HomeMy WebLinkAboutCORRESPONDENCE - PURCHASE ORDER - 9185212Requisition Form
Vendor: Today's Date: Requisition No.:
Ship To: Date Entered:
Date Required: Date Approved:
Special Instructions: Date Denied:
Item # Quantity Unit Description Total Charge Number
Requested By: Authorized By:
Authorized By:
Name, title typed here under the line
Name, title typed here under the line Name, title typed here under the line
Unit Price
I\ENG\FORMS\Blank Requisition.xls
Final Site Grading
Tim McCollough
Bob Hover
Heather Hagar Jack Everett
Connell Resources 109445
Harmony Duct Bank - Harmony Substation $13,800.00 5010082662.554999..3660
DocuSign Envelope ID: 5C750EC4-8580-41EA-B4D9-003837915FAE
9/13/2018
9/13/2018
9/13/2018
DocuSign Envelope ID: 5C750EC4-8580-41EA-B4D9-003837915FAE
Connell Resources, Inc.
7785 Highland Meadows Pkwy, #100
Fort Collins, CO 80528
Phone: (970) 223-3151
Fax: (970) 223-3191
Estimator: Roland Tremble BUDGET FOR COST Date: 8/30/2018
Submitted To: City Of Fort Collins - Utilities Budget Title: Harmony Substation Grading
Address: 700 Wood St. Budget Number:
Fort Collins, CO 80522 Project Location: Harmony Road
Contact: Jack Everett Project City, State: Fort Collins, CO
Phone: (970) 221-6700 Fax: (970) 221-6619 Engineer/Architect:
We have prepared for your information the following items for budget evaluation purposes for the referenced project. This budget includes conceptual quantities, resource
costs, scope-of-work and schedules and therefore may not completely represent all items of work or cost ultimately necessary for completion of the project. This budget
was prepared using reasonable skill and judgment, but is not an offer to perform the Work described.
Item # Item Description Estimated Quantity Unit Unit Price Total Price
A. General Conditions
00-100 Mobilization / Management / Model Creation 1.00 LS $3,200.00 $3,200.00
00-175 Pothole Existing Utilities 8.00 HR $225.00 $1,800.00
Total Price for above A. General Conditions Items: $5,000.00
D. Earthwork
23-500 Finish Grading 2.00 DY $4,400.00 $8,800.00
Total Price for above D. Earthwork Items: $8,800.00
Total Bid Price: $13,800.00
Notes: • Pricing is based upon meeting with Jack Everett
Estiimate is based on no import or export of material, Assumes that surveying and control will be provided by the City of fort collins as
needed.
• The following are excluded from this proposal: Construction layout and engineering; Drainage facility certification; Warrantee period in
excess of one year; Street cleaning for work performed by others; Permits: including but not limited to, city building, development
construction, construction dewatering, wastewater discharge, storm water discharge (NPDES), air quality, etc.; Fees, including but not
limited to, for development, inspection, utility connection, meters, etc.; Dewatering; Maintenance of erosion control devices for others;
quality control or acceptance testing; prairie dog removal, relocation, or extermination; landscaping, seeding, or revegetation.
• All work is contingent on access to the work, signed work order, a mutually agreeable schedule.
• Please provide a minimum of 4 weeks advanced notification of work requests to allow for scheduling the work. No work will be completed
without a signed Contract Agreement.
• Frost removal or winter protection is not included. If requested, it will be billed either on a time and material basis or a lump sum amount
that is mutually agreed upon.
• Environmental site assessment / mitigation of hazardous or contaminated materials is excluded. Treatment or testing for contaminated
groundwater is specifically excluded.
• Add 1% to include performance and payment bond.
• Project is assumed to follow COFC miscelaneous contract and will be charged at Actual cost plus 16% markup.
Harmony Substation Grading Page 1 of 1