PROJECT TITLE: DDA - Old Town Square Renovation
CONTRACTOR: Mortenson Construction, Inc.
PROJECT NUMBER: 8031
PURCHASE ORDER NO.: 9151772
DESCRIPTION: Waterline Installation to Mountain Ave.
. Reason for change:
This change order adds the extension of waterline installation from the DDA terminus point near Trimble
Court Alley to Mountain Ave. This work is being paid for by the City of Fort Collins Utilities as part of the Old
Town Square Renovation.
I
2. Description of Change:
This change order includes installation of 12" C900 waterline, fittings, thrust blocks, service connections,
hydrant installation, valve installation, backfill and testing according to the approved utility plans attached
hereto.
i
3. Change in Contract Cost: $ 43,709.00
4. Change in Contract Time: 0 calendar days for substantial completion
0 calendar days for final completion
ORIGINAL CONTRACT COST
$2,868,187.00
TOTAL APPROVED CHANGE ORDERS
$0.00
TOTAL PENDING CHANGE ORDERS
$0.00
TOTAL THIS CHANGE ORDER
$ 43.709.00
TOTAL % OF ORIGINAL CONTRACT, THIS C.O.
1.52%
TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S
1.52%
ADJUSTED CONTRACT COST
$2,911,896.00
(Assuming all change orders approved)
ACCEPTED BY:
Contractor's Represent "
REVIEWED BY:
Construction Manager
APPROVED BY:
DDA Project Manager
APPROVED BY:
DDA Executive Director
APPROVED BY:
Purchasing Agent over $60,000
cc: City Clerk Architect
Contractor Engineer
Project File Purchasing
DATE: 1 zoi
DATE: 4 13 20 j5
DATE: 13 I S
DATE: (Ito (S
DATE: