WORK ORDER FORM
PURSUANT TO A MASTER AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
DITESCO
WORK ORDER NUMBER: 2-400904600-19
PROJECT TITLE: Linden Street Renovations – Final
Engineering Design
ORIGINAL BID/RFP NUMBER & NAME: 8843 – Engineering Design Support
Services – Linden Street Renovations
MASTER AGREEMENT EFFECTIVE DATE: Original Contract Date
WORK ORDER COMMENCEMENT DATE: 4/18/20
WORK ORDER COMPLETION DATE: 12/1/21
MAXIMUM FEE: (time and reimbursable direct costs): $72,098
PROJECT DESCRIPTION/SCOPE OF SERVICES: Please see attached Scope of Services
Service Provider agrees to perform the services identified above and on the attached forms in
accordance with the terms and conditions contained herein and in the Master Agreement between
the parties. In the event of a conflict between or ambiguity in the terms of the Master Agreement
and this Work Order (including the attached forms) the Master Agreement shall control.
The attached forms consisting of (3) page(s) are hereby accepted and incorporated herein, by
this reference, and Notice to Proceed is hereby given after all parties have signed this document.
SERVICE PROVIDER: Date:
Keith Meyer, PE, President
ACCEPTANCE: Date:
Nicole Hahn, PE, Project Manager
REVIEWED: Date:
Elliot Dale, Senior Buyer
ACCEPTANCE: Date:
Gerry Paul, Purchasing Director
(if greater than $60,000)
DocuSign Envelope ID: 248192EF-7E6E-416C-A169-DDFF29B35633
4/28/2020
5/26/2020
5/26/2020
5/26/2020
Page 1 of 2
2133 S. Timberline Road, Suite 110
Fort Collins, CO 80525
ditescoservices.com
EXHIBIT A
Delivery by email to:
klambrecht@fcgov.com
April 22, 2020
Kyle Lambrecht, PE
Civil Engineer III
City of Fort Collins
281 North College Avenue
Fort Collins, CO 80521
RE: Linden Street Renovations
Engineering Design Proposal and Scope of Work
Dear Kyle:
This letter scope of services follows on our previous conversations regarding extending our base design contract
from preliminary design to 90% construction documents associated with the Linden Street Renovation project. This
effort was requested by the City to further the design effort allowing the CM/GC contractor the ability to price near-
final construction documents and finalize a guaranteed maximum price proposal. Our team will perform the
following tasks:
We will take all construction documents to a 90% completion level according to our base contract terms
and conditions. This work will include all civil engineering and urban design efforts in plan and specification
production.
We will participate in GMP negotiations with the CM/GC contractor and provide an independent cost
evaluation of their pricing proposal.
Our detailed task and fee breakdown is attached. We expect the work to commence immediately with
design plans completed by May 2020.
Thank you again for this opportunity. We look forward to our continued partnership on this project.
Please let me know if you have any questions or require further information regarding this proposal, I can be
reached by phone at 970.988.8605 and email keith.meyer@ditescoservices.com.
Sincerely,
Keith Meyer, P.E.
Enc. scope of services
Cc: Jill Burrell
file
DocuSign Envelope ID: 248192EF-7E6E-416C-A169-DDFF29B35633
City of Fort Collins Engineering
Linden Street Renovations - Final Design 4/22/2020
Keith Meyer Jill Burrell
Kelsey
Petersen
Rhonda
Bunner
Cassidy Hill
Nathan
Johnson
Principal / PM
PM / Task
Leader
Assoc. PM CAD Design Admin
Project
Manager
(hrs) (hrs) (hrs) (hrs) (hrs) (hrs)
$130 $115 $115 $80 $65 $125
Project Management $9,712
PM 1.1 - Contract Management (Budget Management) 3 6 0 0 0 0 $1,080
CM 1.4 - Document Management 0 4 6 0 0 0 $1,150
PM 1.2 - Meetings/Correspondence (Misc. Meetings) 26 13 19 0 6 0 $7,482
Final Design (to 90% from 60%) $17,700
Updated Site Plan 2 4 8 10 0 0 $2,440
Civil Design
Utility Design 4 2 4 6 0 0 $1,690
Storm/Trench Drain 2 0 4 4 0 0 $1,040
Grading Plans 4 2 4 10 0 0 $2,010
Drainage (proposed) / Drainage Memo 6 8 16 0 0 0 $3,540
Roadway Plan and Profile 2 0 4 6 0 0 $1,200
Details 2 2 4 8 0 0 $1,590
Specifications 4 4 8 0 0 0 $1,900
Internal QA/QC 4 2 0 0 0 0 $750
Review Meeting with City Staff 3 3 3 0 0 0 $1,080
City Review (Bluebeam Studio) 0 2 2 0 0 0 $460
CM/GC GMP Review $12,005
GMP Review Meeting 6 0 4 0 0 6 $1,990
Independent Cost Estimate 2 6 0 0 0 55 $7,825
GMP Update (Fall 2020) 8 4 6 0 0 0 $2,190
Russell Mills - Urban Design $32,090
Other direct costs (mileage, reproduction, etc) $591
Work Effort Subtotal 78 62 92 44 6 $71,507
ODCs $591
Cost per labor category $10,114.00 $7,118.50 $10,620.25 $3,520.00 $419.25
Effort (days) 10 8 12 6 1
Effort (weeks) 2 2 2 1 0
Hours per day 0.3 0.2 0.3 0.2 0.0
$72,098
Assumptions:
- 3 month project duration (60-90%)
Phase/Task Description Task Total
Ditesco
Page 2 of 2
DocuSign Envelope ID: 248192EF-7E6E-416C-A169-DDFF29B35633
506 S College Ave, Unit A, Fort Collins, CO 80524 | 970.484.8855 | russellmillsstudios.com
CREATING INSPIRED PLACES TOGETHER
April 19, 2020
Keith Meyer, P.E.
Ditesco
2133 S. Timberline Road, Suite 110
Fort Collins, CO 80525
Re: Linden Street Renovation Additional Services/Change Order Proposal
Dear Keith,
The following additional services and change order request addresses additional services/
scope of work to our existing contract to provide construction documents through 90%
(currently contracted through 60%) and construction administration support services for the
Linden Street Renovation project. The following scope is additional to the current contract
scope and includes subcontracted services with Aqua Engineering (Irrigation) and Mazzetti
(Lighting/Electrical).
Scope & Services
A. Final Design/Construction Documents
1. 90% CD’s
Based on the Preliminary Design Plans, Final Design Documents will be developed in collaboration
with the design team. Approval of the Preliminary Design Plan will constitute approval to begin Final
Design. The following information will be included:
• Site Amenities Layout Plans
• Detail Callout, Furnishings, Materials Plans
• Planting Plans, Tree Protection Plans and Details
• Irrigation Plans and Details
• Lighting Locations and Photometrics
• Electrical Plans and Details
• Site Details and Enlargements w/Structural Review
• Cost Estimate Quantities
• Construction Specifications
• Revisions as required
Meetings:
• Review Meetings w/City Staff (3)
• Review Meetings w/Stakeholders (2)
• Coordination Meetings w/Ditesco (5)
B. Construction AdmInistration
Construction Administration will be conducted during site and landscape construction. Prior to and
during construction, we will provide Construction Administration services for both landscape and
irrigation work in order to ensure that projects are built on time and on budget as related to our
Construction Documents. This will include, but is not limited to the following:
A. Attend Pre-Construction meeting/conference.
B. RFI Responses and ASI/’s.
C. Submittal and Shop Drawing Review
D. Progress Meetings and Site Visits
E. Five irrigation on-site meetings/inspections.
F. Form inspections, site work layout and quality, lighting, planting staking/layout, irrigation
inspections, approval.
G. Punchlists and project close-out.
not included
DocuSign Envelope ID: 248192EF-7E6E-416C-A169-DDFF29B35633
506 S College Ave, Unit A, Fort Collins, CO 80524 | 970.484.8855 | russellmillsstudios.com
CREATING INSPIRED PLACES TOGETHER
I. Digital record drawings for landscape/irrigation based on contractor provided red-lines.
J. 6 month and 11 month walk thru and punchlists.
Change Order Summary Fees (Including Aqua Engineering/Mazetti Lighting/Electrical)
Total Current Contract Amount $ 84,540
Final Design/Construction Documents $ 32,090
Construction Administration $ 21,250
Total Revised Contract Amount $ 137,880
Agreement
Russell + Mills Studios can initiate the proposed services upon written Authorization to
Proceed. Adding your signature in the space provided below and returning a copy for our file
will provide authorization of this proposal and form the basis of our contractual agreement.
Should you have any questions or comments following your review of this proposal we will be
pleased to address them at your earliest convenience.
Sincerely,
Craig Russell, RLA, ASLA
Principal
Authorization to Proceed
Date:
_____________________________________________________________
Signed
Name:
Title:
Date: