CORRESPONDENCE - PURCHASE ORDER - 9200749
Willow St Plaza (~6,200 SF) Ref # Contract Item No. Contract Item Unit Estimated Quantities Unit Price Total Cost 1 201 Clearing and Grubbing LS 1 $ 2,722.00 $ 2,722.00 2 202 Removals LS 3 202 Removal of Concrete Bollard EA 0 $ 100.00 4 202 Remove Type III Barricade EA 0 $ 200.00 $ - 5 202 Removal of Sidewalk SY 140 $ 74.97 $ 10,496.00 6 202 Removal of Gutter LF 0 $ 8.00 $ - 7 202 Removal of Curb and Gutter LF 0 $ 10.00 $ - 8 202 Removal of Timber Curb LF 0 $ 5.00 $ - 9 202 Removal of Concrete Pavement SY 0 $ 25.00 $ - 10 202 Removal of Asphalt Mat (Assumed 6 Inch) SY 0 $ 8.00 $ - 11 202 Removal of Asphalt Mat (Planing) (2 Inch) SY 0 $ 4.00 $ - 12 202 Removal of Recycled Asphalt Material SY 0 $ 3.00 $ - 13 202 Removal of Pipe & Area Inlet LF 0 $ 40.00 $ - 14 202 Removal of Light Standard Foundation EA 0 $ 500.00 $ - 15 202 Removal of Ground Sign - BY OWNER EA 0 $ 750.00 $ - 16 202 Removal of Wall LF 0 $ 90.00 $ - 17 202 Remove Ex Tree Grate - BY OWNER EA 0 $ 25.00 $ - 18 202 Removal of Rock Parking Block EA 0 $ 400.00 $ - 19 202 Removal of Fence LF 40 $ 10.35 $ 414.00 20 202 Removal of Bench, Bike Rack, Planter Pots and/or Trash Can - BY OWNER EA 0 $ 150.00 $ - 21 202 Remove Drip Irrigation and Landscape Bed (Willow Street Lofts/Condos Frontage) EA 0 $ 1,500.00 $ - 22 202 Removal of Landscape Bed, Irrigation, Valve Box, Landscape Rock and Metal Edging EA (Schrader Frontage) 0 $ 1,500.00 $ - 23 202 Remove and Replace Fence at Xcel Site EA $ - 24 202 Removal of Tree EA 0 $ 750.00 $ - 25 203 Raise Grade at Xcel Site, using millings and base CY $ - 26 203 Unclassified Excavation, backfill and grading CY 230 $ 95.19 $ 21,892.55 27 203 Unsuitable Material (CIP) CY 0 $ 50.00 $ - 28 203 Potholing HR 0 $ 55.00 $ - 29 207 Pre-amendment Topsoil - BY OWNER CY 0 $ 100.00 $ - 30 208 Erosion Control LS 1 $ 3,354.00 $ 3,354.00 31 208 Concrete Washout Structure EA 1 $ 817.00 $ 817.00 32 208 Vehicle Tracking Pad EA 0 $ 2,350.00 $ - 33 208 Aggregate Bag with Warning Marker LF 0 $ 10.00 $ - 34 208 Erosion Log (Type 1)(12 Inch) LF 0 $ 8.00 $ - 35 208 Storm Drain Inlet Protection EA 0 $ 80.00 $ - 36 208 Erosion Control Management DAY 0 $ 250.00 $ - 37 210 Decommission Monitoring Well In Place EA 0 $ 450.00 $ - 38 210 Adjust Rim of Ex Monitoring Well and Resurvey for Monitoring EA 0 $ 1,200.00 $ - 39 210 Adjust Manhole EA $ 1,000.00 $ - 40 210 Adjust Valve Box EA 0 $ 500.00 $ - 41 210 Adjust Water Meter Pit EA 1 $ 600.00 $ 600.00 42 210 Adjust Cleanout and Install in Valve Box EA 0 $ 50.00 $ - 43 210 Adjust Curb Stop EA 0 $ 75.00 $ - 44 210 Modify Irrigation System and Remove Sod as Required (Aztlan Frontage) LS 0 $ 2,000.00 $ - 45 210 Relocate Water Meter Pit EA 1 $ - $ - 46 210 Relocate Trees, Shrubs and Planter Box (Debar Frontage) LS 0 $ 2,500.00 $ - 47 210 Relocate Fire Hydrant EA 0 $ 5,000.00 $ - 48 210 Reset Bike Rack - BY OWNER EA 0 $ - 49 210 Reset Portions of Existing Fence (Willow St. Lofts) LF 0 $ - 50 210 Reset Mailbox (Type 1) EA 0 $ 350.00 $ - Willow St Plaza (~6,200 SF) Ref # Contract Item No. Contract Item Unit Estimated Quantities Unit Price Total Cost FINAL For Construction Cost Estimate Willow St Improvements, Willow & Pine Development, and Willow St Plaza Fort Collins, CO June 21, 2019 Independent Bid Price 91 604 84" Dia. Storm Manhole EA 0 $ 5,000.00 $ - 92 604 Concrete pumping LS 1 $ 6,579.00 $ 6,579.00 93 604 Site sealants LS 1 $ 1,688.00 $ 1,688.00 94 607 Fence (Plastic) FOR TREE PROTECTION LF 20 $ 31.60 $ 632.00 95 608 Sidewalk Ramp SY 22 $ 220.70 $ 4,855.40 96 608 Concrete Sidewalk (6 Inch) SY 113 $ 79.51 $ 8,984.63 97 608 Concrete Sidewalk (5" SUB SLAB FOR PAVERS) SY 391 $ 56.66 $ 22,154.00 98 608 Type 1 Interlocking Concrete Pavers (60 mm Thick) (concrete sub-slab) SF 2320 $ 16.60 $ 38,515.00 99 608 Type 1 Interlocking Concrete Pavers (60 mm Thick) (3% over run) SF 0 $ 25.00 $ - 100 608 Type 2 Interlocking Concrete Pavers (60 mm Thick) (concrete sub-slab) SF 990 $ - $ - 101 608 Type 2 Interlocking Concrete Pavers (60 mm Thick) (3% over run) SF 0 $ 25.00 $ - 102 608 Type 3 Interlocking Concrete Pavers (60 mm Thick) (concrete sub-slab) SF 175 $ - $ - 103 608 Type 3 Interlocking Concrete Pavers (60 mm Thick) (3% over run) SF 0 $ 25.00 $ - 104 608 Salvaged, Interlocking Concrete Pavers (Timeline) SF 24 $ - $ - 105 608 Mill Race SF 0 $ 25.00 $ - 106 608 Decorative Concrete Bands LF 0 $ 79.39 $ - 107 608 Buff Sandstone Paver - Salvaged/Existing EA 0 $ 25.00 $ - 108 608 Street Name Text - Sealing of salvaged street names EA 2 $ 272.50 $ 545.00 109 609 Graffiti Control at seatwalls LS 1 $ 2,178.00 $ 2,178.00 110 609 4" Mountable Curb & Gutter LF 0 $ 50.00 $ - 111 609 6" Mountable Curb & Gutter LF 0 $ 35.00 $ - 112 609 6" Vertical Curb & Gutter (2" Catch) LF 0 $ 40.00 $ - 113 609 6" Outfall Curb & Gutter (2" Spill) LF 0 $ 15.00 $ - 114 609 18" Wide Curb & Gutter (2" Catch) LF 0 $ - 115 613 2-Inch Electrical Conduit (Future Pedestrian Signal) LF 0 $ 20.00 $ - 116 613 3-Inch Electrical Conduit (Future Pedestrian Signal) LF 0 $ 25.00 $ - 117 613 Light Standard and Luminaire (Pedestrian) EA 0 $ 5,000.00 $ - 118 613 String Light Cabling LF 318 $ - $ - 119 613 Type C catenary luminaire EA 78 $ 915.19 $ 71,385.00 120 613 Type D in-grade lighting system LS 1 $ 355,719.00 $ 355,719.00 121 613 Lighting Control Center EA 1 $ 50,705.00 $ 50,705.00 122 613 3-inch Electrical Conduit (plastic) LF 0 $ - $ - 123 613 2-inch Electrical Conduit (plastic) LF 0 $ 12.00 $ - 124 613 1-inch Electrical Conduit (plastic) LF 400 $ - $ - 125 613 3/4-inch Electrical Conduit (plastic) LS 200 $ - $ - 126 613 Wiring LS 0.1 $ - $ - 127 613 Pull box tier 22 (11" x 18" x 12") EA 3 $ - $ - 128 613 Pull Box (17" x 30") (Future Pedestrian Signal) EA 0 $ 750.00 $ - 129 613 Electrical System Modifications LS 1 $ - $ - 130 613 2-Plex Receptacles EA 4 $ 857.25 $ 3,429.00 131 622 Recycle Container - BY OWNER EA 0 $ 2,200.00 $ - 132 622 Trash Container - BY OWNER EA 0 $ 2,200.00 $ - 133 622 Bicycle Rack EA 0 $ 1,500.00 $ - 134 622 Type 1 Planter Pot (includes incidentals) - BY OWNER EA 0 $ 1,500.00 $ - Willow St Plaza (~6,200 SF) Ref # Contract Item No. Contract Item Unit Estimated Quantities Unit Price Total Cost FINAL For Construction Cost Estimate Willow St Improvements, Willow & Pine Development, and Willow St Plaza Fort Collins, CO June 21, 2019 Independent Bid Price 1 202 Remove 6" Gate Valve EA 2 202 Removal of Ex Waterline Pipe LF 3 619 3/4" Water Service Connection (CIP) EA 4 619 1" Water Service Connection (CIP) EA 5 619 2" Water Service Connection (CIP) EA 6 619 6" Fire Service Connection (CIP) EA 7 619 8 Inch Water Main w/ Flowfill (CIP) LF 8 619 8 Inch Gate Valve EA 9 619 3/4" Copper Water Pipe (CIP) LF Please Note: Water main quantities do not include the Willow & Pine Development proposed stub connections. $ 820,717.06 WATER MAIN BY CONNELL 135 622 Type 2 Planter Pot (includes incidentals) EA 0 $ 1,500.00 $ - 136 622 Bench EA 0 $ 3,000.00 $ - 137 622 Ornamental Bollard EA 0 $ 1,100.00 $ - 138 622 Pedestrian Light Poles and Concrete Caisson EA 0 $ 9,500.00 $ - 139 622 I-Beam String Light Post - Seat Wall Mount with Concrete Caisson EA 0 $ 5,000.00 $ - 140 622 I-Beam String Light Post - Ground Mount with Concrete Caisson EA 0 $ 5,000.00 $ - 141 622 String Light Building Wall Bracket EA 3 $ 136.35 $ 409.05 142 622 Ornamental Fence Panels EA 0 $ 3,000.00 $ - 143 622 Relocation of the Existing Interpretative Signage EA 0 $ 1,500.00 $ - 144 622 Type 1 Trench Grate at Sidewalk Chase and Frame LF 0 $ 2,500.00 $ - 145 622 Type 2 Trench Grate at Sidewalk Chase and Frame LF 34 $ 456.04 $ 15,505.36 146 622 Type 1 Tree Grate with Frame EA 0 $ 200.00 $ - 147 622 Type 2 Tree Grate with Frame and Trim Ring EA 2 $ 3,473.00 $ 6,946.00 148 622 Drinking Fountain EA 1 $ 14,140.00 $ 14,140.00 149 622 Site Furnishings - Lounge Chair - BY OWNER EA 0 $ 2,200.00 $ - 150 622 Skateboard Deterrents EA 47 $ 99.77 $ 4,689.19 151 623 Irrigation System LS 1 $ 5,445.00 $ 5,445.00 152 619 Mainline Pipe LF 0 $ 4.00 $ - 153 619 Sleeving LF 0 $ 8.00 $ - 154 619 Lateral Pipe LF 0 $ 4.00 $ - 155 619 Drip Lateral Pipe LF 0 $ 1.00 $ - 156 623 Winterization Assembly EA 0 $ 750.00 $ - 157 623 Backflow Prevention Assembly EA 0 $ 1,250.00 $ - 158 623 Master Valve Assembly EA 0 $ 500.00 $ - 159 623 Flow Sensor Assembly EA 0 $ 400.00 $ - 160 623 Isolation Gate Valve Assembly EA 0 $ 500.00 $ - 161 623 Blow Out Assembly EA 0 $ 100.00 $ - 162 623 Quick Coupling Valve Assembly EA 0 $ 1.00 $ - 163 623 Flush Cap Assembly EA 0 $ 25.00 $ - 164 623 Drip Remote Control Valve Assembly EA 0 $ 400.00 $ - 165 623 Planter Pot Irrigation EA 0 $ 100.00 $ - 166 623 Trees In Grate Irrigation EA 0 $ 200.00 $ - 167 623 Two Wire Cable LF 0 $ 1.50 $ - 168 623 Two Wire Cable Grounding EA 0 $ 750.00 $ - 169 625 Construction Surveying LS 1 $ 6,861.00 $ 6,861.00 170 626 Mobilization LS $ - $ - 171 630 Construction Zone Traffic Control LS $ 7,500.00 $ - 172 630 Temporary Fence LS 1 $ 686.00 $ 686.00 173 630 Traffic Control Management LS 1 $ 8,168.00 $ 8,168.00 174 630 Traffic Control Inspection DAY $ - $ - 175 630 General Conditions WK 8 $ 4,721.63 $ 37,773.00 176 700 General Requirements LS 1 $ 25,234.00 $ 25,234.00 51 210 Reset Newsstand Box - BY OWNER EA 0 $ 100.00 $ - 52 210 Reset Landscape Boulder EA $ 150.00 $ - 53 210 Reset Ex Light Standard BY OWNER EA 0 $ 500.00 $ - 54 210 Reset Bench - BY OWNER EA 0 $ 100.00 $ - 55 210 Reset Planter Pot - BY OWNER EA 0 $ - $ - 56 210 Reset Timeline Paver - WITH PAVER COST EA 0 $ 50.00 $ - 57 212 Sodding SF 0 $ 0.80 $ - 58 213 Landscape Weed Barrier Fabric - BY OWNER SY 0 $ 2.50 $ - 59 213 Mulching (Wood Chip)(Special) - BY OWNER CF 0 $ 2.50 $ - 60 213 4” to 8” Inorganic River Cobble - BY OWNER TON 0 $ 150.00 $ - 61 213 Inorganic Mulch (Special) Pea-Gravel - BY OWNER TON 0 $ 40.00 $ - 62 213 Stabilized Crusher Fines TON 0 $ 100.00 $ - 63 213 Landscape Boulders EA 0 $ 300.00 $ - 64 213 Landscape Boulders – Type ‘B’ EA 0 $ 350.00 $ - 65 214 Deciduous Trees (3" Caliper) - BY OWNER EA 0 $ 550.00 $ - 66 214 Ornamental Trees (2" Caliper) EA 0 $ 450.00 $ - 67 214 Deciduous Shrubs (5 Gallon) - BY OWNER EA 0 $ 40.00 $ - 68 214 Perennials (1 Gallon) - BY OWNER EA 0 $ 12.00 $ - 69 214 Ornamental Grasses (1 Gallon) - BY OWNER EA 0 $ 12.00 $ - 70 214 Landscape Maintenance (24 months, includes planting and maintaining planter pots 2 seasons) LS 0 $ 20,000.00 $ - 71 304 Aggregate Base Course (Class 6) (Includes under C&G) (unit wt 105 lb/in-sy) TON 0 $ 30.00 $ - 72 403 Temporary Paving (4 Inch) TON 0 $ 100.00 $ - 73 403 HMA (Patching) (7.5 Inch) TON 0 $ 120.00 $ - 74 403 HMA (Grading S)(75)(PG 64-22)(7.5 Inches) (unit wt 115 lb/in-sy) TON 0 $ 120.00 $ - 75 403 Concrete mobilization LS 1 $ 5,815.00 $ 5,815.00 76 412 Concrete foundation for lighting control center and interpretive sign LS 1 $ 1,212.00 $ 1,212.00 77 412 Concrete Mock ups LS 1 $ 2,493.00 $ 2,493.00 78 412 Concrete Sculpture foundations EA 4 $ 1,721.47 $ 6,885.88 79 601 Raised Concrete Board Form Finish Seat Walls LF 297 $ 238.35 $ 70,790.00 80 603 4 inch PVC Pipe (Complete In Place) LF 0 $ 15.00 $ - 81 603 18 Inch Reinforced Concrete Pipe (Complete In Place) LF 0 $ 100.00 $ - 82 603 23 Inch x 14 Inch Reinforced Concrete Pipe Elliptical (Complete In Place) LF 0 $ 140.00 $ - 83 603 30 Inch Reinforced Concrete Pipe (Complete In Place) LF 0 $ 200.00 $ - 84 603 36 Inch Reinforced Concrete Pipe (Complete In Place) LF 0 $ 250.00 $ - 85 603 29 Inch x 45 Inch Reinforced Concrete Pipe Elliptical (Complete In Place) LF 0 $ 250.00 $ - 86 603 36 Inch to 29 Inch x 45 Inch Transition EA 0 $ 3,200.00 $ - 87 604 Area Inlet & Cleanout EA 0 $ 500.00 $ - 88 604 Type 'R' Inlet EA 0 $ 4,500.00 $ - 89 604 Single Type '13' Combo Inlet EA 0 $ 4,000.00 $ - 90 604 72" Dia. Storm Manhole EA 0 $ 8,500.00 $ - FINAL For Construction Cost Estimate Willow St Improvements, Willow & Pine Development, and Willow St Plaza Fort Collins, CO June 21, 2019 Independent Bid Price