HomeMy WebLinkAboutCORRESPONDENCE - RFP - 8371 ARCHITECTURAL & ENGINEERING SERVICES ON-CALL (4)CHANGE ORDER NO. 02
PROJECT TITLE: City Hall ADA Upgrades
CONTRACTOR: AU Workshop
PROJECT NUMBER: PO 9173154
DESCRIPTION: Design ADA improvements
In preparing change orders show in order as separate numbered paragraphs the following:
1 . Reason for change:
2. Description of change:
3. Change in contract cost:
4. Change in contract time:
(Attach additional sheets as required)
ORIGINAL CONTRACT COST
TOTAL APPROVED CHANGE ORDERS
TOTAL PENDING CHANGE ORDERS
TOTAL THIS CHANGE ORDER
TOTAL % OF THIS CHANGE ORDER
Total C.O. % of Original Contract
ADJUSTED CONTRACT COST
$30,400.00
(Assuminq all chanqe orders approved)
ACCEPTED BY:
Contractor's Representative Date
ACCEPTED BY:
Project Manager Date
REVIEWED BY:
Print Name Date
APPROVED BY:
Date
cc: City Clerk Project File
Contractor Purchasing
Engineer
I
$1,200.00
$0.00
$0.00
0.00%
Extend Completion Date
Extend the project completion date to March 1, 2019
$0.00
No Cost Change --- ---
New Substantial Completion Date of March 1, 2019
Jason Kersey - AU Workshop LLC
Brian Hergott - Operation Services
Print Name Ken Mannon - Operations Services Director
3.95%
$31,600.00
APPROVED BY:
Print Name Gerry Paul - Purchasing Director Date
If over $60,000 - Purchasing Director
02/05/2019