HomeMy WebLinkAboutCHANGE ORDER - BID - 7602 STREETSCAPE MAINTENANCE SERVICESqi 5 2? 2 1
SECTION 00950
CHANGE ORDER NO. 1
PROJECT TITLE: Streetscape Maintenance Service 7602
CONTRACTOR: Korby Landscape
PROJECT NUMBER: 7602
DESCRIPTION:
1. Reason for change: Change to contract. Additional areas added with other areas deleted or
modified.
2. Description of Change: Addition of the following areas to existing contract:
• Tumberry Parkway(s)
• North College Medians and Parkways
• Shield and Hobbit Parkway
• 1-25 and Highway 392 Interchange (west)
• Total Increase Cost of $25,423.22
Deletion of the following areas in the current contract:
• West Horsetooth Medians
• Harmony and College Median
• Kechter & Ziegler Round -A -Bout
• Harmony and Shields Medians
• Total Decrease in Cost of $4411.53
Contract Increase of $21,011,69
3. Change in Contract Cost: $156,031.60 to $177,043.29 (For clarification these cost do not
include the 325 hrs. of labor hours x general labor cost in the
contract
4. Change in Contract Time: NA
ORIGINAL CONTRACT COST $156031.60
TOTAL APPROVED CHANGE ORDER .00
TOTAL PENDING CHANGE ORDER .00
TOTAL THIS CHANGE ORDER $21011.69
TOTAL % OF THIS CHANGE ORDER
TOTAL C.O.% OF ORIGINAL CONTRACT %
ADJUSTED CONTRACT COST $ 177043.29
(Assuming all changes orders approveq)_
ACCEPTED BY: LA DATE:
Contr=or'spr sdjati� ( /
REVIEWED BY: % DATE: �` 3 ' �5�
Project Manager
APPROVED BY:
Director of Purchasing & Risk Management
(over $60,000)
cc: City Clerk Contractor Engineer
Project File Architect Purchasing
DA