CHANGE ORDER
REQUEST (PROPOSAL)
Project: Water Treatment Facility Re-roof
4316 Laporte Ave. Fort Collins Colorado
To: Matt Shaefer - City of Fort Collins
Re: Vapor Barrier
Change Order Request Number: 1
From (Contractor): AAA Roofing & Construction
Date: 2/17/2020
A/E Project Number:
Contract For: Roof Replacement
This Change Order Request (C.O.R.) contains an itemized quotation for changes in the Contract Sum or Contract Time in response to
proposed modifications to the Contract Documents based on Proposal Request No. .
Description of Proposed Change:
Vapor Barrier is a Requirment to be installed. Insurance scope of work does not include Vapor barrier in scope of work.
RFI #1 Response confirms that Vapor Barrier is in fact required
Change order is for Labor and Material
Attached supporting information from: Subcontractor Supplier
Reason For Change:
Vapor Barrier was not included in Insurance loss scope of work, nor was it included in AAA Roofing & Constructions Roof Proposal
Does Proposed Change involve a change in Contract Sum? No Yes [Increase] [Decrease] $ 39,509.22.00
Does Proposed Change involve a change in Contract Time? No Yes [Increase] [Decrease] days.
Attached pages: Proposal Worksheet Summary:
Proposal Worksheet Detail(s):
Signed by: Joshua Morales Date: 2/17/2020
Copies: Owner Consultants File
Copyright 1994, Construction Specifications Institute,
99 Canal Center Plaza, Suite 300 Alexandria, VA 22314
Page of July 1994
CSI Form 13.6A
Roof Replacement Proposal
4316 West Laporte Ave. Fort Collins Colorado
The following change order is for work not included in the original scope. Change requested is needed for roof to be
installed per code and warranty requirements.
SCOPE OF WORK:
• Install Vapor Barrier with Primer to concrete deck (all decks)
o Vapor Barrier $270.00/5sq. 84 rolls $22,680.00
o Primer $140.00/5sq. 83 bucket $11,620.00
o Labor $25/sq. 416 sq $10,400.00
o Mark up 25% $11,175.00
• Vapor Barrier for South Filter Bay ($16,365.78)
The above referenced job will be completed for $39,509.22_ This price includes all material, labor, equipment, dump
fees and Taxes to perform said job. Any additional work that is not stated in the contract will require a change order and an additional
charge to the contract.
Please call with any questions 970-682-0010
First Owner Signature First Owner Printed Name Date
Joshua Morales 03/10/2020
AAA Roofing & Construction
REMIT TO:
ABC SUPPLY CO
PO BOX 842450
DALLAS TX 75284- 2450
(608)368-2562
INVOICE
REGULAR
IMPORTANT: SELLER MAKES NO WARRANTIES: SEE REVERSE SIDE OR
ELECTRONIC ATTACHMENT FOR IMPORTANT TERMS AND CONDITIONS. IF THERE
IS NO REVERSE SIDE OR ELECTRONIC ATTACHMENT, SELLER WILL FURNISH THE
TERMS AND CONDITIONS UPON REQUEST. This order is subject to the terms and
conditions set forth on the reverse side or electronic attachment, and by accepting the below
materials, you agree to those terms and conditions.
Seller represents that with respect to the production of the articles and/or the performance
of the services covered by this invoice, it has fully complied with section 12(A) of the Fair
Labor Standards Act of 1938, as amended.
T/D symbols are described on the reverse side or electronic attachment.
Returns must be made in accordance with ABC's Return Policy. A copy of this policy is
available upon request.
LATE PAYMENT CHARGE: All accounts past due will be subject to a monthly late payment
charge, not to exceed the maximum allowable by state or federal law.
When you provide a check as payment, you authorize us either to use the information from
your check to make a one-time electronic fund transfer from your account or to process the
payment as a check transaction. For inquiries, please call the number provided.
SOLD TO:
AAA ROOFING & CONST LLC
JOB/WATER TREATMENT PLANT
201 EAST 4TH STREET
LOVELAND CO 80537 0000
SHIP TO:
WATER TREATMENT PLANT
4316 LAPORTE AVE
FORT COLLINS CO 80521- 0000
INVOICE DATE
02/11/20
SHIP DATE
02/10/20
PAGE
1 of 1
INVOICE NO.
89970333
CUSTOMER ORDER NO.
4316 LAPORTE
SHIP VIA
OTG
MAIN ACCOUNT NO.
644810
CUSTOMER NO.
743854
TERMS
1%2ND10TH N EOM
SALES REP
TB017902
ITEM NUMBER
16GAOG5115
16GAOG5215
11GASVR134
11GAVRSAP5
99FUELCHRG
ITEM DESCRIPTION
CHANGE ORDER
REQUEST (PROPOSAL)
Project: Water Treatment Facility Re-roof
4316 Laporte Ave. Fort Collins Colorado
To: Matt Shaefer - City of Fort Collins
Re: Parapet Build Out North Filter Bay
Change Order Request Number: 2
From (Contractor): AAA Roofing & Construction
Date: 2/20/2020
A/E Project Number:
Contract For: Roof Replacement
This Change Order Request (C.O.R.) contains an itemized quotation for changes in the Contract Sum or Contract Time in response to
proposed modifications to the Contract Documents based on Proposal Request No. .
Description of Proposed Change:
Add knee wall at parapet (86 lf)
Add preasure treated 2x8 bolted to Concrete stem wall virtically
Add 1/2" plywood screwed to preasure treated lumber to match wall thickness of 2 inched
Add 2 layers of 3/4 inch plywood on inside wall to build out to 3.5 inches
Add preasure treated 2x4 wood nailer top plate
Wrap with high temp Ice and Water Shield (Grace I&W)
Add 2x8 preasure treated wood nailer to existing expansion joint walls for new roof height (130 lf)
Attached supporting information from: Subcontractor Supplier
Reason For Change:
No nailer exists at parapet.
Current wall is 2" bare concrete twin T concrete wall with stems sticking up an extra 8 inches
Current wall is 7.5" tall
New wall needs to be at least 15" tall
New roof height will be approximately 13" above concrete deck
This wall is not included in original scope of work
Additianally 130 lf of 2x8 only (2 sides of wall) will be added to expansion joints to account for new roof height
Does Proposed Change involve a change in Contract Sum? No Yes [Increase] [Decrease] $ 7,143.81
Does Proposed Change involve a change in Contract Time? No Yes [Increase] [Decrease] days.
Attached pages: Proposal Worksheet Summary:
Proposal Worksheet Detail(s):
Signed by: Joshua Morales Date: 2/20/2020
Copies: Owner Consultants File
Copyright 1994, Construction Specifications Institute,
99 Canal Center Plaza, Suite 300 Alexandria, VA 22314
Page of July 1994
CSI Form 13.6A
Change Order #2
Worksheet
4316 West Laporte Ave. Fort Collins Colorado
The following change order is for work not included in the original scope. Change requested is needed for roof to be
installed per code and warranty requirements.
SCOPE OF WORK:
2x10 treated 22 $26.98 $593.56
High temp H&W 2 $175.99 $351.98
Plywood 1/2 7 $13.49 $94.43
nails 1 $34.24 $34.24
tapcons 1 $26.48 $26.48
Plywood 3/4" 8 $33.57 $268.56
L angle $30.69
Nuts $20.70
washers $18.00
Bolts $28.97
wood screws $29.97
2x10 for inner
wall 30 $26.98 $809.40
2X4 top plate 9 $5.77 $51.93
Fuel $6.13
Design 6 $100.00 $600.00
LABOR 50 $55.00 $2,750.00
SUBTOTAL $5,715.04
Mark up 25% $1,428.76
GROSS $7,143.80
Please call with any questions 970-682-0010
Joshua Morales 03/04/2020
AAA Roofing & Construction
GAF OLYBOND 500 PART 1 15GL 417H015
WINTER GRADE
GAF OLYBOND 500 PART 2 15GL 417I015
WINTER GRADE
GAF SA VAPOR RETARDER 45X135'
GAF VAPOR RETARDER SA PRIMER 5GAL
SPECIAL ORDER / NO RETURNS
FUEL SURCHARGE
U/M T/D
DR
EA
RL
DR
EA
QUANTITY
SHIPPED
23
23
0
0
1
QUANTITY
BACKORD
0
0
84
83
0
UNIT
PRICE
550.00
550.00
270.00
140.00
65.00
EXTENDED
PRICE
12,650.00
12,650.00
0.00
0.00
65.00
ABC #482 DENVER OUR TRUCK GROUND
*** ITEMS ON THIS ORDER HAVE BEEN BACKORDERED. ***
*** THE ITEMS WILL SHIP WHEN AVAILABLE UNLESS CANCELLED BY YOU. ***
*** CALL TO CANCEL ANY BACKORDERED ITEMS. ***
SUBTOTAL 25,365.00
NOTE THE SAVINGS: YOU MAY DEDUCT 253.65
IF THIS INVOICE IS PAID BY 04/10/20
+ + TOTAL
PAYABLE IN
U.S. DOLLARS
SUBTOTAL AMOUNT FREIGHT SALES TAX
CO FF 36
25,365.00 0.00 1,915.06 27,280.06