HomeMy WebLinkAboutCORRESPONDENCE - BID - 7658 MISCELLANEOUS CONCRETE ANNUAL (31)Estimate
Date
2/14/2019
Estimate #
C1696
Bill To:
City of Fort Collins
Stormwater
Attn: Doug Groves
P.O. Box 580
Fort Collins, Co. 80522
Project Location
Fossil Creek Meadows
Jason Eich
PO#9190317
P.O./ Work order # Terms
Net 30
Representat...
CH
Phone #
9704843880
Fax #
970-416-6230
E-mail
smagdaleno@lightfieldenterprises.com
Total
We propose to furnish material and labor-complete in accordance with the above specifications.
All work to be completed in a professional manner and in accordance with industry standards. Any alteration or deviation from above
specifications must be done in writing.
Estimate is good for 30 days.
Acceptance of Proposal: The above prices, specifications and conditions are satisfactory and are hereby accepted. Lightfield Enterprises is
authorized to do work as specified. I agree to pay as outlined in the "Terms" stated above.
Date of acceptence________________________Signature_____________________________________________
2600 Midpoint Drive
Fort Collins CO 80525
Description QtyUnit Cost Total
Remove Concrete Curb & Gutter 26 LF 6.50 169.00
Remove Concrete Sidewalk 72 SF 3.75 270.00
Truncated Dome Panel 16 SF 41.00 656.00
Vertical Curb and Gutter - No Sidewalk 49.1 LF 26.00 1,276.60
Flatwork - 6" 44.2 SF 5.85 258.57
Pedestrian Access Ramp 229.5 SF 8.25 1,893.38
Reinforcing Steel- Rebar and weld plates 916 LBS 3.75 3,435.00
Temporary Asphalt Patching 4 TON 195.00 780.00
Foreman 3 HOUR 50.00 150.00
Finisher 9 HOUR 45.00 405.00
Non-reinforced Concrete Footer - 8" 311 SF 18.00 5,598.00
Non-reinforced Concrete Wall - 8" 184 SF 18.00 3,312.00
$18,203.55