HomeMy WebLinkAboutWORK ORDER - PURCHASE ORDER - 9152489ICY
EXHIBIT "A"
WORK ORDER FORM
PURSUANT TO AN AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
CTL Thompson, Inc.
DATED: April 30, 2013
Work Order Number. OP452626
Purchase Order Number:
Project Title: Fort Collins Laboratory Building Relocation (200 LaPorte Ave )
Commencement Date: May 1, 2015
Completion Date: September 15, 2016
Maximum Fee: (time and reimbursable direct costs):$1,720
Project Description: Construction Observation and Testing Services
Scope of Services: See attached scope of work
Professional agrees to perform the
services identified above and on the
attached forms in accordance with the
terms and conditions contained herein
and in the Professional Services
Agreement between the parties. In the
event of a conflict between or ambiguity
in the terms of the Professional
Services Agreement and this work
order (including the attached forms) the
Professional Services Agreement shall
control.
The attached forms consisting of two
() pages are hereby accepted and
incorporated herein, by this reference,
and Notice to Proceed is hereby given.
Facilities Project Manager: Brian Hergott
City of Fo Gollins _
By: — /6
Date. / [� / 47.2 h-5
By:
Director of Purchasing and Risk Management
(over $60,000,00)
Date:
CTL Thompson Rep:
Name:_ Q t .cti-A l,cf-c
\s —
Signature: t\
Date: 44 i 2-2-[ NS
FACILITIES REQUISITION FORM
VENDOR CTLThompson,Inc.
REQ BY: Brian Hergott- Operation Services Work Order# OP-466543
CHARGE# 510108.562020
DATE 4/22115
Billable? Y/N Yes
TOTAL COST: $1.720.00 BUYER: John Stephen
OTY DESCRIPTION
Provide construction observation and material testing services for the relocation of the Laboratory (Butterfly)
building at 222 LaPorte Ave. Please refer to attached proposal dated 4110115 for more details.
ADDITIONAL INFO
COMPUTER INPUT INFORMATION:
VENDOR# REQUISITION # DATE ENTERED:
COST
$1,720.00
April 10, 2015
Revised April 22, 2015
City of Fort Collins
300 Laporte Avenue
P.O. Box 580
Fort Collins, Colorado 80522-0580
Attention: Mr. Brian Hergott, LEED AP
Facilities Project Manager
Subject: Fee Estimate for Construction Observation and Materials Testing Services
City of Fort Collins Utility Administration Building
222 Laporte Avenue
Fort Collins, Colorado
CTLIT Proposal No. FC-15-0107
At your request, CTLIThompson, Inc. is pleased to provide this fee estimate for Construction
Observation and Materials Testing services for the City of Fort Collins Utility Administration Building
project located at 222 Laporte Avenue in Fort Collins, Colorado. We understand testing for this
project should be performed in accordance with City of Fort Collins standards and specifications.
We further understand that the city will use our estimate for the basis of establishing a budget for the
project and to issue a purchase order for our services. Our estimated scope of services and
associated fees were prepared according to the terms and conditions of our professional services
agreement with the City of Fort Collins and are presented below.
UTILITY ADMINISTRATION BUILDING
Earthwork: Compaction testing may be required for items such as grade beam backfill, slab
subgrade, pavement subgrade, utility trench backfill, sidewalk subgrade, curb subgrade, and
retaining wall backfill. We anticipate we will be able to reuse some of the proctors from our previous
project at this site. We estimate a total of 50 site visits will be necessary.
Engineering Technician 50 days x 2 hrs/day x $60/hr $6,000.00
Standard Proctor 2 tests x $80/ea $160.00
Atterberg Limits 2 tests x $60/ea $120.00
Gradation 2 tests x $70/ea $140.00
Subtotal: $6,420.00
Concrete Testing: Concrete testing will be required for the piers, columns, grade beams, slabs, curb,
gutter, and sidewalk. We estimate 60 concrete tests consisting of 4 cylinders each will be
necessary.
Concrete Cylinders 60 tests x $160/test $9,600.00
Subtotal: $9,600.00
400 North Link Lane I Fort Collins, Colorado 80524
Telephone: 970-206-9455 Fax- 970-206-9441
Ed
Drilled Pier Observation: Full-time observation of the drilled piers will be required. We understand
approximately 46 piers are planned. We anticipate the contractor will be able to install approximately
6 piers per day for a total of 8 full -day site visits. If casing is required then drilling may take longer
and additional site visits would be necessary. Drilled pier observation will include reinforcing steel
observations for the piers — concrete testing will be charged at the rates listed above.
Engineering Technician 8 days x 8 hrs/day x $60/hour $3,840.00
Subtotal: $3,840.00
Reinforcing Steel Observation: Reinforcing steel observations will be necessary for the grade
beams, columns, walls, and slabs. We estimate a total of 24 site visits will be necessary.
Engineering Technician 24 days x 2 hrs/day x $50/hr $2,400.00
Subtotal: $2,400.00
Masonry Special Inspection: Masonry inspection and sampling will be necessary for the walls and
elevator shaft. We estimate a total of 44 site visits, and 2 sets of grout, mortar, and prism samples
will be necessary.
Engineering Technician 44 days x 3 hrs/day x $60/hr $7,920.00
Prisms 2 sets x 3 prisms/set x $80/prism $480.00
Grout Cores' 2 sets x 4 cores/set x $40/core $320.00
Mortar Cubes 2 sets x $125/set $250.00
Subtotal: $8,970.00
Structural Steel Weld and Bolt Inspection: Structural steel weld and bolt inspections will be
necessary and will be performed by an [CC certified inspector. We estimate a total of 40 site visits
will be necessary.
Engineering Technician" 40 days x 3 hrs/day x $60/hr $7,200.00
Subtotal: $7,200.00
TOTAL ESTIMATED FEE (UAB): $38,430.00
If grout testing is required for every grout placement, there would not be additional site visits;
however, we would make additional samples which would add the following costs:
Grout Cores' 42 sets x 4 cores/set x $40/core $6,720.00
" If ultrasonic testing of welds is required, 3 site visits from our Denver office would be necessary
and would cost the following:
Engineering Technician 3 days x 5 hrs/day x $60/hr 900.00
TOTAL ESTIMATED FEE (UAB INCLUDING ADDITIONAL SERVICES):
$46,050.00
2
CITY OF FORT COLLINS
FORT COLLINS UTILITY ADMINISTRATION BUILDING
CTL I T FEE ESTIMATE NO. FC-1"107
0
BUTTERFLY BUILDING
Earthwork: Compaction testing may be required for items such as footing subgrade and wall backfill.
We estimate a total of 4 site visits will be necessary.
Engineering Technician 4 days x 2 hrs/day x $60/hr $480.00
Subtotal: $480.00
Concrete Testing: Concrete testing will be required for the footings and foundation walls. We
estimate 2 concrete tests consisting of 4 cylinders each will be necessary.
Concrete Cylinders 2 tests x $160/test $320.00
Subtotal: $320.00
Reinforcing Steel Observation: Reinforcing steel observations will be necessary for the footings and
walls. We estimate a total of 2 site visits will be necessary.
Engineering Technician 2 days x 2 hrs/day x $50/hr $200.00
Subtotal: $200.00
Structural Inspection: Structural inspections will be necessary and will be performed by an ICC
certified inspector. We estimate a total of 4 site visits will be necessary.
Engineering Technician" 4 days x 3 hrs/day x $60/hr
Subtotal:
TOTAL ESTIMATED FEE (BUTTERFLY BUILDING)
720.00
$720.00
$1,720.00
It should be emphasized that this estimate is based upon assumptions of actual quantities and
contractor's schedule. The fee will be charged only for the actual hours and unit rates presented for
tests and observations requested by the owner, contractor or subcontractors who schedule the
services.
If we can be of further assistance, please contact us at your convenience.
Very truly yours,
CTL I THOMPSON, INC.
Heather Grubb
Field Department Manager
CITY OF FORT COLONS 3
FORT COLONS UTILITY ADMINISTRATION BUILDING
CTL I T FEE ESTIMATE NO_ FC-15-0107