HomeMy WebLinkAbout102541 CH2M HILL INC - PURCHASE ORDER - 9200382 (4)Change Order Form (for Work Orders)
Official Purchasing Form
Last updated 10/2017
CHANGE ORDER
NO. 1
PROJECT TITLE: Canal Importation Selected Plan
CONTRACTOR: CH2M HILL Engineers, Inc.
WORK ORDER NUMBER: TRB-2020-01
PO NUMBER: 9200382
DESCRIPTION:
1. Reason for Change: Scope & Cost
2. Description of Change: This project will update the Selected Plan of Improvements for the
Canal Importation Basin. This change order will add the Manchester/Scarborough flow path
to the scope of work for this project. The original work order fee is $149,987.25. This
additional work will add $13,194 to the total fee.
The Manchester Scarborough flow path was not included in the 2014 hydrologic or hydraulic
updates for the Canal Importation Basin and was not included in the scope of work contracted
as Work Order Number: TRB-2020-01. This amendment adds alternatives analysis and
development of a selected plan for the Manchester Scarborough flow path.
3. Change in Work Order Price: $13,194.00
4. Completion Date (if changed): NA
ORIGINAL WORK ORDER PRICE $ 149,987.25
TOTAL APPROVED CHANGE ORDER $ 0.00
TOTAL PENDING CHANGE ORDER $ 0.00
TOTAL THIS CHANGE ORDER $ 13,194.00
TOTAL % OF THIS CHANGE ORDER 8.79 %
TOTAL C.O.% OF ORIGINAL WORK ORDER 8.79 %
ADJUSTED WORK ORDER COST $ 163,181.25
CONTRACTOR: CH2M HILL Engineers, Inc.
By: Date:
Name: Title:
ACCEPTANCE: Date:
Theodore Bender, Civil Engineer II
DocuSign Envelope ID: FC2CB7DE-59A3-4126-B6CF-376917FBABB2
September 16, 2020
Kyle Hamilton Designated Manager
September 16, 2020
Change Order Form (for Work Orders)
Official Purchasing Form
Last updated 10/2017
REVIEWED: Date:
Marisa Donegon, Buyer II
REQUISITION ENTERED BY: Date:
ACCEPTANCE: Date:
Daniel Evans, Civil Engineer III
ACCEPTANCE: Date:
Ken Sampley, Director, Civil Engineering
ACCEPTANCE: Date:
Matt Fater, Interim Deputy Director, Water Engineering & Field Services
ACCEPTANCE: Date:
Gerry Paul, Purchasing Director
(if greater than $60,000)
DocuSign Envelope ID: FC2CB7DE-59A3-4126-B6CF-376917FBABB2
Melissa Walker Coordinator, Finance
9/4/2020
September 16, 2020
September 16, 2020
September 16, 2020
September 21, 2020
September 21, 2020
PAGE 1 OF 6
Attachment A - Scope of Services
Attachment A to the AGREEMENT between the City of Fort Collins, Colorado, a Municipal
Corporation, hereinafter referred to as the City, and CH2M HILL Engineers, Inc., hereinafter referred
to as the Professional, for a project generally described as:
Professional Engineering Services to update the alternatives analysis and selected plan for
the Canal Importation Basin Master Plan.
This scope of service will be performed under an amendment to the Work Order issued in
accordance with the Professional Service Agreement No. 8497 for Stormwater Consulting
Engineering Services, dated September 25, 2017. This scope of work is Amendment 1 to Work Order
Number: TRB-2020-01.
The Professional’s services for the project are detailed hereinafter.
Project Objective: Update the alternatives analysis and selected plan for the Canal Importation Basin
Master Plan including the Manchester Scarborough flow path.
It is understood that the City will designate Mr. Theodore Bender as the City’s Project Manager
(City’s PM). Mr. Theodore Bender will be the City’s primary point of contact with respect to the work
performed under this AGREEMENT, with authority to transmit instructions, receive information, and
interpret and define City policies and decisions relative to elements pertinent to the work covered
by this AGREEMENT.
The Canal Importation Basin is a five square mile basin located in west-central Fort Collins with three
major irrigation canals traversing the basin from north to south (Pleasant Valley and Lake Canal,
New Mercer Ditch, and Larimer County Canal No. 2). The canals intercept runoff within the basin
and transport it out of the basin and also spill runoff into the basin where the canals are capacity
limited. The Canal Importation Basin has a long history of flooding including storm events in 1938,
1975, 1992, and 1997. The most recent drainage basin master plan for the Canal Importation Basin
was completed in 2001 with updates to the hydraulics and hydrology completed in 2014. There are
five primary flow paths within the Canal Importation Basin conveying flows from west to east to the
Old Town Basin and Spring Creek Basin:
1. Mulberry Street Flow Path
2. Plum Street Channel
3. Clearview Channel
4. Canal Importation Channel
5. Elizabeth Street Channel
The scope of work for this master plan update is to update the Alternatives Analysis and Conceptual
Design using the 2014 updates to the hydraulics and hydrology, account for any constructed
improvements, consider current design practices, and evaluate the basin in a more holistic approach
including parks, trails, nature areas, and water quality opportunities.
DocuSign Envelope ID: FC2CB7DE-59A3-4126-B6CF-376917FBABB2
PAGE 2 OF 6
Figure 1: Canal Importation Basin
The Manchester Scarborough flow path was not included in the 2014 hydrologic or hydraulic
updates for the Canal Importation Basin, and was not included in the scope of work contracted as
Work Order Number: TRB-2020-01. This amendment adds alternatives analysis and development of
a selected plan for the Manchester Scarborough flow path.
Task 1 – Project Management and Meetings
Professional’s Project Manager (Professional’s PM) will manage the scope, schedule, and budget,
and keep the City’s PM informed throughout the project. Professional’s PM will prepare and submit
monthly an invoice for services performed and a brief status report. The report will include a
narrative description of progress to-date, actual costs for each Task, estimates of percent complete,
and potential cost variances. The following subtasks are also included in this task.
• Work Order Number: TRB-2020-01 included a total of 7 monthly meetings. This amendment
adds one additional monthly meeting. It was also assumed that the project would be
completed over a 6 month period. This amendment adds 5 months to the overall schedule
for a total of 11 months.
• Project coordination with subcontractors.
Deliverables:
• Monthly invoice and status report.
• Prepare and submit brief meeting minutes that summarize key decisions and action items in
electronic format. Develop a log of key decisions and action items.
Assumptions:
• Project coordination meetings will be held virtually.
• It is assumed that the project will be completed by December 31, 2020.
Task 2 – Data Collection and Review
Professional will review data provided by the City for the Manchester Scarborough flow path
including, but not limited to the following documents:
DocuSign Envelope ID: FC2CB7DE-59A3-4126-B6CF-376917FBABB2
PAGE 3 OF 6
• Canal Importation Basin Master Drainage Plan, Anderson Consulting Engineers, Inc., 2001.
• West Vine Unsteady Canal HEC-RAS Model.
• City of Fort Collins GIS Data including parcels, right-of-way, and utilities.
• Existing LiDAR topography.
• City of Fort Collins Trail Master Plan.
• City of Fort Collins Nature in the City Program.
Professional will also perform a site visit to review the current site conditions, the improvements
proposed in the current drainage master plan, and evaluate opportunities for enhancements to the
basin including water quality, open space and natural areas, parks, trails, and habitat.
Deliverables:
• There are no deliverables associated with this task.
Assumptions:
• Existing conditions hydrologic modeling has been completed and is not required for this
alternatives analysis.
Task 3 – Review of Current Hydrologic Model and Canal HEC-RAS Model
Professional will perform a due diligence review of the current hydrologic model and the unsteady
HEC-RAS model for the PV&L Canal. Professional will coordinate any suggested revisions with the
City and revise the models, as necessary.
Per coordination with City staff, Professional will add existing storm pipes 24” in diameter and larger
to the existing conditions hydrologic model. Professional will also sub divide existing basins to
approximately 25 to 30 acres in size. This revised model will be the baseline model for the
alternatives analysis.
Deliverables:
• Update to Technical Memorandum summarizing any changes to the current hydrologic
model.
• Revised hydrologic model including existing storm drains 24” in diameter and larger and sub
divided basins.
Assumptions:
• The Hydrologic and Hydraulic Model Review Summary dated June 18, 2020 will be updated
to include discussion related to the Manchester Scarborough flow path.
• The existing 2017 City of Fort Collins rain on grid analysis will be used to locate basin design
points when sub dividing the basins.
Task 4 – Alternatives Analysis
For the Manchester Scarborough flow path, Professional will utilize the previously completed
Master Drainage Plan and updates to the Master Drainage Plan, information collected through site
visits, and information collected through coordination with the City to develop alternative
drainageway plans in GIS to address problem areas within the basin. Problem areas include flooding
issues (structures, major roads, and critical facilities), undersized infrastructure, channel or bank
instability for open channels, interaction between drainage features and the canals within the basin,
DocuSign Envelope ID: FC2CB7DE-59A3-4126-B6CF-376917FBABB2
PAGE 4 OF 6
and ecological issues. The alternatives analysis will also include opportunities for water quality
enhancement along the flow path. The alternative improvements will focus on new storm sewer
pipe systems, the existing detention pond upstream of Taft Hill Road, and the existing detention
pond west of the PV&L Canal.
Professional will also perform the following tasks:
• Identify problem areas for the 100-year flood event.
• Evaluate up to two alternatives for the Manchester Scarborough flow path. The two
alternatives are assumed to be a detention option and a conveyance option. The detention
option will focus on maximizing detention along the flow path. The conveyance option will
focus on increasing the conveyance capacity of open channel and pipe systems with no or
limited detention.
• Develop alternative hydrologic models to model the alternative improvements.
• Evaluate water quality opportunities within the basin including those identified as part of
the 2001 master plan.
• Develop a recommended plan for review by the City PM and other City staff.
• Determine sizing for proposed improvements including pipes and detention and water
quality facilities.
• Determine right-of-way required for each alternative.
Deliverables:
• Professional will develop schematic plans in GIS format showing alternative improvements.
• Professional will develop alternative hydrologic models to model the alternative
improvements.
• Revise the Canal Importation Basin – Selected Plan Update Alternatives Analysis Report,
dated August 7, 2020 with information for the Manchester Scarborough flow path.
• Provide Engineer’s Opinion of Probable Cost for each alternative plan.
Assumptions:
• Deliverables will be developed in PDF format. Deliverables will also include AutoCAD, GIS,
and SWMM files.
• Alternatives will consider the 100-year flow rate. The floodway will not be revised with the
alternatives analysis.
• Topographic Survey will not be completed as part of this analysis.
• Geotechnical investigations will not be completed as part of this analysis.
• Subsurface underground investigation will not be completed as part of this analysis. Utility
data will be provided by the City in GIS format.
• Development of alternative hydraulic models to model the alternative improvements is not
required.
• Development of approximate post-project floodplains for each alternative is not required.
DocuSign Envelope ID: FC2CB7DE-59A3-4126-B6CF-376917FBABB2
PAGE 5 OF 6
• Development of damage estimates for the baseline condition and estimated damage
reduction for each alternative is not required.
• Identification of trail, park, and natural space opportunities are not included in this
alternatives analysis given that the flow path is through a fully developed residential
neighborhood.
Task 5 – Conceptual Design for Selected Plan
After City staff review of the Alternatives Analysis and Recommended Plan, City Staff and
Professional will work together to determine the Selected Plan for the Manchester Scarborough
flow path to move forward to Conceptual Design. The selected plan will move forward into a more
detailed Conceptual Design and will include the following tasks:
• Develop a hydrologic model for the Selected Plan, if different than one of the alternative
plans.
• Determined sizing for proposed improvements including pipes, detention facilities, and
water quality facilities.
• Develop typical cross sections in CAD format for proposed improvements.
• Determine right-of-way required for the Selected Plan.
• Coordination with Stream Landscape Architecture.
• QA/QC review of work products and models.
Deliverables:
• Update the report documenting the Alternatives Analysis with the Conceptual Design.
• Develop Conceptual Design plans in CAD format. Drawings include plan and profile drawings
for pipe sections and open channels, grading plans for detention or water quality facilities,
and typical details.
• Develop a conceptual design hydrologic model.
• Provide Engineer’s Opinion of Probable Cost for the Selected Plan including lifecycle costs.
Assumptions
• Deliverables will be developed in PDF and hard copy format. Deliverables will also include
AutoCAD, GIS, and SWMM files.
• The conceptual design analysis will be documented in a combined conceptual design report
along with the five flow paths included in the original AGREEMENT.
• The conceptual design will consider the 100-year flow rate. The floodway will not be revised
with this analysis.
• Development of a selected plan hydraulic model is note required.
• Development of a post-project floodplain is not required.
• Development of a damage reduction estimate for the selected plan is not required.
DocuSign Envelope ID: FC2CB7DE-59A3-4126-B6CF-376917FBABB2
PAGE 6 OF 6
Schedule
An anticipated schedule is shown below in Table 1.
Table 1: Project Schedule
Activity Anticipated Milestone Dates
Notice To Proceed September 8, 2020
Review of Hydrologic and Hydraulic Models September 22, 2020
Completion of Alternatives Analysis October 22, 2020
Determine Selected Plan To be determined – pending public
outreach
Completion of Conceptual Design of Selected Plan To be determined – pending public
outreach
Fee Estimate
Compensation will be on a Time and Materials – Not to Exceed basis. Hourly rates are in accordance
with Contract No. 8497 Stormwater Consulting Engineering Services. Subconsultants will be billed at
cost plus 5%. Refer to Attachment B for a detailed breakdown of the fee estimate.
Project Assumptions
• In providing opinions of cost, financial analyses, economic feasibility projections, and
schedules for the Project, Professional has no control over cost or price of labor and
materials; unknown or latent conditions of existing equipment or structures that may affect
operation or maintenance costs; competitive bidding procedures and market conditions;
time or quality of performance by operating personnel or third parties; and other economic
and operational factors that may materially affect the ultimate Project cost or schedule.
Therefore, Professional makes no warranty that City’s actual Project costs, financial aspects,
economic feasibility, or schedules will not vary from Professional’s opinions, analyses,
projections, or estimates.
• It is assumed that data provided by others is accurate, complete, and will be provided in a
timely fashion. Correction of data provided by others is not included herein.
DocuSign Envelope ID: FC2CB7DE-59A3-4126-B6CF-376917FBABB2
Attachment B
Compensation Schedule
Task
Number Task Description
Kyle Hamilton
Principal Project
Manager
Aaron Cook
Project Manager
Kiersten Hines
Staff Engineer 2
Jeremy Quan
GIS Specialist
Chris Lamb
Engineering Tech 2
Lisa Hoffman
Office/Clerical/Accountin
g
Labor
Hours Labor Expense
Subcontractor Subtask Cost Total Cost
Per Diem Code/Classification 03 05 08 07 14 19
Labor Rates
(1) $235 $173 $122 $135 $92 $83
1 Project Management and Meetings $ 1,448.00
Project Management 4 2 6 $ 858.00 $ 858.00
Meetings 2 2 4 $ 590.00 $ 590.00
2 Data Collection and Review $ 1,159.00
Review Existing Data 1 2 3 $ 417.00 $ 417.00
Site Visit 4 4 $ 692.00 $ 50.00 $ 742.00
3 Review Hydrologic and Hydraulic Models $ 2,391.00
Review Hydrology and Hydraulic Models 1 2 3 $ 417.00 $ 417.00
Revised SWMM Models 2 8 10 $ 1,322.00 $ 1,322.00
Update Technical Memorandum 1 1 2 4 $ 652.00 $ 652.00
4 Alternatives Analysis $ 3,969.00
Identify Problem Areas 1 2 3 $ 417.00 $ 417.00
Develop Alternatives 2 2 4 $ 590.00 $ 590.00
Develop Schematic Plans 1 2 4 7 $ 957.00 $ 957.00
Alternative Hydrologic Models 2 4 6 $ 834.00 $ 834.00
Cost Estimates 2 2 4 $ 590.00 $ 590.00
Prepare Report 1 2 3 $ 581.00 $ 581.00
5 Conceptual Design for Selected Plan $ 4,227.00
Conceptual Design of Selected Plan
(calculations, sizing, cross sections, etc.)
2 2 4 $ 590.00 $ 590.00
Conceptual Design Hydrologic Analysis 2 2 4 $ 590.00 $ 590.00
Cost Estimate 1 2 3 $ 417.00 $ 417.00
Conceptual Design Drawings 1 2 4 8 15 $ 1,805.00 $ 1,805.00
Prepare Report 1 2 2 5 $ 825.00 $ 825.00
Total 4 34 40 4 8 2 92 $ 13,144.00 $ 50.00 $ - $ 13,194.00 $ 13,194.00
1
Rates are in accordance with Contract No. 8497 Stormwater Consulting Engineering Services
Exhibit_B_Fee_Canal_Importation_Basin_Amend_1.xlsx\Fee Estimate 8/25/2020
DocuSign Envelope ID: FC2CB7DE-59A3-4126-B6CF-376917FBABB2