WORK ORDER
PURSUANT TO A MASTER AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
DITESCO, LLC
WORK ORDER NUMBER: 2019-Ditesco-01
PROJECT TITLE: Project Management Services – Residuals
Handling Alternatives Analysis
ORIGINAL BID/RFP NUMBER & NAME: 8745 – Engineering Services for Water,
Wastewater and Stormwater Facilities
Capital Improvements – On-Call
MASTER AGREEMENT EFFECTIVE DATE: August 7, 2018
ARCHITECT/ENGINEER: If using a 3rd party architect/engineer or City
PM/Engineer
OWNER’S REPRESENTATIVE: Mark Kempton
WORK ORDER COMMENCEMENT DATE: August 16, 2019
WORK ORDER COMPLETION DATE: November 31, 2019
MAXIMUM FEE: (time and reimbursable direct costs): $19,728.00
PROJECT DESCRIPTION/SCOPE OF SERVICES: Overall project management of the Residuals
Handling Program through the alternatives analysis including assistance with budget and schedule
management, engineering consultant management, cost control, and data collection.
Service Provider agrees to perform the services identified above and on the attached forms in
accordance with the terms and conditions contained herein and in the Master Agreement between
the parties. In the event of a conflict between or ambiguity in the terms of the Master Agreement
and this Work Order (including the attached forms) the Master Agreement shall control.
The attached forms consisting of three (3) pages are hereby accepted and incorporated herein,
by this reference, and Notice to Proceed is hereby given after all parties have signed this
document.
SERVICE PROVIDER: Ditesco, LLC
By: Date:
Name: Title:
DocuSign Envelope ID: A811FC49-23D9-4115-9FC1-D923A6D4F845
8/15/2019
KEITH MEYER Owner/Manager
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
OWNER’S ACCEPTANCE & EXECUTION:
This Work Order and the attached Contract Documents are hereby accepted and incorporated
herein by this reference.
ACCEPTANCE: Date:
Mark Kempton, Project Manager
REVIEWED: Date:
Pat Johnson, Senior Buyer
APPROVED AS TO FORM: Date:
Name,City Attorney's Title
(if greater than $1,000,000)
ACCEPTANCE: Date:
Carol Webb, Utilities Deputy Director
ACCEPTANCE: Date:
Name, Title
ACCEPTANCE: Date:
Kevin Gertig, Utilities Executive Director
(if greater than $1,000,000)
ACCEPTANCE: Date:
Gerry Paul, Purchasing Director
(if greater than $60,000)
ACCEPTANCE: Date:
Darin Atteberry, City Manager
(if greater than $1,000,000)
ATTEST: Date:
City Clerk
(if greater than $1,000,000)
DocuSign Envelope ID: A811FC49-23D9-4115-9FC1-D923A6D4F845
8/15/2019
8/16/2019
8/19/2019
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
ATTACHMENT A
WORK ORDER SCOPE OF SERVICES
DocuSign Envelope ID: A811FC49-23D9-4115-9FC1-D923A6D4F845
Page 2 of 4
Exhibit A
Residuals Handling
Project Management
Scope of Services
Project Understanding
The City of Fort Collins (COFC) is continuing an evaluation of their Residuals Handling program to determine a
more efficient and effective means to manage aluminum sulfate WTP residuals. The alternatives being evaluated
include belt filter press, centrifuge and discharge to the sanitary sewer collection system.
The project is currently starting the alternatives evaluation phase. HDR is the consulting engineer responsible for
the analysis and design documents. The project is expected to be delivered through selection of a contractor using
a CM/GC or CMaR process. Alternatives analysis will be complete by fall 2019 to allow for appropriate funding
requests within the City. If funded, design is expected to occur throughout 2020.
The services provided under this contract are generally expected to include project management, budget and
schedule control, contract management, oversight and coordination with the design engineers. We are also
anticipating detailed coordination with COFC staff throughout the alternatives analysis process.
Phase: Alternatives Analysis
• During this phase Ditesco will manage the alternatives analysis work with HDR attending meetings,
coordinating with plant staff and working through evaluation steps including on-site belt press
demonstrations and testing.
• We will attend regular coordination meetings with the design consultants and COFC staff to ensure
communication and coordination on various work elements.
• Our team will review and comment on updates to the Solids Handling Study (Jacobs).
• We will review and comment on HDR schedules, work products and deliverables.
• We will attend site visits at various Northern Colorado installations of belt presses; advise on equipment
selection and pricing alternatives.
• We will assist HDR in developing cost estimates for each alternative to include in the final report/technical
memorandum to the City.
• We will assist City staff with polymer dosing pilot testing and evaluate effectiveness on pond drying and
turn over operations.
Deliverables
• Deliverables will include full project documentation presented electronically including: schedules,
submittals, transmittals, reports, photographs, meeting notes, drawings and other relevant information
produced throughout the alternatives analysis phase. All documents will also be provided in an electronic
form (PDF or MS Office) on external drives for City use.
Schedule
The anticipated schedule for the alternatives analysis and design phase are as follows:
Alt Analysis: August through November 2019
DocuSign Envelope ID: A811FC49-23D9-4115-9FC1-D923A6D4F845
Page 3 of 4
Fee Estimate
We have based our fee estimate on the following assumptions:
• 16-week alternatives analysis timeline
• Ditesco will host project Procore site (if necessary)
Estimated Fee: $18,955.00
Estimated Reimbursable Expenses: $ 773.00
Total: $19,728.00
A detailed task breakdown is included. Please find this on page 4 of this scope of work proposal.
The fee shown above is to be billed on a time and material not-to-exceed basis based on the rates shown in the
table on page 4 of this proposal. All reimbursable expenses will be billed at direct cost.
DocuSign Envelope ID: A811FC49-23D9-4115-9FC1-D923A6D4F845
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
ATTACHMENT B
WORK ORDER COST DETAIL
DocuSign Envelope ID: A811FC49-23D9-4115-9FC1-D923A6D4F845
City of Fort Collins
Solids Handling Project Management - Alt Analysis Phase 8/8/2019
A B C D
Keith Meyer Cassidy Hill
Principal Project Admin
(hrs) (hrs)
$145 $65
Task 1: Project Management $18,955
1.1 Contract Management - Alt Analysis
- Contract Management 4 4 $764
- Bi-Weekly Progress Meetings 33 0 $4,829
- Weekly Engineer Coordination and Follow Up; Data Collection 44 0 $6,438
- Budget Management/Cost Control Review with COFC Staff 15 0 $2,111
- Schedule Control 4 0 $528
- COFC Staff Coordination/Meetings 15 0 $2,111
1.3 Review Plans/Specs/Cost Models
- Review Final TM 15 0 $2,175
Alt Analysis Phase Subtotal 125 4 $18,955
% Job Assignment - Phase 0.22 0.01
Cost $18,191 $237
Reimbursable Costs (mileage, etc) $773
Total Cost $19,728
Notes
tech memo comments/review
assume all meetings at WTF; HDR provides meeting minutes
routine coordination; data collection assistance
cost control worksheet/program budget
monthly document management; invoicing
Design Phase/Task Description Task Total
Person/Role - 2019-2020
alternatives analysis
project schedule to manage design and construction
internal CFOC staff meetings
Page 4 of 4