HomeMy WebLinkAboutCORRESPONDENCE - RFP - 8354 MAXIMO MOBILEWORK ORDER
PURSUANT TO A MASTER AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
DATASPLICE LLC
WORK ORDER NUMBER: DS_MAX2019
PROJECT TITLE: DataSplice Interfaces between Maximo
Applications & Warehouse Inventory Functionality
ORIGINAL BID/RFP NUMBER & NAME: 8354 Maximo Mobile Product and Services
MASTER AGREEMENT EFFECTIVE DATE: January 2, 2017
OWNER’S REPRESENTATIVE: Rick Morford
WORK ORDER COMMENCEMENT DATE: April 1, 2019
WORK ORDER COMPLETION DATE: February 28 , 2020
MAXIMUM FEE: (time and reimbursable direct costs): $ 187,552.50
PROJECT DESCRIPTION/SCOPE OF SERVICES: Work Order DS_MAX2019 is for Datasplice to
develop requirements, conduct workshops and prototype sessions for mapping
and forms development with the intent and purpose of delivering a configured
Datasplice implementation for WFO Water Distribution.
Service Provider agrees to perform the services identified above and on the attached forms in
accordance with the terms and conditions contained herein and in the Master Agreement between
the parties. In the event of a conflict between or ambiguity in the terms of the Master Agreement
and this Work Order (including the attached forms) the Master Agreement shall control.
The attached forms consisting of 6 pages are hereby accepted and incorporated herein, by this
reference, and Notice to Proceed is hereby given after all parties have signed this document.
SERVICE PROVIDER: Datasplice LLC.
By: Date:
Name: Ryan Hall Title: Contracts Manager
REVIEWED: Date:
Pat Johnson, Senior Buyer
ACCEPTANCE: Date:
Gerry Paul, Purchasing Director
(if greater than $60,000)
ACCEPTANCE: Date:
Nate Poppema, Datasplice Project Manager
ACCEPTANCE: Date:
Theresa Connor, Deputy Director, Utilities
ACCEPTANCE: Date:
Coy Althoff, Utilities Asset Manager
DocuSign Envelope ID: EF5CC4C9-DF54-4825-B5BB-CA1EB549B5AE
4/3/2019
4/3/2019
4/3/2019
4/3/2019
4/3/2019
4/4/2019
OWNER’S ACCEPTANCE & EXECUTION:
This Work Order and the attached Contract Documents are hereby accepted and incorporated
herein by this reference.
ACCEPTANCE: Date:
Rick Morford, Project Manager
DocuSign Envelope ID: EF5CC4C9-DF54-4825-B5BB-CA1EB549B5AE
4/4/2019
ATTACHMENT A
Datasplice Work Order DS_MAX2019: Water Distribution Implementation Scope of
Work
Project Objective: DataSplice will configure a Water Distribution Application for the City of
Fort Collins. DataSplice will leverage any existing configuration, and other Work
Management/Service Request functionality that was configured as part of the other
configured DataSplice applications. DataSplice will perform the initial workshops with the
selected Managers, Supervisors, Super Users and End Users. DataSplice and Fort Collins
will develop a requirements document based on findings and discoveries during this process.
DataSplice will finalize the configuration with an Agile Software approach based on feedback
and requests received during scheduled Software Sprints. DataSplice has defined the
phases and deliverables for the Water Distribution project.
Sub-Task 1:
Initial Workshops and Requirements
1. DataSplice will coordinate with the FCU Water Distribution project team (Subject Matter
Expert (SME), Project Manager and DataSplice/Maximo Administrators) to employ
standard requirements gathering methods (employee interviewing, crew shadowing, etc.)
to determine the mobile user interface designs and other system requirements. DataSplice
will interview at a minimum: project sponsor, core team, key stakeholders/Super Users,
and FCU IT. DataSplice will create a Requirements document for FCU’s approval.
Deliverables:
1. Requirements Document–This list of requirements will be used to trace requirements
to on-site testing to ensure all requirements are traceable and all requirements are met
from inception to implementation.
Vendor Responsibilities: Coordinate with Fort Collins to perform ride-alongs and
workshops. Provide required documentation for FCU’s approval.
The City Responsibilities: Participate in meetings and provide feedback/updates as
needed. Provide access to the necessary systems required for DataSplice.
Sub-Task 2:
Software Configuration
1. DataSplice will configure the system, in the Development environment, to meet the
approved requirements, as determined by the findings in the requirements phase. The
configuration of the DataSplice application is expected to include the Work Orders and
Forms.
2. DataSplice will modify the default COTS software screens and configuration to interoperate
with the specific FCU Maximo instance and its business processes. In addition to the COTS
standard currently available features.
3. DataSplice will provide any required and related Maximo configuration to ensure that
DataSplice is properly integrating with Maximo. If additional resources are required to
perform any Maximo configuration, DataSplice will notify FCU.
4. DataSplice will build up to 6 Forms based on existing templates or newly provided Forms
from the City of Fort Collins.
Deliverables:
1. Configured DataSplice Water Distribution Application in Maximo DEV and TRN
Environments.
DocuSign Envelope ID: EF5CC4C9-DF54-4825-B5BB-CA1EB549B5AE
Vendor Responsibilities: Lead final Software Sprint meeting, provide updated
documentation.
The City Responsibilities: Participate in meetings and provide updates as requested.
Sub-Task 3:
Software Sprints 1 and 2
1. DataSplice will demo the configured system in the Development and QA/Training
environments, based on the finalized/approved requirements. DataSplice will assist with
any required and related Maximo configuration to ensure that DataSplice is successfully
integrating with Maximo. DataSplice will provide 2 of these “Sprints” to show the software
configuration and functionality.
2. DataSplice will modify the current software configuration to interoperate with the City’s
instance of Maximo and its business processes.
Deliverables:
1. Updated Configuration.
2. 2 Software Sprints
Vendor Responsibilities: Lead 2 Software Sprint meetings, provide updated
documentation.
Sub-Task 4:
Final Sprint and Finalize Configuration
3. DataSplice will finalize the configured system in the Development and QA/Training
environments, based on the finalized/approved requirements. DataSplice will assist with
any required and related Maximo configuration to ensure that DataSplice is successfully
integrating with Maximo.
4. DataSplice will modify the current software configuration to interoperate with the City’s
instance of Maximo and its business processes.
Deliverables:
3. Finalized Configuration.
4. Final Software Sprint.
5. Finalized and locked down DataSplice configuration prior to UAT.
Vendor Responsibilities: Lead final Software Sprint meeting, provide updated
documentation.
The City Responsibilities: Participate in meetings and provide updates as requested.
Sub-Task 5:
User Acceptance Testing Support
1. DataSplice will provide support and guidance as required during UAT. DataSplice will be
on-site at the designated City of Fort Collins location. Problems identified during UAT will
be recorded as “Issues” with the City of Fort Collins project team. All issues will be resolved,
canceled, or deferred (by the City of Fort Collins) prior to go-live.
2. DataSplice will have two technical resources available for support. City of Fort Collins will
need to have multiple (2-3) functional testers and (2-3) technical support personnel during
this phase.
Deliverables:
1. Prepare updated User Acceptance Testing scripts based on any new changes that
have been agreed to be included in the finalized configuration.
2. Support User Acceptance Testing on-site and collect reported defects, change
DocuSign Envelope ID: EF5CC4C9-DF54-4825-B5BB-CA1EB549B5AE
requests and enhancements. Review list with the City of Fort Collins to determine
included configuration items
Vendor Responsibilities: Provide finalized UAT scripts, support UAT remotely and
on-site based on finalized UAT agenda,
The City Responsibilities: Coordinate UAT resources, provide necessary UAT
hardware, determine final UAT planned activities, and execute DataSplice’s test scripts,
review and prioritize UAT items.
Sub-Task 6:
Training
1. DataSplice will provide End User Training for the Water Distribution Groups. The training
will be separated into 3 classes and DataSplice record these training sessions as a
reference for follow-up trainings. DataSplice will also provide up to three 2-hour follow-
up end user training classes.
Deliverables:
1. Provide Training Documentation (User Guide and Cheat Sheet).
2. Perform End User Training for the City of Fort Collins with the designated personnel
to be agreed upon between DataSplice and the City.
3. Provide refresher Training prior to Go-Live to demonstrate any configuration UI
changes.
Vendor Responsibilities: Coordinate Training room and Trainees, provide access to
DataSplice from a device (handheld, laptop, etc.).
The City Responsibilities: Provide training to selected City of Fort Collins trainees.
Provide updated training documentation, record training sessions and distribute to City
of Fort Collins.
Sub-Task 7:
Cutover to Production Support
1. DataSplice, working collaboratively with the City of Fort Collins IT staff, will plan and
perform the migration of the DataSplice Software Application from the test/TRN
environment to the Production environment. The cutover planning will detail required go-
live activities, timing, and responsibilities.
2. During go-live, DataSplice, along with key stakeholders, will perform a test of the
Production environment using the User Acceptance Test plan/scripts to confirm the
success of the migration.
Deliverables:
1. Confirmed Production Environment.
2. Production Cutover Plan.
3. Support the City of Fort Collins in their necessary work processes.
Vendor Responsibilities: Provide Cutover to Production Plan document and support
Go-Live activities.
The City Responsibilities: Coordinate DataSplice and Maximo administrator resources
and the mobile team, prepare devices for deployment, identify users ahead of time for
the initial mobile use.
DocuSign Envelope ID: EF5CC4C9-DF54-4825-B5BB-CA1EB549B5AE
Sub-Task 8:
Post Production Support
1. DataSplice will provide on-site technical and functional support to the users during the first
two days of production. This period of post-implementation support will provide a level of
comfort to the team and enable quick responses to end user questions and training needs.
During this period, DataSplice will have dedicated technical resources to assist with any
technical issues that may arise.
Deliverables:
1. Functional and Technical Support on-site.
Vendor Responsibilities: Provide resources to be on-site, reserve internal technical
resources for the Initial Go-Live period. Capture enhancement requests during this
period.
The City Responsibilities: Provide feedback and report issues to the City of Fort
Collins. Concisely explain the issue so DataSplice can effectively and efficiently
reproduce and correct the issue.
Sub-Task 9:
Project Management
1. DataSplice provides project planning and oversight, time reporting, and
DataSplice resource coordination. The DataSplice Project Manager works
closely with the City Project Manager to ensure a successful outcome.
2. The City provides the lead project management resource effort. The DataSplice
project team members participate in weekly project status meetings as scheduled
by the City and agreed to by DataSplice. Verbal status reports are delivered during
the status meetings. Additionally, written status reports are provided weekly via the
City’s preferred format.
Deliverables:
1. Bi-Weekly written status reports
2. Participate in Bi-Weekly Status meetings Project schedules.
Vendor Responsibilities: Provide weekly written status reports and participate in
weekly meetings.
The City Responsibilities: Participate in meetings and provide updates as requested.
Assumptions:
1. DataSplice will finalize the configuration based on all feedback received through
this stage of the project. DataSplice will produce a list that will include the
configuration items that will be included in the Go-Live.
2. The Development and QA environments will be refreshed prior to UAT. DataSplice
will be performing the majority of the configuration work in the QA environment until
the Development is refreshed.
3. DataSplice will not be creating Work Orders on Service Lines.
Exclusions:
1. Additional configuration changes that were identified after the final Prototype
meeting.
DocuSign Envelope ID: EF5CC4C9-DF54-4825-B5BB-CA1EB549B5AE
Sub-Task 10:
Build up to 6 Forms
1. DataSplice will configure up to 6 Forms Water Distribution Forms.
2. DataSplice will prototype the 6 Forms and incorporate feedback into the Forms.
Deliverables:
1. Finalized Forms Configuration for up to 6 Forms
2. Demonstration of the Forms “as built”
3. Configuration migrated to training environment for testing
Vendor Responsibilities: Lead final Forms Prototype meeting, provide updated
documentation.
The City Responsibilities: Participate in meetings and provide updates as requested.
ATTACHMENT B
Datasplice Work Order DS_MAX2019: Water Distribution Implementation
Project Schedule
DocuSign Envelope ID: EF5CC4C9-DF54-4825-B5BB-CA1EB549B5AE
ATTACHMENT C
Datasplice Work Order DS_MAX2019: Water Distribution Implementation
Project Costs
HOURS BREAKDOWN
Reimbursable Direct Costs
• Reimbursable direct costs take the form of travel related costs. Total travel costs for the
period of performance as defined by Work Order DS_MAX2019 are estimated at $0.00.
Maximum Compensation
• The maximum compensation for both Labor time and Reimbursable direct costs as a
not to exceed is summarized in the table below. This agreement may not be modified,
altered or amended except by written instrument duly executed by both parties, prior to
work proceeding, for the proposed changes.
Labor Direct Costs Total Not to Exceed
(NTE)
$ 187,552.50 $ 0.00 $ 187,552.50
Change Order Tasks Project Manager
- Nate Poppema
Software Engineer
- Mike Johnson
Software
Engineer – Chris
Riess
Totals
Hourly Rate $148.75 $191.25 $191.25
Initial Workshops and
Requirements and Ride
Alongs
4 56 16 76
Software Configuration 206 40 246
Software Sprints 1 and 2 4 32 8 44
Final Sprint and Finalize
Configuration
4 96 16 116
User Acceptance Testing
Support and Add’l
Configuration
64 24 88
Training and Training
Documentation
96 24 120
Cutover to Production
Support
32 16 48
Post Production Support
40 8 48
Project Management 48 80 128
Build up to 6 Forms 48 32 80
Total Planned Labor 60 750 184 994
Total Cost Breakdown $8,925.00 $143,437.50 $35,190.00 $187,552.50