HomeMy WebLinkAboutCORRESPONDENCE - RFP - 8286 CONSTRUCTION CONTRACTOR FOR PROJECTS AT THE WATER & WASTEWATER TREATMENT FACILITIES (17)Change Order Form (for Work Orders)
Official Purchasing Form
Last updated 10/2017
CHANGE ORDER
NO. 1
PROJECT TITLE: DWRF Cogen Gas Conditioning Equipment Procurement
CONTRACTOR: Hydro Construction Inc.
WORK ORDER NUMBER: H-WRF-2018-32
PO NUMBER: 9185842
DESCRIPTION:
1. Reason for Change: Time
2. Description of Change: Delays in the commencement of the construction work order
resulted in delays in submittal approval requiring an extension of the procurement
completion date. Revision of the procurement final completion from November 29, 2019 to
December 31, 2020
3. Change in Work Order Price: NA
4. Completion Date (if changed): December 31, 2020
ORIGINAL WORK ORDER PRICE $ 986,407.00
TOTAL APPROVED CHANGE ORDER 0.00
TOTAL PENDING CHANGE ORDER 0.00
TOTAL THIS CHANGE ORDER 0.00
TOTAL % OF THIS CHANGE ORDER 0%
TOTAL C.O.% OF ORIGINAL WORK ORDER 0%
ADJUSTED WORK ORDER COST $ 986,407.00
CONTRACTOR: Hydro Construction, Inc.
By: Date:
Name: John Podeyn Title: Project Manager
ACCEPTANCE: Date:
Link Mueller, Civil Engineer III
REVIEWED: Date:
Pat Johnson, Senior Buyer
ACCEPTANCE: Date:
Jason Graham, Director, Water Reclamation & Biosolids
DocuSign Envelope ID: 2C066E7D-332A-4822-B977-7BE8F1CD16DD
February 3, 2020
February 3, 2020
February 3, 2020
February 4, 2020
Change Order Form (for Work Orders)
Official Purchasing Form
Last updated 10/2017
ACCEPTANCE: Date:
Matt Fater, Director, Civil Engineering
ACCEPTANCE: Date:
Carol Webb, Deputy Director, Water Resources & Treatment Operations
ACCEPTANCE: Date:
Theresa Connor, Deputy Director, Water Engineering & Field Services
ACCEPTANCE: Date:
Gerry Paul, Purchasing Director
(if greater than $60,000)
DocuSign Envelope ID: 2C066E7D-332A-4822-B977-7BE8F1CD16DD
February 4, 2020
February 4, 2020