PROJECT TITLE: Hoffman Mill Fuel Site
PROJECT NUMBER: PR-600182
CONTRACTOR: CGRS, Inc.
CHANGE ORDER NUMBER: 5
In preparing change orders show in order as separate numbered paragraphs the following:
1. Reason for change 2. Description of change
3. Change in contract cost 4. Change in contract time.
1&2 See attached sheet for detail.
3 The contract cost will be effected, see the attached sheet for change order cost details.
ORIGINAL CONTRACT COST $615,307.00
TOTAL APPROVED CHANGE ORDERS $31,619.69
TOTAL PENDING CHANGE ORDERS $0.00
TOTAL THIS CHANGE ORDER $2,829.38
TOTAL % OF THIS CHANGE ORDER 0.46%
TOTAL C.O. % OF ORIGINAL CONTRACT 5.60%
ADJUSTED CONTRACT COST $649,756.07
(Assuming all change orders approved)
ACCEPTED BY: ______________________________________________________ DATE: ______________
(Contractor's Representative)
REVIEWED BY: ______________________________________________________ DATE: ______________
(City of Ft. Collins)
APPROVED BY: ______________________________________________________ DATE: ______________
(Purchasing Agent over $60,000)
cc: Contractor
Purchasing
Project File
4 There will be a change in contract time, see the attached sheet for details.
08/27/2020
Blake Visser - Sr. Facilities Project Manager 08/28/2020
1. Reason for change
2. Description of change
COR #19 was approved by City PM. Values and dates are to be incorporated into the contract.
3. Change in contract cost
COR #19: $2,829.38
TOTAL this CO: $2,829.38
4. Change in contract time.
Final contract remains per CO #04 as 8/31/2020.
Hoffman Mill Fuel Site - CGRS Change Order #5
COR #19: This is to fix the damage to the West side of the site due to unknown stormwatter drainage