Good morning Rick,
We’re finally coming close to completion of this project. We expect to be 100% finished by next Friday.
During the course of construction, we came across some unforeseen expenses. These were costs we
could not have expected prior to the demo being completed, which is why we are requesting a
supplement to the contract at this time. Please let us know if you have any questions, and if not, if this
supplement is approved and can be added prior to final invoice. I have attached the estimate, but to
summarize, the charges are for the following additional scope of work.
Lines 1‐7 were not included in the original estimate at all, because we thought that the fire department
removed the vent and it would just be able to be put back in, but it actually had to be replaced and we
couldn’t get the same size again, so some siding removal and replacement was also necessary. We also
had to pressure wash that elevation so that the siding could be painted.
Lines 8‐9 are to replace fire damaged top plate, which wasn’t discovered until after the insulation was
removed.
Lines 10‐13 are for trim around the perimeter of the ceiling, because due to code requiring the plywood
ceiling to be replaced with a double layer of 5/8” drywall, the ceiling comes lower than the wall and
there was an unsightly gap caused by this process. We trimmed out the perimeter of the ceiling of both
bathrooms to accommodate this gap.
Line 14 is for plumbing work that was an unknown cost in the original estimate (documented in the
original estimate as unknown at the time). The plumber had to repair several broken pipes in order to
pass city inspection.
Line 15 is to install an attic access – there wasn’t one previously and it was needed in order to do the
work required in the attic – primarily the insulation.
Line 16 was for a heater that was needed to perform the work in the Winter.
Please let me know if you have questions, or if this is approved.
Thank you,
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Caitlin Tanner
Project Coordinator
Cell: 970‐413‐9638
SERVPRO of Fort Collins
Office: 970‐493‐6335
servprofortcollins.com
1
SERVPRO of Fort Collins
D&A Enterprises, Inc.
308 N. Link Lane, Fort Collins, CO 80524
(970) 493-6335
Tax ID: 90-0622986
Franchise #10019
info@servprofortcollins.com
Insured: Fort Collins Parks & Recreation Home: (970) 566-4989
Property: 3074 S Overland Trail
Fort Collins, CO 80535
Estimator: Damen Lippold Business: (970) 286-9749
E-mail: dlippold@servprofortcollins.
com
Position: Estimator - Project Manag
Company: Servpro of Fort Collins
Business: 308 N. Link Lane
Fort Collins, CO 80524
Claim Number: Policy Number: Type of Loss: Fire
Date of Loss: Date Received:
Date Inspected: Date Entered: 1/31/2018 1:43 PM
Price List: COFC8X_JAN18
Restoration/Service/Remodel
Estimate: R18014-SUP
2
SERVPRO of Fort Collins
D&A Enterprises, Inc.
308 N. Link Lane, Fort Collins, CO 80524
(970) 493-6335
Tax ID: 90-0622986
Franchise #10019
info@servprofortcollins.com
R18014-SUP 12/27/2018 Page: 2
R18014-SUP
Exterior
DESCRIPTION QTY
1. Clean with pressure/chemical spray - Heavy 55.00 SF
2. R&R Attic vent - gable end - wood 1.00 EA
3. Seal & paint wood gable vent 1.00 EA
4. Seal & paint wood siding 55.00 SF
5. Prime & paint exterior soffit - wood 28.00 SF
6. Prime & paint exterior fascia - wood, 4"- 6" wide 28.00 LF
7. Mask and prep for paint - plastic, paper, tape (per LF) 52.00 LF
Main Level
Main Level
DESCRIPTION QTY
8. R&R Bottom plate - 2" x 6" - treated 104.00 LF
9. R&R Wedge anchor bolt - 5/8" x 8 1/2" 13.00 EA
Woman's Bathroom Height: 9' 6"
DESCRIPTION QTY
10. Trim board - 1" x 4" - installed (pine) 77.93 LF
11. Seal & paint trim - two coats 77.93 LF
This item includes additional trim work, due to the thickness of the drywall ceiling.
Men's Bathroom Height: 9' 6"
DESCRIPTION QTY
12. Trim board - 1" x 4" - installed (pine) 74.37 LF
13. Seal & paint trim - two coats 74.37 LF
This item includes additional trim work, due to the thickness of the drywall ceiling.
Mechabical Room Height: 9' 6"
3
SERVPRO of Fort Collins
D&A Enterprises, Inc.
308 N. Link Lane, Fort Collins, CO 80524
(970) 493-6335
Tax ID: 90-0622986
Franchise #10019
info@servprofortcollins.com
R18014-SUP 12/27/2018 Page: 3
DESCRIPTION QTY
14. Plumbing (Bid Item) 1.00 EA
The above line item included the below additional work after our plumbers inspected the plumbing.
1- Repair 4" PVC vent stack, including 4" studor vent installed in attic
2- Repair (1) one 2" copper water main
Storage Area/Room Height: 9' 6"
DESCRIPTION QTY
15. R&R Attic entrance cover and trim 1.00 EA
Miscellaneous
DESCRIPTION QTY
16. Temporary heater - propane - per day 20.00 DA
This line item includes the cost to run temp heat for the drywall and painting.
Labor Minimums Applied
DESCRIPTION QTY
17. Siding labor minimum 1.00 EA
Grand Total $5,855.36
Damen Lippold
Estimator - Project Manag
4
SERVPRO of Fort Collins
D&A Enterprises, Inc.
308 N. Link Lane, Fort Collins, CO 80524
(970) 493-6335
Tax ID: 90-0622986
Franchise #10019
info@servprofortcollins.com
R18014-SUP 12/27/2018 Page: 4
Grand Total Areas:
2,244.11 SF Walls 612.43 SF Ceiling 2,856.54 SF Walls and Ceiling
612.43 SF Floor 68.05 SY Flooring 236.22 LF Floor Perimeter
0.00 SF Long Wall 0.00 SF Short Wall 236.22 LF Ceil. Perimeter
612.43 Floor Area 730.90 Total Area 2,568.67 Interior Wall Area
1,372.73 Exterior Wall Area 111.83 Exterior Perimeter of
Walls
1,289.35 Surface Area 12.89 Number of Squares 182.79 Total Perimeter Length
37.08 Total Ridge Length 0.00 Total Hip Length