Change Order Form
PROJECT TITLE: River Restoration et Woodward Tec11 10109y Center Lot 4 BID NUMBER: 7579
CONTRACTOR: Walsh Construction Inc
CHANGE ORDER NUMBER: 5
n
n Dranarmr a.,.,c
I. Reason for cha '"" " �F,,,� etn rlumoerea peregraphSZFie o Owing: nge. See Anached Exhibit A dated March 5, 2015
2. Descdption of Contract Change: See Attached Exhb4 A dated March 5, 2015
3. Change in Contract Cost: See Attached _
4. Change in Contract time: See Attached $ 00 Decrease
0 Increase Decrease
ORIGINAL CONTRACT COST
TOTAL APPROVED CHANGE ORDERS
TOTAL PENDING CHANGE ORDERS
TOTAL THIS CHANGE ORDER
TOTAL % OF THIS CHANGE ORDER
TOTAL C.O. % ORIGINAL CONTRACT
ADJUSTED CONTRACT COST
(Assuming all change orders approved)
LA
lf/Z
$1,994,383.00
$345.975,06
$0.00
_ 38.620.00
1.94% ®-
19.28%
$2,378,978.06
ACCEPTED BY: l� i+� +�T• � -- \
- (welsh nstructio c.) DATE: 3I! �' 15 ...._
APPROVED BY: _
( ty Of Ft. Collins) DATE:
APPROVED BY:
(Purchasing Agent over
tt Comrades
Pluchagnp
PR)jM F40
LO(O
DATE:
Recommended for accepto4 :e
WTWC, LLC
3/18/2015
g1y660
-113
City of
r' _ �y ^O) l'Y Natural Areas
r� (`/>�r'' j [V ` n 1745 14 4%w Milt Rona
� P.O. Box 580
Natural Fon CaBns, CO eo522.05eo
370.416.2815
Areas 4 970 416 2211 lax
Change Order Form
PROJECT TITLE: River Restoration at Woodward Technology Center tot 4
BID NUMBER: 7579
CONTRACTOR: Walsh Construction Inc. / /r
CHANGE ORDER NUMBER: 6-
inprep ring change orders show In order as separate numDerect paragraphs the lvlowly
1. Reason for change:
2. Description of Contract Change.
3. Change in Contract Cost: $ 26,614.00 ®Deoroase
4. Change in Contract time: 0 Increase Decrease
See Attached Exhibit A dated March 5, 2015
ORIGINAL CONTRACT COST $1'994'383'00
TOTAL APPROVED CHANGE ORDERS $394,595.06
TOTAL PENDING CHANGE ORDERS $0"00
28.614.00
TOTAL THIS CHANGE ORDER
TOTAL % OF THIS CHANGE ORDER 1•33%
TOTAL C.O. % OF ORIGINAL CONTRACT 20•'
ADJUSTED CONTRACT COST $2''S��
(Assuming all change orders approved) +t
ACCEPTED BY:�-_ DATE: _� I � &\ \S --
(Walsn Construction. Inc
APPROVED BY: ,((n DATE. I J
( rty of FL Collins)
APPROVED BY: DATE: ---
(Purchasing Agent over $60.000)
�s Corro'eaa
PwU+ashnp
Proled Poe
/3
Cit of
F"'i i ollin +
Natural Areas
V �7
\
PO M580 ry Road
eav 580
Natural
F
Fes, Collins, c099sz2 r:se9
Areas
970,416.2616
970 416.2211 . W
Change Order Form
PROJECT 727LE: River Restoration at oodward Technology Centsr Lot a
BID NUMBER: 7579
CONTRACTOR: Walsh Construction Inc.
CHANGE ORDER NUMBER: 7 C' (/ tj C�
In r w y mange Orders show m or r , separ a num parag 1e a owing t Reason for change:
2. Description of Contract Change:
3. Change in Contract Cost 4Change in Contract $ (30,B20.o0) Increase---J
. Gme: 0 Increase Decrease
See Attached Exhibit A dated March 5, 2015
ORIGINAL CONTRACT COST
TOTAL APPROVED CHANGE ORDERS $1,994,383.00
TOTAL PENDING CHANGE ORDERS $411,209.06
TOTAL THIS CHANGE ORDER $0 00
TOTAL i, OF THIS CHANGE ORDER (30,820.00)
TOTAL C.O. % ORIGINAL CONTRACT
ADJUSTED CONTRACT COST 19.4 7%
(Assuming all Change orders approved) `, \ 52,374,772.06
ACCEPTED BY: I u\Qttv,�T , 4V R-� DATE:
Z
Co Inc.) DATE: -- —.—
APPROVED BY: Zv /f
(City or Ft. Conins )
APPROVED BY:
(Purchasing Agent over $60,000 DATE:
« cone
Purtlxseg
Prow File