Loading...
HomeMy WebLinkAboutCORRESPONDENCE - RFP - 8697 VENDOR SELECTION AND IMPLEMENTATION FOR A UTILITES-BROADBAND BILLING SYSTEM (4)PROJECT CHANGE REQUEST Date (yyyy-mm-dd):2020-04-30 PCR. No. 23 No. SAO: Priority (High-Medium-Low): High Project Change Request Form Page 1 of 2 Description of requirement/issue: As a result of a set of multiple factors, the Utilities Go-Live milestone date was required to move from September 2019 to October 2020. This led to the first amendment to the Master Professional services which formalize the impacts on the project in terms of time and cost agreed between the City of Fort Collins and Open. Description of the actions to follow: As a result to formalize the new Project schedule that result from this amendment. Description of the deliverables to generate: New project scheduled that defines the new dates for the pending project activities and major milestones. Estimated impact of implementing requirement: The impacts in cost and time, were agreed on the amendment 1 of the MPSA. The project schedule moves 13 months. Requested by: Fort Collins Date of request: 2020-April-17 Responsibility/Position: NA Costs assumed by: NA Contract amendment required. (If yes, attach the amended contract) YES X NO Estimations Estimated impact on the time frame Estimated impact on resources Estimated impact on costs Notes Amendment No. 1 13 months As stated on the amendment As stated on the amendment TIME FRAME Current Time Frame: 20200228 Oasis project plan New Time Frame: 20200327 Oasis project plan extended CASH FLOW Current Cashflow: N/A New Cashflow: N/A EXECUTION OF THE SOLUTION APPROVAL By Open: By Client: Name: Diego López Position: Project Manager Date: Signature: Name: Andrew Amato Position: Project Manager Date: 08/11/2020 Signature: Approved X Rejected Approved X Rejected Proposed date for solution delivery: 2020 April 30 Attached files: 20200327 Oasis project plan extended.mpp Diego F. Lopez Aug-11-20 DocuSign Envelope ID: 06C9F715-1A86-43AF-91D3-D5CE5E812FBD Lisa Rosintoski 8/16/2020 Gerry Paul 8/17/2020 PROJECT CHANGE REQUEST Date (yyyy-mm-dd):2020-04-30 PCR. No. 23 No. SAO: Priority (High-Medium-Low): High roject Change Request Form Page 1 of 2 DocuSign Envelope ID: 06C9F715-1A86-43AF-91D3-D5CE5E812FBD