CHANGE ORDER
NO. 02
PROJECT TITLE: West Vine Basin Floodplain Update – Phase II
CONTRACTOR: ICON Engineering, Inc.
WORK ORDER NUMBER: BLA-2019-04
PO NUMBER: 9191204
DESCRIPTION:
1. Reason for Change: Cost, Scope and Time
2. Description of Change: Supplemental 2D hydraulic models used to inform 1D floodplain
model for Poudre School District, Sanctuary, and Granada Heights. Coordination with
external stakeholders (PSD and Sanctuary) and modifications to 1D hydraulic model relating
to the Southern Flow Path PHS Split Flow Reach. See attached scope and fee.
3. Change in Work Order Price: $35,900.00
4. Completion Date (if changed): May 29, 2020
ORIGINAL WORK ORDER PRICE $ 73,560.00
TOTAL APPROVED CHANGE ORDER 0.00
TOTAL PENDING CHANGE ORDER 0.00
TOTAL THIS CHANGE ORDER $ 35,900.00
TOTAL % OF THIS CHANGE ORDER 48.8%
TOTAL C.O.% OF ORIGINAL WORK ORDER 48.8%
ADJUSTED WORK ORDER COST $ 109,460.00
CONTRACTOR: ICON Engineering, Inc.
By: Date:
Name: Craig Jacobson Title: Principal
ACCEPTANCE: Date:
Beck L. Anderson, Project Manager
REQUISITION ENTERED BY: Date:
REVIEWED: Date:
Marisa Donegon, Buyer II
Change Order Form (for Work Orders)
Official Purchasing Form
Last updated 10/2017
ACCEPTANCE: Date:
Ken Sampley, Director, Civil Engineering
ACCEPTANCE: Date:
Theresa Connor, Deputy Director, Water Engineering & Field Services