) (Fast Track) – SY
• 601 – Concrete Class D – CY
• 603 – 15 Inch Reinforced Concrete Pipe (Complete in Place) – LF
• 608 – Concrete Sidewalk (Special) – SY
• 608 – Concrete Sidewalk (6 Inch) – SY
• 608 – Concrete Curb Ramp – SY
• 609 – Curb Type 2 (Section B) – LF
• 609 – Curb and Gutter Type 2 (Section I-B) – LF
• 609 – Curb and Gutter Type 2 (Section II-B) – LF
• 609 – Curb and Gutter Type 2 (Special) – LF
Abrasive Blast Finish – exposed aggregate
39
SECTIONS 412, 601, 603, 608, 609 –
CONCRETE
• Pavement section
40
SECTIONS 412, 601, 603, 608, 609 –
CONCRETE
• Quantities for Fast Track Concrete will be paid only when
required by Project Engineer/Project Manager
• All other uses of high early concrete will be considered
incidental to the work for pay item Concrete Pavement (9
Inch)
• Concrete Curb Ramp pay item includes detectible warning
devices as shown in plans
41
SECTIONS 602, 604, 605, 608, 619, 623
• 602 – Reinforcing Steel – LBS
• 604 – Inlet (Special) (Double) (5 Foot) – EACH
• 604 – Inlet (Special) (Single) (5 Foot) – EACH
• 604 – Manhole Slab Base (10 Foot) – EACH
• 605 – 4 Inch Non-Perforated Pipe Underdrain (Special) – LF
• 605 – 4 Inch Perforated Pipe Underdrain (Special) – LF
• 608 – Metal Sidewalk Culvert – LF
• 619 – Water Meter Vault - EACH
• 619 – Water Service – EACH
– Installation of water service line for irrigation controller as
shown on plans
• 623 – Plastic Pipe (Irrigation Sleeve) – LF
– Valve boxes included in pay item
42
SECTION 610 – MEDIAN
• Median Cover Material (Decorative) – SF
• All medians have an underdrain outfall connected to the storm
system, except the east leg median
43
SECTION 607 – CONSTRUCTION FENCING
• Fence (Plastic) – LF
SECTION 612 - DELINEATOR
• Delineator (Type I) – EACH
44
SECTION 613 - ELECTRICAL
• 2 Inch Electrical Conduit (Bored) – LF
• 2 Inch Electrical Conduit (Plastic) – LF
• 3 Inch Electrical Conduit (Plastic) – LF
• Pull Box (24”x36”x24”) – EACH
• Pull Box (30”x48”x24”) – EACH
45
SECTION 619 – WATER METER VAULT
• Water Meter Vault – EA
46
SECTION 619 – WATER METER VAULT
• Water Meter Vault – EA
47
SECTIONS 620, 626
• 620 – Sanitary Facility – EACH
• 626 – Mobilization – LS
48
SECTIONS 621, 627, 630 – TRAFFIC
• 621 – Detour Pavement – SY
• 627 – 4 Inch Pavement Marking Tape (Removable) – LF
• 627 – 8 Inch Pavement Marking Tape (Removable) – LF
• 627 – 24 Inch Pavement Marking Tape (Removable) – LF
• 630 – Construction Zone Traffic Control – LS
– Covers all traffic control items necessary for the project except
for Flagging and VMS Signs
– Plans developed by Contractor
– Approved by City of Fort Collins at least two (2) weeks prior to
start date
• 630 – Flagging – HOUR
• 630 – Traffic Control Inspection – DAY
• 630 – Traffic Control Management – DAY
49
DETOUR PAVEMENT
• Detour Pavement item includes all work and material necessary to
provide a detour roadway meeting or exceeding the requirements
shown in the plans and specifications
• Pay item measured by square yard of HMA placed in the detour
• Contractor shall remove detour pavement when no longer needed to
maintain traffic
• Contractor shall maintain detour for the entire period it is open to
traffic
• Any needed repairs to be completed at Contractor’s expense
50
SECTION 630 (cont.) – TRAFFIC
• 630 – Portable Message Sign Panel – EACH
– 1 per direction of travel required
– On site and displaying lane closure information at least 5 days
prior to closures
– Required prior to each Traffic Control Plan change
• 630 – Concrete Barrier (Temporary) – LF
• 630 – Impact Attenuator (Temporary) – EACH
• 630 – Business Access Specialty Sign - EACH
• 630 – Traffic Signal (Temporary) – EACH
– Temporary signal plan must be approved by Project Engineer
prior to modification/removal of existing signals
– Contractor shall be responsible for initial installation and
placement
– City will perform any modifications after installation
– One (1) signal head for each open lane of travel
51
TRAFFIC CONTROL
• Allow two (2) weeks for approval of Traffic Control Plans (TCP) for
major phase changes
• Maintain pedestrian and bicycle traffic – TCP to account for these
movements
• Emergency vehicle access into and through construction site
• Provide and maintain continuous temporary access for businesses
and residences
• Maintain 11 foot lanes throughout the project
• See Phasing slide and Traffic Control Plan specification for lane
closure limitations
52
PAVEMENT MARKINGS AND SIGNAGE
• Permanent pavement markings and signage to be furnished /
installed by the City
• Coordinate with City Traffic Department
• Signing and Striping Contact:
Rich Brewbaker
970-221-6792
rbrewbaker@fcgov.com
53
SECTION 700 – FORCE ACCOUNT
• F/A Minor Contract Revisions – FA
• F/A Partnering – FA
• F/A Fuel Cost Adjustment – FA
• F/A Asphalt Cement Cost Adjustment – FA
• F/A On-the-Job Training – HOUR
• F/A Erosion Control – FA
54
UTILITIES
• The following utilities are known to be within the project limit:
Utility/Agency Contact Phone
City Sanitary Sewer Andrew Gingerich 970-221-6232
City Water Andrew Gingerich 970-221-6232
City Storm Sewer Glen Schlueter 970-224-6065
City Forester Ralph Zentz 970-221-6302
City Light & Power Janet McTague 970-221-6700
CenturyLink Bill Johnson 970-377-6401
Xcel Len Hildebrand 970-225-7848
Comcast Don Kapperman 970-567-0245
Level 3 Rick Miller 720-888-7568
City Traffic Joe Olson 970-224-6062
55
UTILITIES
The following utility work will be performed by Utility Company
or their agent:
• CenturyLink – Relocate, adjust and reset pedestals, lines
and manholes
• Comcast – Relocate and reset pedestals, lines and vaults
• Level 3 – Relocate lines and vaults
• City Lighting – Relocate existing lights standards
• City Electric – Relocate vaults and lines
• City Traffic Fiber – Reset traffic control pull boxes and signal
relocations
56
QUESTIONS?