HomeMy WebLinkAboutCORRESPONDENCE - RFP - 8631 GENERAL ENVIRONMENTAL SERVICES (7)Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
WORK ORDER
PURSUANT TO A MASTER AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
CGRS
WORK ORDER NUMBER: 2020 -1.16
PROJECT TITLE: SPCC update for Portner &Timberline substations
ORIGINAL BID/RFP NUMBER & NAME: U8631- General Environmental Services-
CGRS
MASTER AGREEMENT EFFECTIVE DATE: 2/28/18
OWNER’S REPRESENTATIVE: Errin Henggeler
WORK ORDER COMMENCEMENT DATE: UJan 21, 2020
WORK ORDER COMPLETION DATE: UApril 1, 202U0
MAXIMUM FEE: (time and reimbursable direct costs): $2,876.00
PROJECT DESCRIPTION/SCOPE OF SERVICES:
. Prepare SPCC Plan update for the Timberline and Portner substations in accordance
with Code of Federal Regulations (CFR), Title 40, Part 112, prepare site-specific
figures, and have the plan reviewed and certified by a Colorado Professional Engineer
The attached USpill Prevention Control and Countermeasure Plan update Proposals for Portner
and Timberline substationsU consisting of six (6) pages are hereby accepted and incorporated
herein, by this reference, and Notice to Proceed is hereby given after all parties have signed this
document.
SERVICE PROVIDER: CGRS
By: Date:
Name: Title:
Brannan Davis CGRS, Senior Engineer
OWNER’S ACCEPTANCE & EXECUTION:
This Work Order and the attached Contract Documents are hereby accepted and incorporated
herein by this reference.
ACCEPTANCE: Date:
Bob Hover, Senior Manager
DocuSign Envelope ID: 772CC7F9-1ACB-4FCB-B46D-6CF8459A606F
1/30/2020
1/30/2020
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
REVIEWED: Date:
Errin Henggeler, Env Regulatory Specialist
REVIEWED: Date:
Pat Johnson, Senior Buyer, Utilities
DocuSign Envelope ID: 772CC7F9-1ACB-4FCB-B46D-6CF8459A606F
1/29/2020
1/29/2020
Updated Proposal for SPCC Plan Update
City of Fort Collins – Portner Substation
1
www.cgrs.com
800.288.2657
1301 Academy Ct.
Fort Collins, CO 80524
January 21, 2020
Ms. Errin Henggeler Via E-Mail: ehenggeler@fcgov.com
City of Fort Collins
PO Box 580
Fort Collins, Colorado 80522
Re: UPDATED Proposal for Spill Prevention, Control, and Countermeasure Plan Update
City of Fort Collins
Portner Substation
6561 Portner Road
Fort Collins, Colorado
CGRS Site No. 14811
Dear Ms. Henggeler:
CGRS, Inc. (CGRS) is pleased to provide this proposal to prepare a Spill Prevention, Control, and Countermeasure
(SPCC) plan update for the above-referenced facility. The proposal includes a facility inspection and certification of
an SPCC plan to comply with current U.S. Environmental Protection Agency (EPA) SPCC plan rule requirements.
CGRS will prepare an SPCC plan that conforms to applicable EPA requirements outlined in the Code of Federal
Regulations (CFR), Title 40, Part 112 for facilities with aggregate aboveground oil storage capacity greater than
1,320 gallons, which will be organized as follows:
SPCC Plan Outline
Plan Certification and Management Approval
The Environmental Director or other person responsible for implementing the SPCC plan at the facility will sign
the document verifying management approval. The SPCC plan will be approved, signed and stamped by a CGRS
certified professional engineer.
General Requirements
Prepare a site diagram detailing the facility layout, listing oil storage container descriptions, describing discharge
prevention, control, and countermeasure equipment and procedures, and procedures related to disposal and spill
response notification.
Inspections, Tests and Records
Prepare written procedures on performing regular inspections, guidelines on integrity testing and record keeping
requirements.
Personnel, Training and Prevention
Describe training requirements, designated person for spill prevention and regular review/briefings of personnel
on SPCC plan requirements and procedures.
DocuSign Envelope ID: 772CC7F9-1ACB-4FCB-B46D-6CF8459A606F
Updated Proposal for SPCC Plan Update
City of Fort Collins – Portner Substation
2
www.cgrs.com
800.288.2657
1301 Academy Ct.
Fort Collins, CO 80524
Security
This section of the plan describes required security measures implemented at the facility to secure and control
access to the tanks and transfer equipment, securing flow valves, drain valves, pump controls and sealing loading
and unloading connections when not in use, and lighting to detect nighttime spills.
Tank Loading/Unloading Area
Describe secondary containment required for tanker trucks in loading and unloading areas and measures taken
to prevent spills from occurring during transfer.
Facility Drainages
Describe measures taken to prevent uncontrolled drainage of precipitation from secondary containment/dike
areas, management of drain valves, control of drainage from undiked areas and final diversion systems (such as
retention basins), if applicable.
Bulk Storage Containers
This section of the plan provides details on all applicable oil storage containers 55-gallons and greater in size,
including compatibility of the containers with products stored, and construction design, secondary containment
capable of containing the contents of the largest tank plus precipitation, rainwater drainage procedures, corrosion
protection, visual plus additional integrity testing, overfill prevention, and corrective action procedures to promptly
correct and remove leaks.
Transfer Operations
This section includes corrosion protection for buried piping, assuring terminal pipe connections are properly
sealed, proper design of pipe supports, regular inspections of piping and associated equipment, and protection
of aboveground pipes and transfer equipment from vehicle impact.
Scope of Work
CGRS will complete the Scope of Work as follows:
• Prepare SPCC Plan update for the site in accordance with Code of Federal Regulations (CFR), Title 40,
Part 112, prepare site-specific figures, and have the plan reviewed and certified by a Colorado Professional
Engineer.
If additional work is required due to a change in scope of work or unanticipated site conditions, anticipated costs
will be presented to the client prior to implementation.
DocuSign Envelope ID: 772CC7F9-1ACB-4FCB-B46D-6CF8459A606F
Updated Proposal for SPCC Plan Update
City of Fort Collins – Portner Substation
3
www.cgrs.com
800.288.2657
1301 Academy Ct.
Fort Collins, CO 80524
Project Cost
The costs for CGRS to complete the scope of work is summarized in the following table:
Service Description Quantity Unit Unit
Rate Markup Cost Total
A. SPCC Plan Development
Staff Scientist 10 hour $83 $830
Drafting 2 hour $58 $116
TOTAL = $946
B. SPCC Plan Certification
Senior Engineer 4 hour $123 $492
TOTAL = $492
TOTAL = $1,438
Our costs are based in accordance with our current City of Fort Collins contract fee schedule. In addition to all
necessary labor equipment, materials, and permits to complete the foregoing work specifications, CGRS will provide
commercial general, professional, and pollution liability insurance coverage ($5,000,000 aggregate), standard
workers’ compensation, and employers’ liability insurance coverage.
CGRS appreciates the opportunity to provide our professional environmental services to the City of Fort Collins. If
you have any questions regarding this proposal, please contact me at (970) 493-7780 or ewilson@cgrs.com.
Sincerely,
CGRS, Inc.
Prepared by:
Brannan Davis,
Senior Engineer
DocuSign Envelope ID: 772CC7F9-1ACB-4FCB-B46D-6CF8459A606F
Updated Proposal for SPCC Plan Update
City of Fort Collins – Timberline Substation
1
www.cgrs.com
800.288.2657
1301 Academy Ct.
Fort Collins, CO 80524
January 21, 2020
Ms. Errin Henggeler Via E-Mail: ehenggeler@fcgov.com
City of Fort Collins
PO Box 580
Fort Collins, Colorado 80522
Re: UPDATED Proposal for Spill Prevention, Control, and Countermeasure Plan Update
City of Fort Collins
Timberline Substation
1809 South Timberline Road
Fort Collins, Colorado
CGRS Site No. 14812
Dear Ms. Henggeler:
CGRS, Inc. (CGRS) is pleased to provide this proposal to prepare a Spill Prevention, Control, and Countermeasure
(SPCC) plan update for the above-referenced facility. The proposal includes a facility inspection and certification of
an SPCC plan to comply with current U.S. Environmental Protection Agency (EPA) SPCC plan rule requirements.
CGRS will prepare an SPCC plan that conforms to applicable EPA requirements outlined in the Code of Federal
Regulations (CFR), Title 40, Part 112 for facilities with aggregate aboveground oil storage capacity greater than
1,320 gallons, which will be organized as follows:
SPCC Plan Outline
Plan Certification and Management Approval
The Environmental Director or other person responsible for implementing the SPCC plan at the facility will sign
the document verifying management approval. The SPCC plan will be approved, signed and stamped by a CGRS
certified professional engineer.
General Requirements
Prepare a site diagram detailing the facility layout, listing oil storage container descriptions, describing discharge
prevention, control, and countermeasure equipment and procedures, and procedures related to disposal and spill
response notification.
Inspections, Tests and Records
Prepare written procedures on performing regular inspections, guidelines on integrity testing and record keeping
requirements.
Personnel, Training and Prevention
Describe training requirements, designated person for spill prevention and regular review/briefings of personnel
on SPCC plan requirements and procedures.
DocuSign Envelope ID: 772CC7F9-1ACB-4FCB-B46D-6CF8459A606F
Updated Proposal for SPCC Plan Update
City of Fort Collins – Timberline Substation
2
www.cgrs.com
800.288.2657
1301 Academy Ct.
Fort Collins, CO 80524
Security
This section of the plan describes required security measures implemented at the facility to secure and control
access to the tanks and transfer equipment, securing flow valves, drain valves, pump controls and sealing loading
and unloading connections when not in use, and lighting to detect nighttime spills.
Tank Loading/Unloading Area
Describe secondary containment required for tanker trucks in loading and unloading areas and measures taken
to prevent spills from occurring during transfer.
Facility Drainages
Describe measures taken to prevent uncontrolled drainage of precipitation from secondary containment/dike
areas, management of drain valves, control of drainage from undiked areas and final diversion systems (such as
retention basins), if applicable.
Bulk Storage Containers
This section of the plan provides details on all applicable oil storage containers 55-gallons and greater in size,
including compatibility of the containers with products stored, and construction design, secondary containment
capable of containing the contents of the largest tank plus precipitation, rainwater drainage procedures, corrosion
protection, visual plus additional integrity testing, overfill prevention, and corrective action procedures to promptly
correct and remove leaks.
Transfer Operations
This section includes corrosion protection for buried piping, assuring terminal pipe connections are properly
sealed, proper design of pipe supports, regular inspections of piping and associated equipment, and protection
of aboveground pipes and transfer equipment from vehicle impact.
Scope of Work
CGRS will complete the Scope of Work as follows:
• Prepare SPCC Plan update for the site in accordance with Code of Federal Regulations (CFR), Title 40,
Part 112, prepare site-specific figures, and have the plan reviewed and certified by a Colorado Professional
Engineer.
If additional work is required due to a change in scope of work or unanticipated site conditions, anticipated costs
will be presented to the client prior to implementation.
DocuSign Envelope ID: 772CC7F9-1ACB-4FCB-B46D-6CF8459A606F
Updated Proposal for SPCC Plan Update
City of Fort Collins – Timberline Substation
3
www.cgrs.com
800.288.2657
1301 Academy Ct.
Fort Collins, CO 80524
Project Cost
The costs for CGRS to complete the scope of work is summarized in the following table:
Service Description Quantity Unit Unit
Rate Markup Cost Total
A. SPCC Plan Development
Staff Scientist 10 hour $83 $830
Drafting 2 hour $58 $116
TOTAL = $946
B. SPCC Plan Certification
Senior Engineer 4 hour $123 $492
TOTAL = $492
TOTAL = $1,438
Our costs are based in accordance with our current City of Fort Collins contract fee schedule. In addition to all
necessary labor equipment, materials, and permits to complete the foregoing work specifications, CGRS will provide
commercial general, professional, and pollution liability insurance coverage ($5,000,000 aggregate), standard
workers’ compensation, and employers’ liability insurance coverage.
CGRS appreciates the opportunity to provide our professional environmental services to the City of Fort Collins. If
you have any questions regarding this proposal, please contact me at (970) 493-7780 or ewilson@cgrs.com.
Sincerely,
CGRS, Inc.
Prepared by:
Brannan Davis, PE
Senior Engineer
DocuSign Envelope ID: 772CC7F9-1ACB-4FCB-B46D-6CF8459A606F