HomeMy WebLinkAboutCHANGE ORDER - AGREEMENT MISC - WIZARD WORKSCHANGE ORDER NO. 01
PROJECT TITLE:
MAX BRT - STC Gate
CONTRACTOR:
Wizard Works
PROJECT NUMBER:
PURCHASE ORDER NO.:
9145866
DESCRIPTION:
Contract reconciliation through 12-24-14
1. Reason for change:
This change order reconciles contract changes on the MAX BRT STC Gate contract through December 24, 2014. i
This change order is supported by work change directives describing each change authorized on this contract.
Work change directive 1 is hereby incorporated by reference.
2. Description of Change:
This change order includes changes to the contract to address power supply to the STC Gate controller. This
change addresses both a contract time and value change.
3. Change in Contract Cost: $5,951.00
4. Change in Contract Time: 39 calendar days for substantial completion
p calendar days for final completion
ORIGINAL CONTRACT COST $59,401.00
TOTAL APPROVED CHANGE ORDERS $0.00
TOTAL PENDING CHANGE ORDERS $0.00
TOTAL THIS CHANGE ORDER $ 5,951.00
TOTAL % OF ORIGINAL CONTRACT, THIS C.O. 10.02%
TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S 10.02%
ADJUSTED CONTRACT COST $
(Assuming all change orders approved)
ACCEPTED
Contractor's
REVIEWED
Construction
APPROVED
City Project I
APPROVEC
City Engineer
APPROVED BY: N I
Purchasing Agent over $60,000
cc: Owner Engineer
contractor Purchasing
Project File
DATE: /' a _ /s
DATE: 1-27-IS
DATE: ( - 23,� • t'�_
DATE: ! _ 2-O _ /
DATE:
ma"'AL
CHANGE ORDER NO. 1
SUPPORTING DOCUMENTATION
Project: MAX BRT — STC Gate
Project No. 9145866
Date: January 2, 2015
Description of Change:
281 N College Ave
Fort Collins, CO 80524
This change order amends the MAX BRT STC Gate contract to accommodate a necessary power source to the
STC Gate. Work change directive 1is hereby incorporated by reference and included as attached.
Change in Contract Value:
The contract value is being increased by $5,951.00. Please see attached work change directive as summarized in
the table(s) below.
Work -Change Directives
Item Number
Description
Contract Value
WCDO01
Gate Power Connection
$5,951.00
Total Work Change Directives:
$5,951.00
Total Contract Change — this change order
Total Change Order: $5,951.00
Change in Contract Time:
Contract time changes associated with this change order are summarized below. All days shown are calendar
days.
Contract lime Summary
Original Contract Completion Date:
December 24, 2014
Contract Extension CD 001 — Gate Power Connection
39 calendar day(s)
Revised Contract Completion Date COi :
February 1, 2015
Page 1 of 1
Change Order 01
MAX BRT — STC Gate
maxWORK CHANGE DIRECTIVE
TO CONTRACTOR: Wizard Works Security Systems, Inc. WCD NO: 001
PROJECT: Mason Corridor — MAX BRT - STC Gate PROJECT NO: 9145866
OWNER: City of Fort Collins — Engineering Department
ENGINEER: City of Fort Collins IT Department/Ditesco
The following additions, deletions, or revisions to the Work have been ordered and authorized:
Description of Work:
(Title of WCD): Gate Power Connection
This Work Change Directive (WCD) directs the Contractor to procure materials and complete the work as
described in Alternate 2 listed below:
CRY
Alternate 2 - Contractor to bore additional 2" HDPE conduit to landscape area at STC; terminate
conduit in 12"x18"xl8" junction box; run %" GRC conduit up the exterior face of the STC column,
secured with conduit clips; connect new'/4" GRC conduit into electrical conduit chase, mounted to the
overhead canopy; continue installing new %" conduit, through utilitiy chase, core through wall, tic into
electrical room, and terminate in panel LIA. Electrical conduit wall penetration shall be scaled, water
tight. Contractor shall pull new wire from STC Gate location, through new conduit routing, and
terminate in Panel LIA. All surface mounted GRC to be painted to match the existing surface.
The work shall include supplying equipment, labor, and mateials to perform the work according to the MAX
BRT project specifications and approved submittals.
Accepted Price: 5$ ,951.00
Accepted Time Extension: 21 Calendar Days
The existing conduit availability assumed could be utilized during design is not feasible. A new conduit run is
necessary to install in order to provide power to the STC gate.
Attachments (List Supporting Documents):
Proposed Routing Drawings. Email Correspondence. Contractor Pricing.
It is understood that this Work Change Directive may change the Contract Price and/or Time, and is evidence that the parties
expect a Change Order request for approval to subsequently follow this Work Change Directive.
WCDOOI-GATE-POWER_CONNECTION-FINAL PAGE OF
Ordered By: (., (G�[ December 22, 2014
Owner Date
Recommended By: �vl DD
December 22, 2014
/)'Construction Manager Date
Copy: Owner, Engineer, File
PAGE 2 of 2
Tii M,yte n( TifA.� 9%
WIZARD WORKS
1960 N Rocky View Rd
Castle Rock, CO 80108
Phone
DATE
ESTIMATE NO.
303-798-5337
1 303-798-4492
12/18/2014
14-441
wizard-works@att.net
Estimate
NAME/ADDRESS
Ship To
STC-FTC
South Transit Center
City of Ft Collins, Colorado
TERMS
REP
FOB
ITEM
DESCRIPTION
QTY
COST
TOTAL
_- WCD 01 --
900CS
Alternate 2 - Underground boring charges
1
2,959.00
2,959.00
900CS
Alternate 2 - Electrical work charges
1
2,992.00
2,992.00
Sub Total - For WDC-01
5,951.00
NOTES: We are requesting an additional 3 weeks be added to the time line from the acceptance of this change order.
Sales Tax
0.00%
0.00
SIGNATURE
TOTAL
S5,95100
�,?.`
N�}m�u7F.dd
No Text
2 PLATFORM LIGHTING PLAN K7�
E3.0 1/16"w 1' -0"
10 R n12 n13 n14 n15T T T T T
4
f
Fort Coltins
Date of Estimate: 22-Dec-14
Contract Type: Mason Corridor - STC Herd Bid
Existing Contract or PO (Y/N): Y
Description of Goods (A) or Services IS): STC WCD 001 ICE
Additional conduit required for power routing to gate
Independent Cost Estimate
I have obtained the following estimate from; MAX BRT unit prlcesfNCD cost and online pricing
Published Price List / Past Pricing (date)
Engineering or Technical Estimate (performed by) JIII Burrell
Independent Third Party Estimate (performed by)
Other (specify)
Cost Estimate Details:
(Estimate calculafed In US Dollars)
e.,.r ..r sr...n..n e.....
Product
Unit Price
Quantity
Unit
Contract Item
Total
Bore 2" HDPE DR11 Conduit
$7.62
115
LF
MAX BRT
$876.30
2" HDPE DR 11 Conduit
$10.34
115
LF
MAX BRT
$1.189.10
Trenching
$4.35
10
' LF
MAX BRT
$43.60
1" GRC Conduil
$20.00
140
LF
MAX BRT
$2,800.00
12" x 18" Vault
$752.00
1
EA
MAX BRT
$752.00
14 gaugeconductor
$0.15
255
LF
MAXBRT
$35.25
6 aauae conductor
$0.00
255
LF
MAX BRT
$204.00
Landscaping Repair
$5000
1
LB
Estimated allowance
$50.00
Mark-up 5°/
$29T56
Sub -Total
$6,250.91
Cost of Services, Repairs, or Non -Standard Items
Item/Task:
Markup $0.00
Total Cost $6,250.91
Signature of Preparer:�/
2i18/2015
View assistance for Search Results
System for Award Management
Search Results
Current Search Terms: wizard* Works*
Notice: This printed document represents only the first page of your SAM search results. More results may be available. To
print your complete search results, you can download the PDF and print It.
No records found for current search.
SAM I system for Award Management 1.0
Note to all Users: This is a Federal Government computer system. Use of this
system constitutes consent to monitoring at all times.
Glossary
Search
Results
Entity
Exclusion
Search
it e
By Record
Status
BY
Functional
Area - Entity
Management
BY
Functional
Area -
perforrnance
Information
IBM v1.P.24.201 0116-1831
USA.g9�v,_
https://www.sam.gov/portal/SAM/?navigationalstate=JBPNS_rOOABXdcACJgYXZheCSmYW N Icy5wb3JObGVOYnJpZGdI LINUQVRFXOIEAAAAAQApdmlldzo... 1/1