WORK ORDER
PURSUANT TO A MASTER AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
MARINE DIVING SOLUTIONS, LLC.
WORK ORDER NUMBER: 1
PROJECT TITLE: Joe Wright Reservoir
ORIGINAL BID/RFP NUMBER & NAME: 9085 Dive Team Services
MASTER AGREEMENT EFFECTIVE DATE: April 22, 2020
ARCHITECT/ENGINEER: HDR Engineering
OWNER’S REPRESENTATIVE: Mark Kempton
WORK ORDER COMMENCEMENT DATE: May 18, 2020
WORK ORDER COMPLETION DATE: September 30, 2020
MAXIMUM FEE: (time and reimbursable direct costs): $39,500.00
PROJECT DESCRIPTION/SCOPE OF SERVICES: See Exhibit A, Work Order Scope of
Services.
Service Provider agrees to perform the services identified above and on the attached forms in
accordance with the terms and conditions contained herein and in the Master Agreement between
the parties. In the event of a conflict between or ambiguity in the terms of the Master Agreement
and this Work Order (including the attached forms) the Master Agreement shall control.
The attached forms consisting of three (3) pages are hereby accepted and incorporated herein,
by this reference, and Notice to Proceed is hereby given after all parties have signed this
document.
SERVICE PROVIDER: Marine Diving Solutions, LLC
By: Date:
Name: Title:
DocuSign Envelope ID: 16EA7374-E166-4140-8495-81B52215B066
5/15/2020
Ian Stephens Owner
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
OWNER’S ACCEPTANCE & EXECUTION:
This Work Order and the attached Contract Documents are hereby accepted and incorporated
herein by this reference.
ACCEPTANCE: Date:
Mark Kempton, Project Manager
REVIEWED: Date:
Marisa Donegon, Buyer
DocuSign Envelope ID: 16EA7374-E166-4140-8495-81B52215B066
5/12/2020
5/12/2020
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
ATTACHMENT A
WORK ORDER SCOPE OF SERVICES
Objective
The City of Fort Collins (City) requested proposals from qualified Vendors to assess the inlet
structure of Joe Wright Reservoir, using divers or a Remote Operated Vehicle (ROV).
Scope of Work
Service Provider will mobilize to Joe Wright Reservoir located at Cameron Pass
in Larimer County, Colorado and provide the following services:
• Set up mobile dive station on or near the gate operating tower to include
commercial dive team, project manager, ROV, working platform/pontoon boat,
hyperbaric chamber, commercial dive equipment and other miscellaneous
materials needed for Scope of Work. There will be no subcontractors needed.
• Working with the City’s Evaluation Team members, conduct an
assessment inspection of the outlet pipe through the gate tower grated opening.
Service Provider will conduct an ROV inspection of the inlet pipeline measuring
approximately 370’ long and 6’ diameter. The inspection will be recorded with high
definition video and documented accordingly.
• Service Provider plans beginning the inspection in the control operating tower and
finishing the inspection at the inlet structure approximately 300’ from the dam face. Upon
completion of the pipeline, Service Provider will complete a formal assessment of the
condition of the pipeline by its NASSCO PACP inspector and civil engineer. A formal
report will be furnished to the city that will include still color photos.
• Upon completion of the inlet pipeline inspection and inlet structure inspection, Service
Provider will complete an inspection of the Slide Gates and the stems and stem guides
in the tower. The inspection will also be completed with the ROV and a formal
assessment will be completed by one of Service Provider’s civil engineers. A formal
report will be furnished to the City that will include still color photos.
• After the tower and pipeline inspection, Service Provider will assess the intake structure
and trash rack by certified commercial divers. Service Provider will use the grid
coordinates furnished by the City and use its 27’ dive vessel to position divers and
equipment over the intake structure. A decent line will be sent to the bottom to what is
expected to be the proximity of the intake structure. A diver will then be sent down the
down line and will determine if the structure is at that given location. If the location is off
slightly, a diver will then hook up a line to the down line and begin searching patterns to
find the structure. The diver will begin circles in 5’ increments. Every time the diver
makes a circle to the same location, they will proceed 5’ further out and begin a circle in
the opposite direction until the intake structure is found.
• Due to the depths of the water and elevation, Service Provider will plan on having divers
not exceed 30 minutes of working time underwater. Service Provider is confident that the
DocuSign Envelope ID: 16EA7374-E166-4140-8495-81B52215B066
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
dive team will be able to locate and assess the condition of the intake structure and trash
rack in 1 to 2 days (allowing for possible weather delays).
• Upon approval from the City of the assessment of the inlet structure and pipeline, all
work areas will be left in the same or better condition upon completion of this Scope of
Work.
Deliverables:
Service Provider shall provide the City with an electronic file containing video and still photos of
the inlet structure, as well as a formal report of the conditions observed in the dam conduit as
described in the Scope of Work above.
Schedule:
Service Provider will plan to mobilize and perform the services described in this Scope of Work
in early August 2020, at the direction of the City’s Project Manager. The services described are
anticipated to take 5 business days.
All deliverables shall be provided to the City no later than September 30, 2020.
DocuSign Envelope ID: 16EA7374-E166-4140-8495-81B52215B066
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
ATTACHMENT B
WORK ORDER COST DETAIL
All work will be completed by a 4-man minimum dive crew for the Joe Wright Reservoir, as
directed by the City’s Project Manager.
The City’s payment terms are Net 30.
Task Rate Per Hour
Rate Over
8 Hours
Estimated
Number
of Days
Total Rate
Mobilization/Demobilization for
Hyperbaric Chamber, ROV and
Vessel
$10,000.00 N/A N/A $10,000.00
4 Man Commercial Dive Team $687.50 (8 Hour
Daily Rate
Minimum)
$750.00* 5 $27,500.00
Written Report with Photos and
Results of Inspections
$2,000.00 N/A N/A $2,000.00
Total $39,500.00
*Overtime is not anticipated to be required and will be approved in advance by the City
Representative, if applicable.
DocuSign Envelope ID: 16EA7374-E166-4140-8495-81B52215B066
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017