Loading...
HomeMy WebLinkAboutCORRESPONDENCE - BID - 8983 BURN BUILDING SITE WORK FOR POUDRE FIRE AUTHORITYSECTION 00950 CHANGE ORDER NO. PROJECT TITLE: 8983 Burn Building Site Work for Poudre Fire Authority CONTRACTOR: Brinkman Construction, Inc. DESCRIPTION: 1. Reason for change: 2. Description of Change: 3. Change in Contract Cost: 4. Change in Contract Time: ORIGINAL CONTRACT COST $ .00 TOTAL APPROVED CHANGE ORDER .00 TOTAL PENDING CHANGE ORDER .00 TOTAL THIS CHANGE ORDER .00 TOTAL % OF THIS CHANGE ORDER % TOTAL C.O.% OF ORIGNINAL CONTRACT % ADJUSTED CONTRACT COST $ .00 (Assuming all change orders approved) ACCEPTED BY: DATE: Contractor's Representative ACCEPTED BY: DATE: Project Manager REVIEWED BY: DATE: Title: APPROVED BY: DATE: Title: APPROVED BY: DATE: Purchasing Agent over $60,000 cc: City Clerk Contractor Engineer Project File Architect Purchasing DocuSign Envelope ID: 044A52BE-FD42-4996-82D1-1B56235FA8D5 248,791 8.8 6.4 233,925 14,866 65,652 168,273 002 T Broekemeier 5/21/2020 OCO #2 - Design Change The contract time will not be changed. $14,866.00 Balance of additional work included in post-bid design change. Design change - increase in scope of work. DocuSign Envelope ID: 113A9946-83EB-4E77-BECD-E8339DE9E634 May 28, 2020 June 8, 2020 Sr. Buyer CHANGE REQUEST DESCRIPTION COST BREAKDOWN SCOPE DESCRIPTION UNIT COST HR $ - HR $ - HR $ - LS $ 3,300.00 LS $ 4,303.81 LS $ 4,531.10 LS $ 1,751.17 $ - $ - $ - $ 13,886.08 $ - $ 138.86 $ 841.50 $ (0.44) $ 14,866.00 SCHEDULE IMPACT CHANGE REQUEST STATUS Architect/Owner Brinkman Construction, Inc. Signature: Signature: Date: Date: 1.00% This duration will extend the overall schedule by: The Owner agrees to pay for all changes in the Work performed by the Contractor under this Change Item according to the terms of the Agreement. The amount paid by the Owner shall be full compensation for all Work requested and for all effects of this document on the Work. The Owner understands that this Change Item, along with other approved Change Items, will be complied into a Change Order at a later date. ROUNDING CORRECTION CHANGE ITEM TOTAL This duration will have no impact on the overall schedule: X This duration will accelerate the overall schedule by: CONTACTOR OH&P 6.00% SUBTOTAL COSTS CITY & COUNTY TAX 0.00% INSURANCE 17-01-250 Larimer County Permit fees in excess of bid due to increased SOW $ 1,751.17 1 02-30-100 Dunrite Excavation Removal & disposal of 9 trees in area of work $ 4,303.81 1 05-55-250 Distinctive Welding Structrural slab hot-dip galvanized embed plates $ 4,531.10 1 01-01-100 BCI Project Superintendent $ 85.00 0 02-30-100 Dunrite Excavation Structrural Slab 3/4" fill - 2500 sf $ 3,300.00 1 01-01-010 BCI Project Manager $ 85.00 0 01-01-040 BCI Project Engineer $ 65.00 0 Fort Collins, CO 80521 CHANGE ITEM #: OCO #2 This change order represents the balance of work not captured in OCO#1 and is associated wth the increased scope from bid to construction drawings. The changes include 3/4" angular under slab fill, removal and haul-off of 5 medium and 4 large trees in area of new work, (11) Type A and (5) Type B structural slab 3/4" hot-dip galvanized embed plates, and balance of permit fees from bid value to permit issuance due to increased scope of work. COST CODE SUBCONTRACTOR COST QUANTITY PROJECT ADDRESS: 3400 W Vine Dr OWNER CHANGE ITEM PROJECT NAME: PFA Burn Bldg Site Work PROJECT #: 19-0034 DocuSign Envelope ID: 113A9946-83EB-4E77-BECD-E8339DE9E634