HomeMy WebLinkAboutWORK ORDER - RFP - 7175 BRIDGE INSPECTION MAINTENANCE REPAIR AND REPLACEMENT PROGRAM (15)WORK ORDER
PURSUANT TO AN AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
MICHAEL BAKER JR., INC.
DATED: February 25, 2015
Work Order Number: 4-254902100-15
Purchase Order Number:
Project Title: Arthur Ditch Manhole Retrofits Project Post -Design Support Services
Original Bid/RFP Project Number & Name:
Commencement Date: 2/2512015
Completion Date: 5/29/2015
Maximum Fee: (time and reimbursable direct costs): Not to exceed $6,020.00
7,1 -0 /�
Project Description: Arthur Ditch Manhole Retrofits Project Post -Design Support Services
Scope of Services. See attached.
Professional agrees to perform the services
identified above and on the attached forms in
accordance with the terms and conditions
contained herein and in the Professional Services
Agreement between the parties. In the event of a
conflict between or ambiguity in the terms of the
Professional Services Agreement and this work
order (including the attached forms) the
Professional Services Agreement shall control.
The attached forms consisting of two (2) pages
are hereby accepted and incorporated herein, by
this reference, and Notice to Proceed is hereby
given.
Professional
By:
Date: 2l2 V1S—
City of Fort
By:
Project Manager: ang
Date: ��
By:
Gerry Paul
Director of Purchasing and Risk Management
(over $60,000.00)
Date:
165 South Union Boulevard, Suite 200 1 Lakewood, CO 80228
Office: 720.514.110 1 Fax: 720.479.3157
TO: Jin Wang, City of Fort Collins
FROM: Dave Nemovitz, Michael Baker International
DATE: February 25, 201S
PROJECT: Design Services for Arthur Ditch Manhole Retrofits at Lake Street and
Prospect Road Project
SUBJECT: Post -Design Support Services - Scope of Work & Fee Estimate
At the request of the City, Baker will provide post -design engineering support during construction
for the above referenced project. As the Engineer -of -Record, Baker is best suited to support the
City for this work, including:
• Review of contractor submittals (working drawings, shop drawings, and product
information)
• Review and response of contractor requests for information (RFI)
• Other technical support as requested by the City.
An approximate estimate of labor and fee has been prepared to support this work. The estimate is
approximate because the level and scale of the work is not known at this time, and is subject to the
Contractor's needs. Therefore, if additional scope is needed beyond that assumed in the attached
estimate, a change order would be needed to complete that work.
This requested is for a total $6,020. Please refer to the attached estimate for a breakdown of costs.
Please contact me if you have an questions or concerns.
Regards,
Dave Nemovitz, PE
Enclosure
MICI IAH BAKER INTERNAT10NA1, C"
Global Innovatiorv... Done Right
:1.111► /®LLLYPORT PNISI
(t