HomeMy WebLinkAboutCORRESPONDENCE - PURCHASE ORDER - 9191407Change Order Form (for Work Orders)
Official Purchasing Form
Last updated 10/2017
CHANGE ORDER
NO. 2
PROJECT TITLE: Hickory Street RR Bore - Construction
SERVICE PROVIDER: BT Construction, Inc.
WORK ORDER NUMBER: Hick-BTC-4
PO NUMBER: 9191407
DESCRIPTION:
1. Reason for Change: Cost.
2. Description of Change: The Work Order Price will reduce from $ 353,540.98 to $219,334.67
3. Change in Work Order Price: $ 134,206.31
4. Change in Work Order Time: N/A
ORIGINAL WORK ORDER PRICE $ 353,540.98
TOTAL APPROVED CHANGE ORDER 0.00
TOTAL PENDING CHANGE ORDER 0.00
TOTAL THIS CHANGE ORDER $134,206.31
TOTAL % OF THIS CHANGE ORDER 37.96%
TOTAL C.O.% OF ORIGINAL WORK ORDER 37.96%
ADJUSTED WORK ORDER COST $ 219,334.67
SERVICE PROVIDER: Date:
John Beckos, BT Construction, Inc. Project Manager
ACCEPTANCE: Date:
Heather McDowell, Project Manager
REVIEWED: Date:
Pat Johnson, Senior Buyer
ACCEPTANCE: Date:
Matt Fater, Director, Civil Engineering
DocuSign Envelope ID: 4C0DD98A-9D9F-405C-905E-29E1D32B5AF0
May 12, 2020
May 12, 2020
May 13, 2020
May 14, 2020
Change Order Form (for Work Orders)
Official Purchasing Form
Last updated 10/2017
ACCEPTANCE: Date:
Andrew Gingerich, Interim Deputy Director, Water Engineering & Field Services
ACCEPTANCE: Date:
Gerry Paul, Purchasing Director
(if greater than $60,000)
DocuSign Envelope ID: 4C0DD98A-9D9F-405C-905E-29E1D32B5AF0
May 14, 2020
BTC Invoice # 64040-R
PROJECT: Hickory St. RR Bore
OWNER: Water Utilities, City of Fort Collins CONTRACTOR: BT Construction, Inc. APPLICATION NUMBER: Five (5)
700 Wood St 9885 Emporia Street APPLICATION DATE: 03/17/20
Fort Collins, CO 80521 Henderson, CO 80640 PERIOD BEGINNING:
PERIOD ENDING:
ENGINEER: Merrick and Company
2725 Rocky Mountain Ave, Suite 410 PO NUMBER: 9191407
Loveland, CO 80538 COFC WORK ORDER #: HICK-BTC-4
CHANGE ORDERS: PAY APPLICATION: RETAINAGE:
SCOPE OF WORK CHANGE ORDERS: Application is made for Payment as shown below in connection with the Contract.
The present status of the account for this Contract is as follows.
NUMBER DATE AMOUNT
Original Contract Amount: $353,540.98 Retainage to Date: $10,966.73
Net Change by Change Order: $0.00 Retainage Previous: $115.47
Revised Current Contract Amount: $353,540.98
Change in Retainage: $ 10,851.26
Total Work Completed to Date: $219,334.67
Total Change Order Work to Date: $0.00
Total Stored to Date: $0.00
Total Completed and Stored Materials to Date: $219,334.67
RECONCILLIATION CHANGE ORDER:
Less Previous Payment (before Retainage): $219,334.67
NUMBER DATE AMOUNT
Amount due this Pay Application (Retainage): $10,966.73
Less Retainage (this month): $0.00
Net Change by Change Order: $0.00
Change Order %: 0.00%
CERTIFICATION:
The undersigned CONTRACTOR certifies that all obligations of CONTRACTOR incurred in connection with
the WORK have been satisfied as required in paragraph 14.3 of the General Conditions of the Contract.
The above Amount Due this Application is requested by the CONTRACTOR's Project Manager.
Date: By:
Erin Evans, Project Engineer I
Payment of the above Amount Due This Application has been reviewed by the OWNER'S Project Manager.
Date: By:
Heather McDowell, P.E. Special Projects Manager
Payment of the above Amount Due This Application is approved by the OWNER.
Date: By:
Matt Fater, Chief Engineer
AMOUNT DUE THIS APPLICATION: $10,966.73
3/17/2020
DocuSign Envelope ID: 4C0DD98A-9D9F-405C-905E-29E1D32B5AF0
APPLICATION AND CERTIFICATE FOR PAYMENT PO# 9191407
INVOICE# 64040-R
TO: City of Fort Collins PO# 9191407 PAY APPLICATION #4
Accounting Department HICKORY STREET RAILROAD
PO Box 580 BORE FROM:
Fort Collins, CO 80522 MAIN CONSTRUCTION TO: 3/17/2020
CONTRACT
FROM: BT CONSTRUCTION INC.
9885 Emporia St. BTC PROJECT NO: 64040
Henderson, CO 80640 CONTRACT DATE: July 8, 2019
(303) 469-0199 CONTRACT FOR: City of Fort Collins
CONTRACTOR'S APPLICATION FOR PAYMENT
ORIGINAL CONTRACT SUM ........................ $353,540.98
Net change by change orders ........................ $0.00
CHANGE ORDER ADDITIONS $0.00 CONTRACT SUM TO DATE ........................ $353,540.98
CHANGE ORDER DEDUCTIONS $0.00 TOTAL COMPLETED TO DATE ........................ $219,334.67
NET CHANGE ORDERS $0.00 RETAINAGE:
5% of Contract Sum $0.00
TOTAL RETAINAGE ........................ $0.00
TOTAL EARNED LESS RETAINAGE .............. $208,367.93
LESS PREVIOUS PAYMENTS..................... $208,367.93
CURRENT PAYMENT DUE ........................ $10,966.73
BALANCE TO FINISH PLUS RETAINAGE ...... $134,206.31
The undersigned Contractor certifies that 1) all information contained in this application is true and correct;
2) that all monies previously paid to the undersigned on behalf of third parties who have performed work/supplied
materials on this project has been paid to those parties and undersigned, upon request, will provide lien releases
from those third parties; and 3) undersigned waives and releases all right to claim any mechanic's lien for labor,
services, machinery, tools, equipment and materials furnished through the date of this application when paid, for
the construction of improvement on the project here-in billed / specified above.
COMPANY: BT Construction, Inc.
CONTRACTOR: ...........................................................DATE: .. ................................
State of: ............................................. County of: .........................
Subscribed and sworn to before me this ....................... day of ............................ , 20......
Notary Public: ...........................................................................................
My Commission expires: ............................................................................
ENGINEER'S CERTIFICATE FOR PAYMENT
In accordance with the Contract Documents, based on on-site observations and the data comprising the above
application, the Engineer certifies to the Owner that the work has progressed to the point indicated; that to the best
of his knowledge, information and belief, the quality of the work is in accordance with the contract documents; and
that the Contractor is entitled to the payment of the amount certified.
AMT CERTIFIED $...........................ENGINEER: ............ ................................................... DATE: .............................
3/17/2020
DocuSign Envelope ID: 4C0DD98A-9D9F-405C-905E-29E1D32B5AF0
BT CONSTRUCTION, INC.
9985 EMPORIA STREET Schedule of Values
HENDERSON CO 80640 FROM:
TO: 3/17/2020
A B C D E F G H I K L M
ITEM BID UNIT CONTRACT PREVIOUS PREVIOUS QTY THIS TOTAL TOTAL %
# DESCRIPTION QTY UNIT PRICE TOTAL COST QUANTITY COST ESTIMATE BTC COST MARGIN TOTAL BILLED QUANTITY COST COMP
(C*E) (G*E) AMOUNT (G + I) (H+J+L) (M/F)
GENERAL CONDITIONS FINAL BILLED $$ $$ LEFT TO SPEND UNDER (OVER) BUDG. NOTES
1
Mobilization/Demobilization -
Trucking, Crew, Safety Supplies
& Orientation, Toilet, Dumpster,
Sub Mobs
1.00 LS $16,353.36 $16,353.36 0.41 $6,776.47 0.00 $0.00 $0.00 $0.00 0.41 $6,776.47 41% $6,776.47 $0.00 $9,576.89
Less equipment to mobilize, and some came
from Windsor. Efficient on safety supplies.
2 General Conditions 1.00 LS $9,066.99 $9,066.99 0.52 $4,759.62 0.00 $0.00 $0.00 $0.00 0.52 $4,759.62 52% $4,759.62 $0.00 $4,307.37 We were efficient
3 Supervision 1.00 LS $37,309.40 $37,309.40 0.78 $29,258.82 0.00 $0.00 $0.00 $0.00 0.78 $29,258.82 78% $29,258.82 $0.00 $8,050.58 Shorter duration job than planned.
RAILROAD COSTS
4 Railroad Protective Insurance 1.00 LS $2,353.00 $2,353.00 0.50 $1,176.47 0.00 $0.00 $0.00 $0.00 0.50 $1,176.47 50% $1,176.47 $0.00 $1,176.53 Cost less
EROSION & SEDIMENT CONTROL
5 BMP's - Sub installation 1.00 LS $3,776.49 $3,776.49 0.00 $0.00 0.00 $0.00 $0.00 $0.00 0.00 $0.00 0% $0.00 $0.00 $3,776.49 BTC self performed
6
BMP'S - Crew BMP
Maintenance
6.00 Wk $191.42 $1,148.50 1.05 $1,211.42 0.00 $0.00 $0.00 $0.00 1.05 $1,211.42 105% $1,211.42 $0.00 ($62.92)
Self performed, overall erosion control was
under budget.
24" Auger Bore for 8" PVC WL Carrier
7 Bore Pit Excavation 2.00 DY $11,435.58 $22,871.16 1.71 $19,548.24 0.00 $0.00 $0.00 $0.00 1.71 $19,548.24 85% $19,548.24 $0.00 $3,322.92
8 Receive Pit Excavation 1.00 DY $7,623.72 $7,623.72 0.61 $4,647.53 0.00 $0.00 $0.00 $0.00 0.61 $4,647.53 61% $4,647.53 $0.00 $2,976.19
9 Tunnel Setup 1.00 LS $29,211.41 $29,211.41 0.36 $10,371.86 0.00 $0.00 $0.00 $0.00 0.36 $10,371.86 36% $10,371.86 $0.00 $18,839.55
10 Tunnel 126.00 LF $300.13 $37,816.11 100.08 $30,037.99 0.00 $0.00 $0.00 $0.00 100.08 $30,037.99 79% $30,037.99 $0.00 $7,778.12
11 Skid Pipe 126.00 LF $157.92 $19,897.98 9.71 $1,533.09 0.00 $0.00 $0.00 $0.00 9.71 $1,533.09 8% $1,533.09 $0.00 $18,364.89
12 Tunnel Teardown 1.00 LS $15,247.44 $15,247.44 0.10 $1,462.50 0.00 $0.00 $0.00 $0.00 0.10 $1,462.50 10% $1,462.50 $0.00 $13,784.94
13 Bore Pit Backfill 1.00 LS $15,247.44 $15,247.44 1.60 $24,327.19 0.00 $0.00 $0.00 $0.00 1.60 $24,327.19 160% $24,327.19 $0.00 ($9,079.75)
14 Receive Pit Backfill 1.00 LS $10,799.16 $10,799.16 0.88 $9,482.64 0.00 $0.00 $0.00 $0.00 0.88 $9,482.64 88% $9,482.64 $0.00 $1,316.52
15 Tunnel Grouting 126.00 LF $61.07 $7,694.73 92.22 $5,632.10 0.00 $0.00 $0.00 $0.00 92.22 $5,632.10 73% $5,632.10 $0.00 $2,062.63
Open-Cut Pipe & Connections
16
Install 8" C900, Wet Tap, Bends,
GV's, Cap & Temp. Blowoff,
Thrust Blocks, etc.
1.00 LS $46,637.88 $46,637.88 1.01 $47,175.28 0.00 $0.00 $0.00 $0.00 1.01 $47,175.28 101% $47,175.28 $0.00 ($537.40)
17
Hydrostatic Testing/Disinfection
1.00 LS $1,914.15 $1,914.15 1.02 $1,943.41 0.00 $0.00 $0.00 $0.00 1.02 $1,943.41 102% $1,943.41 $0.00 ($29.26)
Asphalt Removal & Replacement
18 Sawcutting/ Subgrade Prep 1.00 LS $2,491.52 $2,491.52 0.35 $870.64 0.00 $0.00 $0.00 $0.00 0.35 $870.64 35% $870.64 $0.00 $1,620.88
19 Asphalt Patch 135.00 SY $126.49 $17,076.65 0.00 $18,637.05 0.00 $0.00 $0.00 $0.00 0.00 $18,637.05 109% $18,637.05 $0.00 ($1,560.40)
MISCELLANEOUS CONSTRUCTION
20
Misc. Construction Dewatering
1.00 LS $13,120.64 $13,120.64 0.00 $482.35 0.00 $0.00 $0.00 $0.00 0.00 $482.35 4% $482.35 $0.00 $12,638.29
50% charged for application fee. Terminated
permit before renewal date, so no other fees
charged
GBM Contingency
21 GBM Contingency 1.00 LS $35,883.25 $35,883.25 0.00 $0.00 0.00 $0.00 $0.00 $0.00 0.00 $0.00 0% $0.00 $0.00 $35,883.25 Not used
TOTALS $353,540.98 $219,334.67 $0.00 $0.00 $0.00 $219,334.67 62% $219,334.67 $0.00 $134,206.31 Final cost.
Came in just under budget.
J
BILLED THIS ESTIMATE
HICKORY ST RR BORE
FINAL PROJECT PROJECTIONS
Overall under budget on the tunneling items by
$59k. Worked very effeciently and had little to
no issues.
Came in just over budget.