Loading...
HomeMy WebLinkAboutCORRESPONDENCE - RFP - 9105 CONSTRUCTION MANAGER/GENERAL CONTRACTOR FOR THE NATURAL AREAS DEPARTMENTOfficial Purchasing Document Last updated 10/2017 Services Agreement – Work Order Type 9105 Construction Manager/General Contractor for the Natural Areas Department Page 9 of 113 EXHIBIT A WORK ORDER FORM PURSUANT TO A MASTER AGREEMENT BETWEEN THE CITY OF FORT COLLINS AND J-2 CONTRACTING COMPANY WORK ORDER NUMBER: PROJECT TITLE: ORIGINAL BID/RFP NUMBER & NAME: 9105 CM/GC for the Natural Areas Department MASTER AGREEMENT EFFECTIVE DATE: August 1, 2020 WORK ORDER COMMENCEMENT DATE: WORK ORDER COMPLETION DATE: MAXIMUM FEE: (time and reimbursable direct costs): PROJECT DESCRIPTION/SCOPE OF SERVICES: Service Provider agrees to perform the services identified above and on the attached forms in accordance with the terms and conditions contained herein and in the Master Agreement between the parties. In the event of a conflict between or ambiguity in the terms of the Master Agreement and this Work Order (including the attached forms) the Master Agreement shall control. The attached forms consisting of ( ) page(s) are hereby accepted and incorporated herein, by this reference, and Notice to Proceed is hereby given after all parties have signed this document. SERVICE PROVIDER: Date: ACCEPTANCE: Date: REVIEWED: Date: ACCEPTANCE: Date: DocuSign Envelope ID: 3167A3FA-EC0C-4993-8060-F57A0526A99D fifteen 15 See attached $22,255.86 October 31, 2020 September 1, 2020 Siphon Overpass Pedestrian Bridge Modifications 400903822 - J-2 - 2020 - 01 DocuSign Envelope ID: 789F2B50-BAC8-4E04-9C84-608730988F11 Chris Leone President 8/25/2020 Civil Engineer II 8/25/2020 Caleb Feaver Dan Woodward 8/25/2020 Engineering - Capital Projects Elliot Dale 8/28/2020 Buyer $ 15,065.96 17.65% $ 2,659.14 $ 1,440.00 11.65% $ 167.76 $ 2,618.00 11.65% $ 305.00 $ 19,123.96 $3,131.90 $22,255.86 Subcontractors Overhed Profit and Insurance % Subcontractors Markup Big R Bridge 3733 Refurbishment GMP PROPOSAL Self Preform Markup Total DIRECT CONSTRUCTION COSTS: Total Markup CALCULATED ESTIMATE OF TOTAL PROJECT COST Materials Construction Costs: (Labor & Equipment ) Materials Overhed Profit and Insurance % Self Preform Markup Subcontractors Construction Costs: (Labor & Equipment ) Self Preform Overhed Profit and Insurance % Pricing Rollup Self Preform Construction Costs: (Labor & Equipment ) DocuSign Envelope ID: 789F2B50-BAC8-4E04-9C84-608730988F11 Cost Component Summary Report Project Name: Refurbish Big R Bridge 3733 Customer: City Of Fort Collins Job Number: Billing Address: 215 North Mason Street, 2nd Floor Bid As: Fort Collins, CO 80524 Estimator: Phone: Project Address: Contact: Completion Date: Labor Type Total Quantity UM Average Unit Cost Total Cost Labor NA Laborer (Dylan, Ladd, Josh, Cody) 94.50 HR $30.18 $2,851.96 NA Operator (Graig, Etc..) 9.00 HR $38.81 $349.27 Superintendent/PM (Chris/Chance/Ryan/Carol) 12.00 HR $80.36 $964.30 Welder Fabricator 94.50 HR $67.09 $6,339.63 Total: $10,505.15 Equipment Name Total Quantity UM Average Unit Cost Total Cost Equipment BOBCAT E45 Mini Excavator 24.14 HR $39.50 $953.57 Welding And Service Truck 73.50 HR $49.08 $3,607.23 Total: $4,560.81 Material Type Total Quantity UM Average Unit Cost Total Cost Material Concrete Cribbing 8.00 UNIT $180.00 $1,440.00 Total: $1,440.00 Item # Description Total Quantity UM Unit Cost Total Cost Subcontracted [3] 30 Yard Roll Off And Single Service (Unassigned) 1.00 EACH $488.00 $488.00 [2] Sub - HR 140 Ton Crane (Unassigned) 6.00 HR $355.00 $2,130.00 Total: $2,618.00 8/16/2020 10:03:26 PM Page 1 of 1 DocuSign Envelope ID: 789F2B50-BAC8-4E04-9C84-608730988F11 To: City Of Fort Collins Contact: Project Name: Refurbish Big R Bridge 3733 Bid Number: Fort Collins, CO 80524 Fax: Address: 215 North Mason Street, 2nd Floor Phone: Project Location: Bid Date: Item # Item Description Estimated Quantity Unit Unit Price Total Price 1 Mobilization 1.00 LS $2,183.23 $2,183.23 2 Hoist And Re-crib Bridge To Min 3.5' Height. Shim To 1.00 LS $5,456.06 $5,456.06 Level Recheck And Shim At Deck Removal Completion 3 Deck Remnant Removal: Stay-in-Place Forms (SIP's) 1.00 LS $6,900.54 $6,900.54 O Air Arc And Grind SIP Plug Welded Connection Devices Flush With The Floorbeam Top Flanges. O Remove And Dispose Of SIP's 4 Deck Remnant Removal: Deck Longitudinal Channels 1.00 LS $3,974.66 $3,974.66 O Grind Welds Between The Tops Of The Deck Channels And The Truss Verticals. O Grind Welds Between The Deck Channel Bottom Flange Toes And The Tops Of The Floor Beams. O Remove And Dispose Of Deck Channels 5 Deck Remnant Removal: Deck End Plates. 1.00 LS $609.47 $609.47 O Grind Welds Between The Deck End Plates And The Truss End Posts. O Grind Welds Between The Deck End Plates And The End Floor Beams. O Remove And Dispose Of End Plates Total Bid Price: $19,123.96 Notes: • J-2 Contracting Company proposes to furnish all labor, material, and equipment to perform the following work: Hoist, Reset, and Refurbish Pedestrian brisge per line item descriptions • Exclusions: Permits, Fees, Testing, Staking, • This is a not to exceed estimate based on projected quantities, actual billing to be based on contracted labor and equipment rates • Quotation void if not accepted within 30 Days • Payment terms are: Monthly progress payments due in 30 days net with 1 1/2% per month finance charges for balances over 30 days old ACCEPTED: The above prices, specifications and conditions are satisfactory and are hereby accepted. Buyer: Signature: Date of Acceptance: CONFIRMED: J-2 Contracting Company Authorized Signature: Estimator: 8/16/2020 10:18:38 PM Page 1 of 1 DocuSign Envelope ID: 789F2B50-BAC8-4E04-9C84-608730988F11 This scope of work is pertinent to a City-hired contractor to perform work on the steel pedestrian truss that is stored off Mulberry Street in the City of Fort Collins. The work will include jacking the truss to level and removing deck remnants (stay-in-place forms, deck end plates, and deck longitudinal channels). This welded weathering steel Pratt Truss consists of box shaped members and has parallel chords, a 165’ span, and 24 panels. Floorbeams are welded to the truss vertical members, approximately 10” above the bottom chords, per plans. Note that bottom chords and diagonal members are in tension, and thus considered fracture critical. Truss verticals are in compression. Also note that floorbeams are spaced at less than 7’ throughout, and are thus not considered fracture critical. The truss is stored in a yard off Mulberry Street. It was relocated here in 2015. Truss nodes, panels and floorbeams are numbered from north to south, starting with Floorbeam/Node “0” and Panel “1”. Trusses are designated as west and east. There are bolted field splices in Panel 12. The concrete portion of the deck was removed, prior to its relocation to the site, but deck remnants remain (stay-in-place forms, deck end plates, and deck end channels). As the truss sits in the yard, the end floorbeam at the North End (Floorbeam 0) is out of level by ¼” over 2’. There are timber blocks below the end post bearing plates at this location. The end floorbeam at the South End (Floorbeam 24) is out of level by 7/8” over 2’. At the south end, there are settled wooden blocks located below the truss bottom chords; there are no wooden block supporting the end post bearing plates. Work to be performed is as follows: 1. Jacking of the Truss (to be done first): • General: o Jacks shall be used that have adequate capacity to support the structure. o Contractor will use appropriate jacking method. o Contractor will provide proper support/blocking between the jack and the bottom chord/sole plate to prevent damage while jacking. o Cribbing to be built as the structure is jacked to prevent large fall if the jacks fail. o Jacks below west and east truss will be simultaneously raised/lowered when jacking one end of the structure (no differential jacking/lowering). o Observers from the City and/or Baker will be on-site to ensure no differential jacking or signs of structural issues, such as torsion, overstressing, etc. • North end: o Place jacks below the truss bottom chords, near the end posts. o Provide support between the jacks and truss bottom chord to distribute load, and to ensure there is no damage to the bottom chord. This support should be at least as wide as the truss bottom chord o Provide support between the jack base and existing ground, if deemed required by the contractor. o Simultaneously jack each truss until the end floorbeam is level and the floorbeam underside is approximately 4’ off the ground. o Provide timber support (ie cribbing) below each bearing plate. o Lower jacks onto the timber supports below bearing plates, so that the underside of the floorbeam is at least 3.5’ off the ground. o Check truss for level before removing jacks. o Check truss for signs of jacking damage or torsion DRAFT DocuSign Envelope ID: 789F2B50-BAC8-4E04-9C84-608730988F11 • South end o Excavate soil, if required, to allow jack placement below the bearing plates. o Provide support/blocking between the jacks and bearing plates, if deemed required by the contractor. o Provide support between the jacks and the ground, if deemed required by the contractor. o Simultaneously jack each truss until the floorbeam is level and approximately 4’ above the ground. o Place timber supports below the truss bottom chord, leaving room for subsequent jack installation below the truss bottom chords, near the end of the trusses. o Lower the jacks so that the truss rests on the timber below the bottom chord. o Remove jacks from below the bearing plates. o Re-install jacks below truss bottom chord (near the bearings) and snug jacks up against truss. o Place supports below masonry plates to allow at least 3.5’ clearance below the end floorbeam. o Raise jack enough to remove timber below truss bottom chord and slowly lower truss onto timber below the bearing plates. o Check truss for level before removing jacks. o Check truss for signs of jacking damage or torsion. 2. Deck Remnant Removal: • General o When grinding all welds and Stay-in-Place Form connection devices, take care not to remove material from the floorbeams or truss members. • Stay-in-Place Forms (SIP’s) o Grind SIP plug welded connection devices flush with the floorbeam top flanges. o Remove and dispose of SIP’s. • Deck Longitudinal Channels o Grind welds between the tops of the deck channels and the truss verticals. o Grind welds between the deck channel bottom flange toes and the tops of the floorbeams. o All welds should be ground flush with the truss verticals and floorbeams. o Remove deck channels from the structure. o Channels to be stored/removed from the site, as directed by the City. • Deck End Plates. o Grind welds between the deck end plates and the truss end posts. o Grind welds between the deck end plates and the end floorbeams. o Remove end plates from the structure. o End plates to be stored/removed from the site, as directed by the City. 3. Final check of truss level: • After removing deck remnants, do a final check of end floorbeams for levelness and clearance, in the event subsequent settlement has occurred. • If required, jack, shim and level the truss before leaving site, following jacking procedures mentioned under bullet no. 1 above. Attachments: o Sheet(s) from Baker 06/26/2020 initial inspection. o Sheet(s) from Baker 2/11/2015 Inspection Findings Report. DRAFT DocuSign Envelope ID: 789F2B50-BAC8-4E04-9C84-608730988F11 Prepared by: Page 1 of 17 Bridge No. Mulberry Pedestrian Truss Inspected by: M. Orlowsky Town: Fort Collins Inspection Date 6-26-2020 Fort Collins W.O. #14 Photo #1 : West elevation, looking southeast. Photo #2 : East elevation, looking southwest. DocuSign Envelope ID: 789F2B50-BAC8-4E04-9C84-608730988F11 Prepared by: Page 2 of 17 Bridge No. Mulberry Pedestrian Truss Inspected by: M. Orlowsky Town: Fort Collins Inspection Date 6-26-2020 Fort Collins W.O. #14 Photo #3 : Typical underside, looking north from floorbeam 7. Note the leakage stains along the floorbeams. Floorbeam weathering steel protective coating is failing. Photo #4 : Typical underside, looking north from floorbeam 8. Note the leakage stains along the floorbeams. DocuSign Envelope ID: 789F2B50-BAC8-4E04-9C84-608730988F11 Prepared by: Page 3 of 17 Bridge No. Mulberry Pedestrian Truss Inspected by: M. Orlowsky Town: Fort Collins Inspection Date 6-26-2020 Fort Collins W.O. #14 Photo #5 : Looking south through the structure from the north end. Photo #6 : Looking north through the structure from the south end. DocuSign Envelope ID: 789F2B50-BAC8-4E04-9C84-608730988F11 Prepared by: Page 4 of 17 Bridge No. Mulberry Pedestrian Truss Inspected by: M. Orlowsky Town: Fort Collins Inspection Date 6-26-2020 Fort Collins W.O. #14 Photo #7 : North end of the bridge. End of bridge is supported by timber blocks at the bearing areas. Structure is out of level ¼” over 2’, measured at the end floorbeam. Photo #8 : South end of the bridge. Note that the timber support blocks are installed below the truss bottom chord, NOT at the sole plates. Structure is 7/8” out of level over 2’, measured at the end floorbeam. DocuSign Envelope ID: 789F2B50-BAC8-4E04-9C84-608730988F11 Prepared by: Page 5 of 17 Bridge No. Mulberry Pedestrian Truss Inspected by: M. Orlowsky Town: Fort Collins Inspection Date 6-26-2020 Fort Collins W.O. #14 Photo #9 : Southwest corner of the bridge: Timber block is not located below the sole plate. Photo #10 : Southeast corner of the bridge: Timber block is not located below the sole plate. DocuSign Envelope ID: 789F2B50-BAC8-4E04-9C84-608730988F11 Prepared by: Page 10 of 17 Bridge No. Mulberry Pedestrian Truss Inspected by: M. Orlowsky Town: Fort Collins Inspection Date 6-26-2020 Fort Collins W.O. #14 Photo #19 : Floorbeam 24, top surface, looking west: Laminated rust along the floorbeam to flange and deck end plate. Photo #20 : Typical stay-in-place forms, looking north from node 10. Note the removed sections. DocuSign Envelope ID: 789F2B50-BAC8-4E04-9C84-608730988F11 Prepared by: Page 11 of 17 Bridge No. Mulberry Pedestrian Truss Inspected by: M. Orlowsky Town: Fort Collins Inspection Date 6-26-2020 Fort Collins W.O. #14 Photo #21 : Stay in place form at L8 at the west truss. Note the welded form connections to the top of the floorbeam. Photo #22 : Same location as previous photo. Close-up of the welded stay-in-place form connections. DocuSign Envelope ID: 789F2B50-BAC8-4E04-9C84-608730988F11 Prepared by: Page 12 of 17 Bridge No. Mulberry Pedestrian Truss Inspected by: M. Orlowsky Town: Fort Collins Inspection Date 6-26-2020 Fort Collins W.O. #14 Photo #23 : Typical stay-in-place form splice. Note the round welded stay-in-place form connections at the form seam. Photo #24 : Deck channel at L8 at the east truss: Laminated rust along the deck channel, typical. DocuSign Envelope ID: 789F2B50-BAC8-4E04-9C84-608730988F11 DocuSign Envelope ID: 789F2B50-BAC8-4E04-9C84-608730988F11 Span 1 towards Mulberry and Lemay, East Span Nomenclature: Example note to write on steel: S1,US, L0, IB - Span 1, Upstream Truss, Lower Chord #, Inboard Face (inboard always to deck) U0 U1 U2 U3 U4 U5 U6 U7 U8 U9 U10 U11 U12 U13 U14 U15 U16 U17 U18 U19 U20 U21 U22 U23 U24 L0 L1 L2 L3 L4 L5 L6 L7 L8 L9 L10 L11 L12 L13 L14 L15 L16 L17 L18 L19 L20 L21 L22 L23 L24 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Abut 1 Pier 2 DS Truss US Truss US / DS Truss DocuSign Envelope ID: 789F2B50-BAC8-4E04-9C84-608730988F11