HomeMy WebLinkAboutCORRESPONDENCE - RFP - 9078 MOUNTAIN AVENUE RESHAPING PROJECTWORK ORDER FORM
PURSUANT TO A MASTER AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
TOOLE DESIGN GROUP, LLC
WORK ORDER NUMBER: 1
PROJECT TITLE: Workplan and Existing and Future
Conditions Assessment
ORIGINAL BID/RFP NUMBER & NAME: 9078 Mountain Avenue Reshaping Project
MASTER AGREEMENT EFFECTIVE DATE: May 1, 2020
WORK ORDER COMMENCEMENT DATE: May 1, 2020
WORK ORDER COMPLETION DATE: June 30, 2020
MAXIMUM FEE: (time and reimbursable direct costs): $18,306
PROJECT DESCRIPTION/SCOPE OF SERVICES: See attached scope and fee to complete
Task 1 through Task 2.3.
Professional agrees to perform the services identified above and on the attached forms in
accordance with the terms and conditions contained herein and in the Master Agreement between
the parties. In the event of a conflict between or ambiguity in the terms of the Master Agreement
and this Work Order (including the attached forms) the Master Agreement shall control.
The attached forms consisting of two (2) pages are hereby accepted and incorporated herein, by
this reference, and Notice to Proceed is hereby given after all parties have signed this document.
PROFESSIONAL: Date:
Ken Ray, Project Manager
ACCEPTANCE: Date:
Seth Lorson, Project Manager
REVIEWED: Date:
Elliot Dale, Senior Buyer
ACCEPTANCE: Date:
Gerry Paul, Purchasing Director
(if greater than $60,000)
Work Order 1 - 9078 Mountain Avenue Reshaping Project Page 1 of 3
DocuSign Envelope ID: 9B0D24E4-2DE5-45FD-8C9B-65410CFFFEE8
5/19/2020
5/19/2020
5/19/2020
EXHIBIT A
SCOPE OF SERVICES
A. Scope of Work
This scope of work describes the services to be provided by Toole Design as part of the
Mountain Avenue Reshaping project. The following scope is based on a work plan (dated
4/8/20) developed by City staff with input from Toole Design, and it includes only a portion
of the scope of work described in the Request for Proposals (dated 1/24/20) and the
scope of work described in Toole Design’s proposal (dated 2/17/20) and interview
presentation (dated 3/3/20).
Task 1: Work Plan and Project Management
Toole Design will work with City staff to prepare a work plan to guide the study effort,
especially in light of COVID-19 and associated social distancing requirements and
economic impacts.
Toole Design will facilitate a project kickoff meeting with the project steering committee to
present the project scope, desired outcomes, and opportunities for input and feedback.
Task 2: Existing and Future Conditions
Toole Design will work with City staff to gather and organize qualitative and quantitative
data including traffic volumes (all modes), crash history, parking utilization, emergency
service operations, utility locations, and ridehailing operator patterns.
Toole Design will create a plan-view, aerial graphic that highlights existing geometric and
operational conditions. Toole Design will produce illustrative cross-sections for each
block.
Toole Design will summarize existing, local plans and studies including the Downtown
Plan, the Bicycle Master Plan, the Jefferson Street Alternative Analysis, the Parking Plan,
the Transportation Master Plan, and the Pedestrian Priority Plan.
Toole Design will gather examples and guidance for public realm design, curbside
management, balancing multimodal mobility and motor vehicle parking capacity, and
utility integration.
Toole Design will conduct a preliminary strengths, weaknesses, opportunities, and threats
(SWOT) analysis on the Mountain Avenue corridor based on data gathered, the City’s
existing goals, and national best practices.
Work Order 1 - 9078 Mountain Avenue Reshaping Project Page 2 of 3
DocuSign Envelope ID: 9B0D24E4-2DE5-45FD-8C9B-65410CFFFEE8
Toole Design Group Walker Consultants
Principal‐in‐
Charge
Senior
Landscape
Architect
Project
Manager
Engineering
Lead I
Project
Engineer
Planner
II
Designer
II
Lead
Planner Planner Task Hourly
Subtotals
Task Labor
Subtotals
$260.00 $146.00 $136.00 $194.00 $147.00 $115.00 $92.00 $210.00 $170.00
1: Work Plan and Project Management
Work and Public Involvement Plan 2 2 4 8 $1,356
Project Kickoff Meeting 4 6
10 $1,400
Check‐in Meetings 4 4
8 $1,128
Progress Reports 1 2
3 $532
Subtotal Hours 3 10 16 0 0 0 0 0 0 29
Subtotal Effort $780 $1,460 $2,176 $0 $0 $0 $0 $0 $0 $4,416
2. Existing and Future Conditions
2.1 Existing Operational Conditions
Summarize/Analyze Conditions 4
4
6 28 42 $7,256
2.2 Existing Physical Conditions
Plan View and Aerial Graphics 2 2
4
12 20 $2,256
Cross Sections by Block 4
12
16 $1,692
2.3 Future Needs and Goals
Land Use, Public Space, and
Transportation Trends 2 2 2 2 2 8 18 $2,686
Subtotal Hours 2 4 4 6 10 12 24 6 28 96
Subtotal Effort $520 $584 $544 $1,164 $1,470 $1,380 $2,208 $1,260 $4,760 $13,890
Total Hours 5 14 20 6 10 12 24 6 28 125
Total Effort $1,300 $2,044 $2,720 $1,164 $1,470 $1,380 $2,208 $1,260 $4,760 $18,306