CHANGE ORDER
NO. #1
PROJECT TITLE: DataSplice Business Process, Prototype, and Configuration work for Water
Engineering & Field Services (WEFS) Waste Water division
CONTRACTOR: Datasplice LLC
WORK ORDER NUMBER:4a
PO NUMBER:
DESCRIPTION: Additional Datasplice support for Broadband Warehouse Materials Management.
Changed per R.Morford. 4/23/19
1. .Reason for Change: Project Schedule is out dated
2. Description of Change: Work Order was executed several months ago, schedule has become out dated
and needs to be updated to align with the current Oasis Broadband Warehouse schedule.
3. Change in Work Order Price: $0.00
4. Completion Date (if changed): June 28, 2019
ORIGINAL WORK ORDER PRICE $ 0.00
TOTAL APPROVED CHANGE ORDER $ 0.00
TOTAL PENDING CHANGE ORDER $ 0.00
TOTAL THIS CHANGE ORDER $ 0.00
TOTAL % OF THIS CHANGE ORDER %
TOTAL C.O.% OF ORIGINAL WORK ORDER %
ADJUSTED WORK ORDER COST $ $ 0.00
CONTRACTOR: Datasplice LLC
By: Date:
Name: Ryan Hall Title: Contracts Manager
REVIEWED: Date:
Pat Johnson, Buyer or Senior Buyer
ACCEPTANCE: Date:
Nate Poppema, datasplice LLC Project Manager
REVIEWED: Date:
Lori Clements, Sr Manager, Customer Support
REVIEWED: Date:
Lisa Rosintoski, Deputy Director, Utilities
ACCEPTANCE: Date:
Colman Keane, Executive Director, Broadband
DocuSign Envelope ID: DA1474DC-68D0-46A4-85F9-062A136A79DA
Change Order Form (for Work Orders) Official Purchasing Form
Last updated 10/2017
ACCEPTANCE: Date:
Coy Althoff, Utilities Asset Manager
ACCEPTANCE: Date:
Rick Morford, Project Manager
Attachment A
Datasplice Work Order #4a, Change Order #1 – updated work order schedule