Subject: Fee Estimate for Construction Observation and Materials Testing Services
Streets Facility Park
Fort Collins, Colorado
Fee Estimate No. FC 19-0122
At your request, CTL|Thompson, Inc. is pleased to provide this fee estimate for Construction
Observation and Materials Testing services for the Streets Facility Park project located in Fort
Collins, Colorado. We used the geotechnical report and plans that were provided in preparation of
our proposal.
We understand that the city will use our estimate for the basis of establishing a budget for the
project and to issue a purchase order for our services. Our estimated scope of services and
associated fees were prepared according to the terms and conditions of our professional services
agreement with the City of Fort Collins and are presented below.
Soil Compaction Testing: Compaction testing for utility trench backfill, pavement subgrade, sidewalk
subgrade, footing subgrade, slab subgrade, and foundation backfill will be necessary. We estimate
24 site visits will be necessary.
Soil Compaction Testing
24 days x 2 hrs/day x $70/hr
$3,360.00
Proctor Test
3 tests x $100/test
$300.00
Gradation Test
3 tests x $50/test
$150.00
Atterberg Limits Test
3 tests x $70/test
$210.00
Subtotal:
$4,020.00
Asphalt Testing: Compaction testing for the asphalt patches may be necessary. We estimate 2 site
visits will be necessary.
Engineering Technician
2 days x 3 hrs/day x $70/hr
$420.00
Subtotal:
$420.00
CITY OF FORT COLLINS
STREETS FACILITY PARK
CTL | T FEE ESTIMATE NO. FC-19-0122
2
Reinforcing Steel: Observation of the reinforcing steel for the bathroom and trellis foundations may
be necessary. We estimate 4 site visits will be necessary.
Engineering Technician
4 days x 2 hrs/day x $60/hr
$480.00
Subtotal:
$480.00
Concrete Testing: Concrete testing will be required for the sidewalks, curb, pavement, footings,
slabs, and foundation walls. We estimate 12 tests will be required.
Concrete Tests
12 tests x $180/test
$2,160.00
Subtotal:
$2,160.00
Masonry Observation: Observation of the reinforcement and grouting for the restroom walls will be
required. We estimate 6 site visits will be necessary.
Engineering Technician
6 days x 3 hrs/day x $70/hr
$1,260.00
Grout Test
4 cores x $50/test
$200.00
Mortar Test
1 set x $135/set
$135.00
Grouted Prism Test
3 prisms x $80/test
$240.00
Subtotal:
$1,835.00
Structural Steel Inspection: Inspection of the structural steel connections for the bathroom and trellis
may be necessary. We estimate 4 site visits will be necessary.
Engineering Technician
4 days x 3 hrs/day x $70/hr
$840.00
Subtotal:
$840.00
TOTAL ESTIMATED FEE: $9,755.00
It should be emphasized that this estimate is based upon assumptions of actual quantities and
contractor’s schedule. The fee will be charged only for the actual hours and unit rates presented for
tests and observations requested by the owner, contractor or subcontractors who schedule the
services.
If we can be of further assistance, please contact us at your convenience.
Very truly yours,
CTL | THOMPSON, INC.
Heather Grubb
Field Department Manager