Loading...
HomeMy WebLinkAboutCORRESPONDENCE - PURCHASE ORDER - 9201123FACILITIES REQUISITION FORM VENDOR DATE REQ BY: Work Order # CHARGE# TOTAL COST: - BUYER: OTY DESCRIPTION COST ADDITIONAL INFO COMPUTER INPUT INFORMATION: VENDOR# REQUISITION # DATE ENTERED: Billable? Y/N City of Fort Collins - Light and Power Utility 07-16-2020 Matthew Schaefer, Proj. Mgr. PR-600367 Y 701200.564010 $7,855.65 Elliot Dale, Senior Buyer 1 Lincoln Center: Exterior Lighting East Parking Lot: Replace existing luminaires Northwest Parking Lot / Loading Dock: Replace existing luminaires $7,855.65 WORK REQUEST L & P Representative: Date: . Description and location of work to be performed: Comments: The individual signing below (or the company represented by the individual) agrees to pay the cost of the construction described on this work request, based on actual labor, equipment, materials, contractual, and overhead costs incurred by the utility. Any estimates given are based on the best information available at the time of the request. Actual costs may vary from the estimate due to unspecified field conditions encountered during construction. Bill To: Company Name: Attention: Mail Address: City & Zip: Telephone: Authorized signature Print name Telephone Title Customer purchase order No. (if available) Terms: Payment in full due 30 days from invoice date. Dm:wkreq-T&M.doc revised January 27, 2014 Light and Power Utility 700 Wood St. - P.O. Box 580 Ft. Collins, CO 80522-0580 (970) 221-6700 (970) 221-6619 (fax) WO/NW #_________________ Workorder Number: Quote-Lincol Center Workorder Title Lincoln Center Lighting Estimate Summary 05/19/2020 Material Added (WO) $ 3,066.47 Total Material + 15% Warehouse $ 3,526.44 Total Material Returned (WO) $ Total Direct Charge Materials $ Labor Costs $ 846.13 Total Labor + 38.56% Benefits $ 1,172.40 Total Equipment Costs (WO) $ Total Labor,External,WhseMaterial & Equip $ 4,698.84 Total + 15% Contingency $ 5,403.66 Total Cost + 15% ES & GA $ 6,214.21 Labor Cost/$28.44 (WO)Hrs 29.75 Workorder Number: Quote-Lincol Center Workorder Title Lincoln Center Lighting Estimate Summary 05/19/2020 Material Added (WO) $ 569.53 Total Material + 15% Warehouse $ 654.96 Total Material Returned (WO) $ Total Direct Charge Materials $ Labor Costs $ 423.06 Total Labor + 38.56% Benefits $ 586.20 Total Equipment Costs (WO) $ Total Labor,External,WhseMaterial & Equip $ 1,241.16 Total + 15% Contingency $ 1,427.34 Total Cost + 15% ES & GA $ 1,641.44 Labor Cost/$28.44 (WO)Hrs 14.88 Workorder Number: Quote-Lincol Center Workorder Title Lincoln Center Lighting Estimate Summary 05/19/2020 Material Added (WO) $ 3,636.00 Total Material + 15% Warehouse $ 4,181.40 Total Material Returned (WO) $ Total Direct Charge Materials $ Labor Costs $ 1,269.19 Total Labor + 38.56% Benefits $ 1,758.60 Total Equipment Costs (WO) $ Total Labor,External,WhseMaterial & Equip $ 5,940.00 Total + 15% Contingency $ 6,831.00 Total Cost + 15% ES & GA $ 7,855.65 Labor Cost/$28.44 (WO)Hrs 44.63 Work Order Number Quote-Lincol C Title Lincoln Center Lighting ProjectDescription Quote for Improving Lighting in Area Prepared By J Spaulding Date 04/10/2018 Combined Bill Of Material List ItemID Category Description Quantity Cost 2018 Labor 4-Man Crew W/O Benefits 6 HR $1,031.22 67717705 Warehouse GROUND; 5/8" X 8' COPPER 6 EA $60.10 70127835 Warehouse LED, 88W, TYPE 2, 120-277VAC MULTIVOLT 2 EA $549.50 70127838 Warehouse LED, 65W, TYPE 3, POST TOP MOUNTED, 120-277VAC MULTIVOLT 4 EA $3,026.40 Tuesday, May 19, 2020 Page 1 of 1