HomeMy WebLinkAboutCORRESPONDENCE - RFP - 8225 MAXIMO CONSULTING SERVICES (9)WORK ORDER
PURSUANT TO A MASTER AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
EXCERGY CORPORATION
WORK ORDER NUMBER: LPO_DBREVIEW
PROJECT TITLE: Consulting Support for Asset Register and Work Order
Management System
ORIGINAL BID/RFP NUMBER & NAME: 8225 Maximo Consulting Services
MASTER AGREEMENT EFFECTIVE DATE: March 28, 2016
OWNER’S REPRESENTATIVE: Rick Morford
WORK ORDER COMMENCEMENT DATE: March 11, 2019
WORK ORDER COMPLETION DATE: April 4, 2019
MAXIMUM FEE: (time and reimbursable direct costs): $39,898.00
PROJECT DESCRIPTION/SCOPE OF SERVICES: In preparation for the LPO Data Conversion/Migration to
Maximo Excergy is being asked to assess and review designated LPO Microsoft Access
data.
Service Provider agrees to perform the services identified above and on the attached forms in accordance with
the terms and conditions contained herein and in the Master Agreement between the parties. In the event of
a conflict between or ambiguity in the terms of the Master Agreement and this Work Order (including the
attached forms) the Master Agreement shall control.
The attached forms consisting of 4 pages are hereby accepted and incorporated herein, by this reference, and
Notice to Proceed is hereby given after all parties have signed this document.
SERVICE PROVIDER: Excergy Corporation
By: Date:
Name: __James Ketchledge Title: CEO & President
OWNER’S ACCEPTANCE & EXECUTION:
This Work Order and the attached Contract Documents are hereby accepted and incorporated herein by this
reference.
REVIEWED: Date: _
Pat Johnson, Senior Buyer
ACCEPTANCE: Date: _
Tim McCollough, Deputy Director, Utilities
ACCEPTANCE: Date: _
Coy Althoff, Utilities Asset Manager
ACCEPTANCE: Date:
DocuSign Envelope ID: AE56C546-8934-415D-AEDF-14DD3B905E32
3/15/2019
3/18/2019
3/18/2019
3/18/2019
Gerry Paul, Purchasing Director
(if greater than $60,000)
ACCEPTANCE: Date:
Rick Morford, Project Manager
DocuSign Envelope ID: AE56C546-8934-415D-AEDF-14DD3B905E32
3/18/2019
Attachment A
Work Order LPO_DBREVIEW, Excergy LPO Access Data Assessment Scope of Work
LPO Data Project Objective:
Work Order LPO_DBREVIEW is to cover Excergy’s work assisting Fort Collins with an LPO
data assessment of designated Access Data to include but not limited to: Structures,
ADMIRE, Serialized Equipment and Switch Point Inspections. This support will be
executed to cover the LPO Access Data Assessment for a period of time not to exceed 4
weeks; a week will be defined as 5, 8-hour days.
Task 1: Project Support
Excergy, upon request from City of Fort Collins, will provide assistance in the
following areas of Project Management: planning and oversight, maintenance of
schedule, reporting of issues which may include risk management. Excergy will
provide a consulting team labor/task invoice report broken down by individual
Excergy resource and time spent per task.
The City of Fort Collins will provide the lead project management resource as a central
point of contact. Excergy project team members will participate as needed in ad-hoc
or scheduled meetings organized by the City of Fort Collins. Verbal status reports may
be required during any ad-hoc or scheduled status meetings. In addition to verbal
reports, work order updates shall be included as part of the weekly project status
meeting report authorized by Work Order LPO_DBREVIEW. Hours for this support are
shown in the labor hours and cost breakdown table below (Appendix C).
Excergy Deliverables for this task
• Provide assistance/support for steps required to complete all tasks listed in this
work order
• Maintain communications (email/voice/other)
• Review, edit, or provide feedback following completion of each task listed in this
work order
• Participate in/support ad-hoc or scheduled meetings as needed, which may
include teleconferences or online with appropriate staff as needed
• Manage consulting team in performance of tasks and activities including time
reporting
• Work order updates
Utility Deliverables for this task
• Provide a Utilities PM as a central point of contact
• Work with City of Fort Collins Utilities and Excergy Teams to complete all tasks
in this work order
• Participate in/support scheduled meetings, which may include
teleconferences or online with appropriate utility personnel as needed
• Provide administrative/logistics/meeting support as needed
• Maintain communications (email/voice/other)
DocuSign Envelope ID: AE56C546-8934-415D-AEDF-14DD3B905E32
• Review, edit, or provide feedback as necessary to finalize task deliverables
• Support/Manage Utility Teams in the performance of, or activities required to
complete, tasks listed in this work order
Task 2: Bi-Weekly Meetings
The Excergy team together with the City of Fort Collins staff will participate in two (2)
bi-weekly meetings in support of Work Order LPO_DBREVIEW tasks. Excergy, upon
request from the City of Fort Collins, will provide agendas for scheduled bi-weekly
support meetings. Excergy upon request may be asked to facilitate Work Order
LPO_DBREVIEW support meetings, as well at times Excergy may be tasked with
developing presentations for support meetings.
The City of Fort Collins will be responsible for scheduling all Work Order
LPO_DBREVIEW bi-weekly support meetings. Documenting all Work Order
LPO_DBREVIEW bi-weekly support meetings and distribution of meeting
notes/documentation to all City of Fort Collins staff and Excergy team members
participating in these support meetings will be the responsibility of the City Project
Manager. Hours for this support are shown in the labor hours and cost breakdown
table below (Appendix C).
Excergy Deliverables for this task
• Facilitate two bi-weekly meetings to status on findings
• Upon request develop support meeting agendas
• As needed, develop support meeting presentations
• Participate in support meetings as requested, which may include
teleconferences or online with appropriate staff as needed
• Maintain communications (email/voice/other)
• Execute consulting tasks and activities as required
Utility Deliverables for this task
• Participate in support meetings, which may include teleconferences or online
with appropriate utility personnel
• Provide administrative/logistics/meeting support
• Maintain communications (email/voice/other)
• Record and document all support meetings
• Distribute all support meeting documentation to City of Fort Collins Utilities staff
and Excergy team members participating in support meetings
Task 3: Data Implementation Assessment
Excergy, with Fort Collin’s assistance, will review designated LPO Access data in
preparation for a future migration into Maximo; this data review will be to determine
effort required for a subsequent data migration. After a thorough data review by Fort
Collins a copy of the designated LPO Access data will be provided to Excergy for an
assessment and review.
Following the data review by Fort Collins staff and the follow-up data review by
DocuSign Envelope ID: AE56C546-8934-415D-AEDF-14DD3B905E32
Excergy, findings status will be shared with Fort Collins to clarify questions identified
during the review and to confirm next steps needed to correct any issues which might
impede migrating LPO Access data into Maximo at a later date. Hours for this support
are shown in the labor hours and cost breakdown table below (Appendix C).
Excergy Deliverables for this task
• Provide assistance/support for Data review tasks as requested by Fort Collins
• Maintain communications (email/voice/other)
• Review, edit, or provide feedback following data review
• Support scheduled meetings, which may include teleconferences or online with
appropriate staff as needed
• Execute consulting tasks and activities as required
Utility Deliverables for this task
• Provide the LPO Access data to Excergy for review
• Participate in/support scheduled meetings, which may include
teleconferences or online with appropriate utility personnel as needed
• Maintain communications (email/voice/other)
• Review, edit, or provide feedback as necessary to finalize task deliverables
• Execute utility tasks and activities as needed
Task 4 Organization Change Management - Stakeholder Matrix and Timeline
Excergy will assist in identifying the impacts of the LPO database migration to LPO
staff and will also consider impacts from other FCU high priority projects. A
stakeholder matrix will be developed showing LPO staff that will be impacted by the
LPO database migrations and by other FCU projects such as GIS/ADMS and the
Oasis/OSF projects. A second dimension will identify stakeholder impact over time to
help identify the timing for when various high priority projects will be deployed. The
outputs from these deliverables will identify who is impacted by the Maximo and
other high priority project initiatives and when they are being impacted. Hours for this
support are shown in the labor hours and cost breakdown table below (Appendix C).
Excergy Deliverables for this task
• Compile stakeholder by technology (LPO database, system, application) matrix
• Compile stakeholder by high priority project timeline
Utility Deliverables for this task
• Provide administrative/logistics/meeting support
• Maintain communications (email/voice/other)
• Review, edit, or provide feedback as necessary to finalize deliverables in a timely
manner
Attachment B
Work Order LPO_DBREVIEW, Excergy LPO Access Data Assessment Schedule
DocuSign Envelope ID: AE56C546-8934-415D-AEDF-14DD3B905E32
Figure 1 LPO Preliminary Data Assessment Schedule
This Project schedule will be reviewed and updated during the bi-weekly Project Status
meeting. The period of performance for this work order is March 11, 2019 to April 5,
2019. If changes in work order scope or a deviation from the attached schedule are
required during the performance of this work order a change order will be executed.
DocuSign Envelope ID: AE56C546-8934-415D-AEDF-14DD3B905E32
Attachment C
Work Order LPO_DBREVIEW, Excergy LPO Access Data Assessment Pricing
Figure 2 Labor & Costs Breakdown
Reimbursable Direct Costs: Reimbursable direct costs take the form of travel related costs. Total travel
costs for the period of performance as defined by Work Order LPO_DBREVIEW are estimated at
$2,122.00.
Labor Direct Costs Total Not to Exceed
(NTE)
$37,776 $ 2,122 $ 39,898
Project Director
Communication
s/Change
Management
Specialist
Communication
s/Change
Management
Specialist
Business
Process
Specialist
Project
Manager
Functional
Maximo
Specialist Tier 2
Functional
Maximo
Specialist Tier 2
Functional
Maximo
Specialist Tier 2
Jim Ketchledge Lynn Adams Rebecca Shiflea Mark Hatfield Patrick Noonan Rick Crory Andrew Tan
Emmanuel
Okekeocha
$ 247.00 $ 247.00 $ 247.00 $ 247.00 $ 225.00 $ 160.00 $ 160.00 $ 160.00 Total Hours Amount
Task 1 - Project Support
Project Support 1 8 8 4 21 $ 3,967.00
Subtotal 1 - - - 8 8 4 - 21 $ 3,967.00
Task 2 - Project Communications
Bi-Weekly Meetings 6 6 12 $ 2,310.00
Subtotal - - - - 6 6 - - 12 $ 2,310.00
Task 3 - Data Implementation Assessment
Conduct Data Review 8 40 80 128 $ 21,000.00
Review Feedback 2 3 3 8 $ 1,410.00
Subtotal - - - - 10 43 84 - 137 $ 22,570.00
Task 4 - OCM - Stakeholder Matrix and Timeline
Stakeholder by technology matrix 1 3 18 22 $ 5,038.00
Stakeholder by high priority project timeline 1 2 14 17 $ 3,891.00
Subtotal - 2 5 - 32 - - - 39 $ 8,929.00
Total Hours 1 2 5 - 56 57 88 - 209 $ 37,776.00
Total Labor $ 247.00 $ 494.00 $ 1,235.00 $ - $ 12,600.00 $ 9,120.00 $ 14,080.00 $ -
Travel Expense $ - $ - $ - $ - $ 668.00 $ 1,454.00 $ - $ - $ 2,122.00
Total Cost to Client $ 247.00 $ 494.00 $ 1,235.00 $ - $ 13,268.00 $ 10,574.00 $ 14,080.00 $ - $ 39,898.00