HomeMy WebLinkAboutCORRESPONDENCE - BID - 7658 MISCELLANEOUS CONCRETE ANNUAL (14)10/26/18 202.01 Sawcut Concrete/Asphalt (0" < 4") Lineal Foot 0 0 $3.47 $ - 202.02 Sawcut Concrete/Asphalt 4" < 6" Lineal Foot 100 120 $3.68 $ 441.60 202.03 Sawcut Concrete/Asphalt 6" < 8" Lineal Foot 0 0 $3.99 $ - 202.04 Sawcut Concrete/Asphalt 8" ≤ 10" Lineal Foot 0 0 $5.78 $ - 202.05 Sawcut - Additional 1" Depth Lineal Foot 0 0 $1.26 $ - 202.06 Remove Concrete Sidewalk Square Foot 530 636 $3.57 $ 2,270.52 202.07 Remove Concrete Curb and Gutter Lineal Foot 0 0 $6.09 $ - 202.08 Remove Monolithic Curb, Gutter & Sidewalk Square Foot 0 0 $3.89 $ - 202.09 Remove Concrete Driveway/Apron/Crosspan Square Foot 650 780 $4.15 $ 3,237.00 202.10 Remove Concrete Pavement - 10" Square Foot 0 0 $4.94 $ - 202.11 Remove Concrete Pavement - Additional 1" Depth Square Foot 0 0 $1.05 $ - 202.12 Remove Asphalt - 6" Square Foot 200 240 $2.73 $ 655.20 202.13 Remove Asphalt - Additional 1" Depth Square Foot 0 0 $1.05 $ - 202.14 Remove Inlet Each 0 0 $540.75 $ - 202.15 Remove and Haul Driveway Fillet Each 0 0 $52.50 $ - 202.16 Remove Flagstone Square Foot 0 0 $3.15 $ - 203.01 Excavation - General Less Than 50 CY Cubic Yard 0 0 $49.35 $ - 203.02 Excavation - General Over 50 CY Cubic Yard 0 0 $44.10 $ - 203.03 Excavation - Walls Only Cubic Yard 0 0 $12.08 $ - 203.04 Excavation - New Inlet Each 0 0 $425.25 $ - 203.05 Borrow - Less than 100 Ton Ton 0 0 $26.25 $ - 203.06 Borrow - Over 100 Ton Ton 0 0 $23.10 $ - 208.01 Stormwater Protection - Rock Filled Wattle Lineal Foot 0 0 $12.08 $ - 208.02 Stormwater Protection - Recycled Rubber Filled Wattle Lineal Foot 0 0 $16.80 $ - 208.03 Stormwater Protection - Straw Bales Each 0 0 $21.00 $ - 210.01 Reset Flagstone Square Foot 0 0 $4.20 $ - 210.02 Reset Brick Pavers Square Foot 0 0 $8.40 $ - 210.03 Adjust Manhole Each 0 0 $105.00 $ - 210.04 Adjust Valve Box Each 0 0 $105.00 $ - 304.01 Aggregate Base Course/Recycled Concrete Base ≤ 5 Tons Ton 0 0 $40.95 $ - 304.02 Aggregate Base Course/Recycled Concrete Base > 5 Tons Ton 0 0 $38.85 $ - 304.03 Recycled Asphalt Base Ton 0 0 $26.25 $ - 403.01 Temporary Asphalt Patching Ton 3 3.6 $215.25 $ 774.90 601.01 Exposed Sand Finish - Additional Charge Square Foot 0 0 $3.68 $ - 602.01 Reinforcing Steel Pound 0 0 $2.30 $ - 602.02 Reinforcing Steel - Epoxy Coated Pound 0 0 $3.45 $ - 604.01 Install New Area Inlet Each 0 0 $1,485.00 $ - 604.02 Area Inlet – Additional Foot Depth Lineal Foot 0 0 $136.50 $ - 604.03 Reconstruct Area Inlet Deck – Remove & Replace Each 0 0 $1,575.00 $ - 604.04 Reconstruct Area Inlet Deck - Additional Foot Opening – Remove & Replace Lineal Foot 0 0 $136.50 $ - 604.05 Reconstruct Catch Basin Deck - Remove & Replace Each 0 0 $780.00 $ - 604.06 Reconstruct Catch Basin Deck - Additional Foot Opening – Remove & Replace Lineal Foot 0 0 $151.20 $ - 604.07 Install New Curb Inlet – 4’ Opening Each 0 0 $2,003.00 $ - 604.08 Curb Inlet – Additional Foot Depth Lineal Foot 0 0 $115.50 $ - 604.09 Reconstruct Curb Inlet Deck – Remove and Replace Each 0 0 $761.25 $ - 604.10 Reconstruct Curb Inlet Deck – Additional Foot Opening – Remove and Replace Lineal Foot 0 0 $136.50 $ - 604.11 Install New Type R Inlet - 5' Opening Each 0 0 $3,680.00 $ - 604.12 Type R Inlet – Additional Foot Depth Lineal Foot 0 0 $173.25 $ - 604.13 Reconstruct Type R Inlet Deck – Remove and Replace Each 0 0 $1,286.25 $ - 604.14 Reconstruct Type R Inlet Deck – Additional Foot Opening – Remove and Replace Lineal Foot 0 0 $131.25 $ - 604.15 Install New Modified Type 13 Curb Inlet (includes new Frame, Grate & Adjustable Curb Bonnet) Each 0 0 $2,645.00 $ - 604.16 Modified Type 13 Curb Inlet – Additional Foot Depth Lineal Foot 0 0 $168.00 $ - 604.17 Reconstruct Modified Type 13 Curb Inlet Deck – Remove & Replace Each 0 0 $1,737.25 $ - 604.18 Reconstruct Modified Type 13 Curb Inlet Deck – Additional Foot Opening – Remove and Replace Lineal Foot 0 0 $252.00 $ - 604.19 Modified Type 13 Curb Inlet – Materials only - (Frame, Grate, & adjustable bonnet (East Jordan Iron Works 7030 or Equivalent Material) Each 0 0 $760.00 $ - 604.20 Concrete Sidewalk Culvert – 4’ opening Each 0 0 $624.75 $ - 604.21 Metal Sidewalk Culvert - 2' Opening, Remove & Replace Each 0 0 $625.00 $ - 604.22 Metal Sidewalk Culvert - 2' Opening, Materials Only Each 0 0 $2,130.00 $ - 604.23 Additional Square Foot 5/8" Plate Square Foot 0 0 $215.00 $ - 608.41 Non-reinforced Concrete Footer - 8" Square Foot 0 0 $17.33 $ - 608.42 Concrete Staining/Sealing Square Foot 0 0 $4.20 $ - 608.43 Expansion and Caulking Lineal Foot 0 0 $4.15 $ - 608.44 Joint Sealant (Pavement) Lineal Foot 0 0 $4.46 $ - 608.45 Irrigation Sleeve Lineal Foot 0 0 $4.46 $ - 608.46 Dump Fee Ton 0 0 $58.80 $ - $ 50,845.02 626.01 Mobilization - Invoices Under $1000 LS 0 0 $0.00 $ - 630.01 "NO PARKING" Sign With Stand Per Each Per Day 40 48 $2.10 $ 100.80 630.02 Vertical Panel Without Light Per Each Per Day 0 0 $1.31 $ - 630.03 Channelizing Barrels Per Each Per Day 0 0 $1.58 $ - 630.04 Type I/II Barricade Without Light Per Each Per Day 0 0 $0.68 $ - 630.05 Type III Barricade Without Light Per Each Per Day 20 24 $3.94 $ 94.56 630.06 Size A Sign With Stand ( < 16SF) Per Each Per Day 40 48 $1.89 $ 90.72 630.07 Size B Sign With Stand ( > 16SF) Per Each Per Day 40 48 $2.10 $ 100.80 630.08 Size A Specialty Sign - Cost of Manufacturing Each 0 0 $73.50 $ - 630.09 Size B Specialty Sign - Cost of Manufacturing Each 0 0 $78.75 $ - 630.10 Cone With Reflective Strip Per Each Per Day 0 0 $0.84 $ - 630.11 Safety Fence Per Roll Per Day 20 24 $4.46 $ 107.04 630.12 Light Per Each Per Day 0 0 $0.53 $ - 630.13 Advance Warning Flashing or Sequencing Arrow Panel Per Each Per Day 0 0 $78.75 $ - 630.14 Variable Message Board Per Each Per Day 0 0 $183.75 $ - 630.15 Traffic Control Supervisor Per Day 7 8.4 $434.70 $ 3,651.48 630.16 Traffic Control Supervisor Hour 0 0 $45.15 $ - 630.17 Flagging Hour 50 60 $29.93 $ 1,795.80 $ 5,941.20 $ 56,786.22 SUM TRAFFIC CONTROL WORK TOTAL COST SUM CONCRETE WORK TRAFFIC CONTROL 608.01 Driveover Curb, Gutter & 6" Sidewalk Lineal Foot 0 0 $44.10 $ - 608.02 Driveover Curb and Gutter - No Sidewalk Lineal Foot 430 516 $24.68 $ 12,734.88 608.03 Vertical Curb, Gutter and 6" Sidewalk Lineal Foot 0 0 $45.57 $ - 608.04 Vertical Curb and Gutter - No Sidewalk Lineal Foot 60 72 $28.35 $ 2,041.20 608.05 Out Fall Curb & Gutter Lineal Foot 0 0 $22.68 $ - 608.06 Hollywood Curb, Gutter and 6" Sidewalk Lineal Foot 0 0 $32.18 $ - 608.07 Hollywood Curb and Gutter - No Sidewalk Lineal Foot 0 0 $20.06 $ - 608.08 Highback Curb and Gutter - No Sidewalk Lineal Foot 0 0 $38.90 $ - 608.09 Barrier Curb - 6" x 18" Lineal Foot 430 516 $25.36 $ 13,085.76 608.10 Barrier Curb - Key Way Style Lineal Foot 0 0 $25.36 $ - 608.11 Barrier Curb - Epoxy Lineal Foot 0 0 $20.21 $ - 608.12 Mountable Curb - 12" x 18" Lineal Foot 0 0 $25.99 $ - 608.13 Mountable Curb - Keyway Style Lineal Foot 0 0 $25.36 $ - 608.14 Mountable Curb – Epoxy Lineal Foot 0 0 $24.68 $ - 608.15 Pedestrian Access Ramp Square Foot 0 0 $8.03 $ - 608.16 Pedestrian Access Ramp, Highback Curb Square Foot 0 0 $9.08 $ - 608.17 Truncated Dome Panel Square Foot 0 0 $52.75 $ - 608.18 Apron - 8" Square Foot 0 0 $8.56 $ - 608.19 Crosspan - 8" Square Foot 0 0 $8.56 $ - 608.20 Valley Pan - 6" Square Foot 0 0 $7.61 $ - 608.21 Flatwork - 4" Square Foot 530 636 $5.25 $ 3,339.00 608.22 Flatwork - 6" Square Foot 770 924 $6.09 $ 5,627.16 608.23 Replace Flatwork - 1" Additional Depth Square Foot 0 0 $1.10 $ - 608.24 Concrete Pavement 8" (Joints Sealed) Square Foot 0 0 $8.56 $ - 608.25 Alley Approach - 8" Square Foot 650 780 $8.51 $ 6,637.80 608.26 Enhanced Crosswalk - 10" Tile Red Square Foot 0 0 $13.13 $ - 608.27 Enhanced Crosswalk - 10" San Diego Buff Square Foot 0 0 $11.87 $ - 608.28 Enhanced Crosswalk - 10" Brick Red, Stamped Square Foot 0 0 $14.07 $ - 608.29 Colored Trail with Fibermesh - 5" Yosemite Brown Square Foot 0 0 $7.46 $ - 608.30 Mow Strip - 4" x 12" Lineal Foot 0 0 $9.71 $ - 608.31 Splashblock - 4" Exposed Aggregate Square Foot 0 0 $7.46 $ - 608.32 Splashblock - 4" San Diego Buff Square Foot 0 0 $7.82 $ - 608.33 Median Cover - 4" San Diego Buff Square Foot 0 0 $7.82 $ - 608.34 Fibermesh - Added to Any Item - Additional Charge Pounds / Cubic Yard 0 0 $10.76 $ - 608.35 24 Hour High Early Concrete - Added to Any Item - Additional Charge Cubic Yard 0 0 $21.00 $ - 608.36 Stamp Pattern - Added to Any Item, Additional Charge Square Foot 0 0 $2.89 $ - 608.37 6" Concrete Bollard Each 0 0 $464.00 $ - 608.38 8" Concrete Bollard Each 0 0 $580.00 $ - 608.39 Flowable Fill Cubic Yard 0 0 $120.75 $ - 608.40 Non-reinforced Concrete Wall - 8" Square Face Foot 0 0 $17.33 $ - CONCRETE WORK SHERWOOD ALLEY BID SCHEDULE Item No. Description Unit Quantity Quantity Plus 20% 2018 Revised Unit Price Total Cost Est