Loading...
HomeMy WebLinkAboutBID - 8035 ARTHUR DITCH BRIDGE REPLACEMENT - CANYON STREET (2)ADDENDUM NO. 2 SPECIFICATIONS AND CONTRACT DOCUMENTS Description of BID 8035: Arthur Ditch Bridge Replacement Canyon Avenue OPENING DATE: 3:00 PM (Our Clock) December 10, 2014 To all prospective bidders under the specifications and contract documents described above, the following changes/additions are hereby made and detailed in the following sections of this addendum: THE BID OPENING HAS BEEN MOVED TO DECEMBER 10, 2014 AT 3:OOPM, OUR CLOCK. No further questions will be answered. Exhibit 1 – Questions and Answers. Exhibit 2 – Revised Bid Schedule - The bid sheet has been revised / attached that includes a $3500.00 F/A line item for landscape related repairs and improvements. Exhibit 3 - Included is a copy of the geotechnical report for this project which includes future repair locations that were sampled at the same time. Please contact John Stephen, CPPO, LEED AP, Senior Buyer at (970) 221-6777 with any questions regarding this addendum. RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED BY A WRITTEN STATEMENT ENCLOSED WITH THE BID/QUOTE STATING THAT THIS ADDENDUM HAS BEEN RECEIVED. Financial Services Purchasing Division 215 N. Mason St. 2nd Floor PO Box 580 Fort Collins, CO 80522 970.221.6775 970.221.6707 fcgov.com/purchasing Exhibit 1 - Questions and Answers 1. Is the existing box culvert precast or cast in place? a. The existing box at the downstream tie in point on Mulberry is precast, installed about 2004. The box being removed and replaced is cast in place. 2. Are the dimensions of the existing box culvert as shown on the upstream tie in consistent for the entire box to be removed (12’ X 3.5’)? a. Yes, however, these are the approximate inside dimensions. The wall thicknesses have varied along the alignment as discovered over time. Historically the existing box wall thickness has been 9”-12”. Without absolute confirmation of what this location entails, we could not specify exact dimensions of the existing, only provide historical reference of what has been found in other locations. 3. Does the precast box require epoxy coated reinforcing steel? a. No, final precast box design will be reviewed via shop drawing; however, the reinforcing steel for the precast section will NOT require epoxy coating. 4. What is the intent of the milling? a. The roadway profile changes are considerable at this location. Staff has analyzed station by station cross sections of existing vs. proposed. Some areas, as shown on page 6 require the full-depth section of existing HMA to be removed, while others areas will receive a milling of depths from 0-7” inches. The roadway will then need a series of leveling courses and full section build up to achieve a consistent base for the final 2” lift of HMA. 1 Clearing and Grubbing LS 1 $ - $ - 2 Removal of Portions of Structures (RCB) LF 312 $ - $ - 3 Removal of Inlet EACH 2 $ - $ - 4 Removal of Pipe LF 21 $ - $ - 5 Removal of Curb and Gutter LF 637 $ - $ - 6 Removal of Concrete (4"-8") SY 237 $ - $ - 7 Removal of Asphalt Mat (6"-9") SY 1068 $ - $ - 8 Removal of Asphalt Mat (Planing) (less than 3") SY 506 $ - $ - 9 Removal of Asphalt Mat (Planing) (3"-7.5") SY 600 $ - $ - 10 Removal of Wall LF 92 $ - $ - 11 Removal of Bollard EACH 2 $ - $ - 12 Removal of Posts (Including Attached Chain) EACH 12 $ - $ - 13 Potholing HOUR 16 $ - $ - 14 Embankment CY 14 $ - $ - 15 Muck Excavation CY 10 $ - $ - 16 Structure Excavation CY 841 $ - $ - 17 Structural Backfill (Class 1) CY 336 $ - $ - 18 Filter Material (Class A) CY 148 $ - $ - 19 Topsoil CY 20 $ - $ - 20 Silt Fence LF 193 $ - $ - 21 Erosion Control Supervisor HR 40 $ - $ - 22 Aggregate Bags LF 86 $ - $ - 23 Stabilized Construction Entrance EACH 1 $ - $ - 24 Concrete Washout Structure EACH 1 $ - $ - 25 Storm Drain Inlet Protection (Type II) EACH 7 $ - $ - 26 Remove & Stockpile Modular Wall LF 34 $ - $ - 27 Adjust Manhole EACH 2 $ - $ - 28 Dewatering LS 1 $ - $ - 29 Sod SF 1560 $ - $ - 30 Landscape Boarder (Timber Treated) (8' long) EACH 8 $ - $ - 31 Aggregate Base Course (Class 6) TON 103 $ - $ - 32 Aggregate Base Course (Special) (3"-4" Cobble) CY 8 $ - $ - 33 Hot Mix Asphalt (Grading S) (75) (PG 64-22) TON 216 $ - $ - 34 Hot Mix Asphalt (Grading SX) (75) (PG 64-22) TON 253 $ - $ - 35 Hot Mix Asphalt (Temporary) TON 29 $ - $ - 36 Waterproofing Membrane SY 195 $ - $ - 37 Concrete Class D (RCB) CY 44 $ - $ - 38 Concrete Wall (Mulberry St) LF 48 $ - $ - 39 Reinforcing Steel (Epoxy) LB 12837 $ - $ - 40 15 Inch Reinforced Concrete Pipe (CIP) (CLASS III) LF 119 $ - $ - 41 9'x2.5' Concrete Box Culvert (4-sided) (Precast) LF 582 $ - $ - 42 Single Curb Inlet EACH 2 $ - $ - 43 Manhole Ring & Cover (30-Inch) EACH 2 $ - $ - 44 Manhole Ring & Cover (36-Inch) EACH 1 $ - $ - 45 Fence (Plastic) LF 475 $ - $ - 46 Fence (Temporary) LF 668 $ - $ - 47 Concrete Driveways (6-Inch) SY 38 $ - $ - 48 Concrete Sidewalk (4-Inch) SY 162 $ - $ - 49 Curb and Gutter (Infall) LF 460 $ - $ - 50 Curb and Gutter (Outfall) LF 151 $ - $ - 51 Temporary Curb (8" Vertical Barrier) (DT-701) LF 87 $ - $ - 52 Sanitary Facility EACH 1 $ - $ - 53 Mobilization LS 1 $ - $ - 54 Concrete Barrier (Temporary)(includes resets) LF 132 $ - $ - 55 Barricade (Type 3 M-A)(Temporary) EACH 8 $ - $ - 56 Construction Traffic Sign (Panel Size A) EACH 9 $ - $ - 57 Construction Traffic Sign (Panel Size B) EACH 4 $ - $ - 58 Traffic Control Management DAY 20 $ - $ - 59 Traffic Control Inspection DAY 45 $ - $ - 60 Flagging HR 80 $ - $ - Geotechnical Engineering Report Arthur Ditch Bridge Replacement (RFP 7525) Three Intersections Fort Collins, Colorado December 3, 2013 Terracon Project No. 20135038 Prepared for: J-U-B Engineers, Inc. Fort Collins, Colorado Prepared by: Terracon Consultants, Inc. Fort Collins, Colorado TABLE OF CONTENTS Page EXECUTIVE SUMMARY ............................................................................................................ i 1.0 INTRODUCTION .............................................................................................................1 2.0 PROJECT INFORMATION .............................................................................................1 2.1 Project Description ...............................................................................................1 2.2 Site Location and Description...............................................................................2 3.0 SUBSURFACE CONDITIONS ........................................................................................2 3.1 Typical Subsurface Profile ...................................................................................2 3.2 Laboratory Testing ...............................................................................................3 3.3 Groundwater ........................................................................................................3 4.0 RECOMMENDATIONS FOR DESIGN AND CONSTRUCTION ......................................4 4.1 Geotechnical Considerations ...............................................................................4 4.1.1 Existing, Undocumented Fill .....................................................................4 4.1.2 Shallow Groundwater ...............................................................................4 4.1.3 Expansive/Collapsible Soils ......................................................................5 4.2 Earthwork.............................................................................................................5 4.2.1 Site Preparation ........................................................................................5 4.2.2 Demolition ................................................................................................6 4.2.3 Excavation ................................................................................................6 4.2.4 Subgrade Preparation ...............................................................................7 4.2.5 Fill Materials and Placement ......................................................................7 4.2.6 Compaction Requirements ........................................................................8 4.2.7 Grading and Drainage ...............................................................................9 4.2.8 Corrosion Protection .................................................................................9 4.3 Foundations .........................................................................................................9 4.3.1 Box Culvert - Design Recommendations ................................................10 4.3.2 Box Culverts - Bedding Recommendations .............................................11 4.4 Seismic Considerations......................................................................................11 4.5 Lateral Earth Pressures .....................................................................................12 5.0 GENERAL COMMENTS ...............................................................................................13 TABLE OF CONTENTS (continued) Appendix A – FIELD EXPLORATION Exhibit A-1 Site Location Map Exhibits A-2 to A-4 Boring Location Plan Exhibit A-5 Field Exploration Description Exhibits A-6 to A-14 Boring Logs Appendix B – LABORATORY TESTING Exhibit B-1 Laboratory Testing Description Exhibit B-2 Atterberg Limits Test Results Exhibits B-3 to B-4 Grain-size Distribution Test Results Exhibits B-5 to B-7 Swell-consolidation Test Results Appendix C – SUPPORTING DOCUMENTS Exhibit C-1 General Notes Exhibit C-2 Unified Soil Classification System Exhibit C-3 Laboratory Test Significance and Purpose Exhibits C-4 and C-5 Report Terminology Geotechnical Engineering Report Arthur Ditch Bridge Replacement (RFP 7525) Ŷ Fort Collins, Colorado December 3, 2013 Ŷ Terracon Project No. 20135038 Responsive Ŷ Resourceful Ŷ Reliable i EXECUTIVE SUMMARY A geotechnical investigation has been performed for the proposed Arthur Ditch Bridge Replacements to be constructed near the intersections of West Mulberry Street and Canyon Avenue, West Oak Street and South Whitcomb Street, and West Olive Street and South Loomis Avenue in Fort Collins, Colorado. Nine (9) borings, presented as Exhibits A-6 through A-14 and designated as Boring No. 1-1 through Boring No. 3-3, were performed to depths of approximately 15½ to 20½ feet below existing site grades. This report specifically addresses the recommendations for the three (3) proposed concrete box culvert replacements. Borings performed in these areas are for informational purposes and will be utilized by others. Based on the information obtained from our subsurface exploration, the site can be developed for the proposed project. However, the following geotechnical considerations were identified and will need to be considered: „ Existing, undocumented fill was encountered in the borings performed on this site to depths ranging from about 1½ to 5 feet below existing site grades. However, we believe deeper fills are present at each site corresponding with the construction of the existing box culverts. At the time this report was prepared, we did not possess any compaction test records for the existing fill. Recommendations for the existing fill are presented in this report. „ Comparatively soft and/or very moist to nearly saturated soils are anticipated at bearing depths of the proposed box culverts. These materials should be stabilized prior to construction of the proposed box culverts and placement of fills to achieve desired grades. „ The proposed replacement box culverts can be constructed on a reinforced concrete slab within a properly bedded excavation underlain by stable, prepared subgrade consisting of either properly compacted subgrade or engineered fill. If a pre-cast box culvert is selected, the base of the structure will constitute a reinforced concrete slab; no foundation will be necessary. „ The 2012 International Building Code, Table 1613.5.2 IBC seismic site classification for all three sites is D. „ Close monitoring of the construction operations discussed herein will be critical in achieving the design subgrade support. We therefore recommend that Terracon be retained to monitor this portion of the work. This summary should be used in conjunction with the entire report for design purposes. It should be recognized that details were not included or fully developed in this section, and the report must be read in its entirety for a comprehensive understanding of the items contained Geotechnical Engineering Report Arthur Ditch Bridge Replacement (RFP 7525) Ŷ Fort Collins, Colorado December 3, 2013 Ŷ Terracon Project No. 20135038 Responsive Ŷ Resourceful Ŷ Reliable ii herein. The section titled GENERAL COMMENTS should be read for an understanding of the report limitations. Responsive Ŷ Resourceful Ŷ Reliable 1 GEOTECHNICAL ENGINEERING REPORT Arthur Ditch Bridge Replacement (RFP 7525) Three Intersections Fort Collins, Colorado Terracon Project No. 20135038 December 3, 2013 1.0 INTRODUCTION This report presents the results of our geotechnical engineering services performed for the proposed Arthur Ditch Bridge Replacements to be constructed near the intersections of West Mulberry Street and Canyon Avenue, West Oak Street and South Whitcomb Street, and West Olive Street and South Loomis Avenue in Fort Collins, Colorado. The purpose of these services is to provide information and geotechnical engineering recommendations relative to: „ subsurface soil conditions „ foundation design and construction „ groundwater conditions „ seismic considerations „ grading and drainage „ earthwork „ lateral earth pressures Our geotechnical engineering scope of work for this project included the initial site visit, the advancement of nine (9) test borings to depths ranging from approximately 15 to 25 feet below existing site grades, laboratory testing for soil engineering properties and engineering analyses to provide geotechnical design and construction recommendations. Logs of the borings along with Boring Location Plans (Exhibits A-2 through A-4) are included in Appendix A. The results of the laboratory testing performed on soil samples obtained from the site during the field exploration are included in Appendix B. 2.0 PROJECT INFORMATION 2.1 Project Description Item Description Site layout Refer to the Boring Location Plans (Exhibits A-2 through A-4 in Appendix A) Proposed construction We understand the three existing box culverts will be replaced with new concrete box culverts. Grading We anticipate cuts and fills on the order of 10 feet will be required to complete the proposed box culvert replacements. Geotechnical Engineering Report Arthur Ditch Bridge Replacement (RFP 7525) Ŷ Fort Collins, Colorado December 3, 2013 Ŷ Terracon Project No. 20135038 Responsive Ŷ Resourceful Ŷ Reliable 2 2.2 Site Location and Description Item Description Location The three proposed box culvert replacement sites are located near the intersections of West Mulberry Street and Canyon Avenue, West Oak Street and South Whitcomb Street, and West Olive Street and South Loomis Avenue in Fort Collins, Colorado. Existing improvements The existing concrete box culverts are located in residential neighborhoods (West Oak Street and South Whitcomb Street; West Olive Street and South Loomis Avenue) and the parking lot of a city pool (Canyon Avenue between West Mulberry Street and West Magnolia Street). Current ground cover The proposed construction areas are covered with asphalt pavements, concrete curb and gutter, concrete flatwork, and landscaping. Existing topography The sites are relatively flat. 3.0 SUBSURFACE CONDITIONS 3.1 Typical Subsurface Profile Specific conditions encountered at each boring location are indicated on the individual boring logs included in Appendix A. Stratification boundaries on the boring logs represent the approximate location of changes in soil types; in-situ, the transition between materials may be gradual. Based on the results of the borings, subsurface conditions on the project site can be generalized as follows: Material Description Approximate Depth to Bottom of Stratum (feet) Consistency/Density/Hardness Existing asphalt pavement About 2 to 91/2 inches except in Boring No. 3-1. -- Existing aggregate base course About 3 to 4 inches in Boring Nos. 1- 2 and 1-3 only. -- Existing concrete slab About 3 inches in Boring No. 2-2 only. -- Fill materials consisting of lean clay, sand, silt, and gravel About 1½ to 5 feet below existing site grades in Boring Nos. 1-1, 1-2, 2-1, 2-2, 2-3, 3-2, and 3-3 only. -- Sandy lean clay About 9 to 20½ feet below existing site grades. Medium stiff to very stiff Well-graded sand with silt and gravel To the maximum depth of exploration of about 20½ feet in all borings except Boring No. 2-1, 2-2, and 2-3. Very loose to dense Geotechnical Engineering Report Arthur Ditch Bridge Replacement (RFP 7525) Ŷ Fort Collins, Colorado December 3, 2013 Ŷ Terracon Project No. 20135038 Responsive Ŷ Resourceful Ŷ Reliable 3 3.2 Laboratory Testing Representative soil samples were selected for swell-consolidation testing and exhibited 0.6 to 1.1 percent compression when wetted. Samples of site soils selected for plasticity testing exhibited low to medium plasticity with liquid limits ranging from 25 to 43 and plasticity indices ranging from 5 to 21. Corrosivity testing was not completed at the time we prepared this report. Once this testing has been completed, we will provide test results under separate cover. Laboratory test results are presented in Appendix B. 3.3 Groundwater The boreholes were observed while drilling and after completion for the presence and level of groundwater. The water levels observed in the boreholes are noted on the attached boring logs, and are summarized below: Boring Number Depth to groundwater while drilling, ft. Elevation of groundwater while drilling, ft. 1-1 17 4984.6 1-2 18 4984.6 1-3 17 4984.4 2-1 17 4985.1 2-2 16 4986.4 2-3 16 4986.0 3-1 13 4989.0 3-2 13 4989.4 3-3 13.5 4988.7 These observations represent groundwater conditions at the time of the field exploration, and may not be indicative of other times or at other locations. Groundwater levels can be expected to fluctuate with varying seasonal and weather conditions, and other factors. Groundwater level fluctuations occur due to seasonal variations, amount of rainfall, runoff and other factors not evident at the time the borings were performed. Therefore, groundwater levels during construction or at other times in the life of the culverts may be higher or lower than the levels indicated on the boring logs. The possibility of groundwater level fluctuations should be considered when developing the design and construction plans for the project. Geotechnical Engineering Report Arthur Ditch Bridge Replacement (RFP 7525) Ŷ Fort Collins, Colorado December 3, 2013 Ŷ Terracon Project No. 20135038 Responsive Ŷ Resourceful Ŷ Reliable 4 4.0 RECOMMENDATIONS FOR DESIGN AND CONSTRUCTION 4.1 Geotechnical Considerations Based on subsurface conditions encountered in the borings, the site appears suitable for the proposed construction from a geotechnical point of view provided certain precautions and design and construction recommendations described in this report are followed. We have identified geotechnical conditions that could impact design and construction of the proposed concrete box culverts and other site improvements. 4.1.1 Existing, Undocumented Fill As previously noted, existing undocumented fills were encountered to depths up to about 5 feet in the borings drilled at the site. However, we believe deeper fills are present at all three locations and the fills were placed as part of the construction of the existing channels. We do not possess any information regarding whether the fill was placed under the observation of a geotechnical engineer. Support of concrete box culverts on or above existing fill soils is discussed in this report. However, even with the recommended construction testing services, there is an inherent risk for the owner that compressible fill or unsuitable material within or buried by the fill will not be discovered. This risk of unforeseen conditions cannot be eliminated without completely removing the existing fill, but can be reduced by performing additional testing and evaluation. Demolition and removal of the existing box culverts, as well as excavations for the proposed box culverts, will likely result in complete removal of existing fill below the new structures. However, we recommend complete removal of existing fill during demolition and recompacting below repair elements such as pavements, concrete flatwork, curb, and gutter. While we did not encounter existing fill below a depth of about 5 feet within our test borings, it is possible that fill may be encountered at greater depths during site excavations. We recommend that foundation excavations be observed on a full-time basis during construction and the project team considers budget contingencies for unanticipated fill removal and replacement. 4.1.2 Shallow Groundwater As previously stated, groundwater was measured at depths ranging from about 13 to 18 feet below existing site grades. Terracon recommends maintaining a separation of at least 3 feet between the bottom of proposed concrete box culvert foundations and measured groundwater levels. It is also possible and likely that groundwater levels below this site may rise. Our experience in the area suggests a rise in groundwater levels of 3 to 5 feet should be expected during spring runoff. Geotechnical Engineering Report Arthur Ditch Bridge Replacement (RFP 7525) Ŷ Fort Collins, Colorado December 3, 2013 Ŷ Terracon Project No. 20135038 Responsive Ŷ Resourceful Ŷ Reliable 5 4.1.3 Expansive/Collapsible Soils Laboratory testing indicates the on-site sandy lean clay soils, near the anticipated foundation depths, exhibited 0.6 to 1.1 percent compression upon wetting at the samples in-situ moisture content. However, it is our opinion these materials will exhibit a higher expansive potential if the clays undergo a significant loss of moisture. This report provides recommendations to help mitigate the effects of soil shrinkage and expansion. However, even if these procedures are followed, some movement and cracking in the box culverts and surrounding pavements/concrete flatwork should be anticipated. The severity of cracking and other damage such as uneven culvert foundations and cracked pavements/concrete flatwork will probably increase if any modification of the site results in excessive wetting or drying of the on-site clays. Eliminating the risk of movement and distress is generally not be feasible, but it may be possible to further reduce the risk of movement if significantly more expensive measures are used during construction. It is imperative the recommendations described in section 4.2.7 Grading and Drainage of this report be followed to reduce movement. 4.2 Earthwork The following presents recommendations for site preparation, demolition, excavation, subgrade preparation and placement of engineered fills on the project. All earthwork on the project should be observed and evaluated by Terracon on a full-time basis. The evaluation of earthwork should include observation of over-excavation operations, testing of engineered fills, subgrade preparation, subgrade stabilization, and other geotechnical conditions exposed during the construction of the project. 4.2.1 Site Preparation Prior to placing any fill, strip and remove existing vegetation, existing pavements, the undocumented existing fill, and any other deleterious materials from the proposed construction areas. Stripped organic materials should be wasted from the site or used to re-vegetate landscaped areas after completion of grading operations. Prior to the placement of fills, the site should be graded to create a relatively level surface to receive fill, and to provide for a relatively uniform thickness of fill beneath proposed structures. If fill is placed in areas of the site where existing slopes are steeper than 5:1 (horizontal:vertical), the area should be benched to reduce the potential for slippage between existing slopes and fills. Benches should be wide enough to accommodate compaction and earth moving equipment, and to allow placement of horizontal lifts of fill. Geotechnical Engineering Report Arthur Ditch Bridge Replacement (RFP 7525) Ŷ Fort Collins, Colorado December 3, 2013 Ŷ Terracon Project No. 20135038 Responsive Ŷ Resourceful Ŷ Reliable 6 4.2.2 Demolition Demolition of the existing concrete box culverts should include complete removal of all foundation systems, below-grade structural elements, pavements, and exterior flat work within the proposed construction areas. This should include removal of any utilities to be abandoned along with any loose utility trench backfill or loose backfill found adjacent to existing foundations. All materials derived from the demolition of existing structures and pavements should be removed from the site. Consideration could be given to re-using the asphalt and concrete provided the materials are processed and uniformly blended with the on-site soils. Asphalt and/or concrete materials should be processed to a maximum size of 2-inches and blended at a ratio of 30 percent asphalt/concrete to 70 percent of on-site soils. 4.2.3 Excavation It is anticipated that excavations for the proposed construction can be accomplished with conventional earthmoving equipment. Excavations into the on-site soils may encounter weak and/or nearly saturated soil conditions with possible caving conditions. The soils to be excavated can vary significantly across the site as their classifications are based solely on the materials encountered in widely-spaced exploratory test borings. The contractor should verify that similar conditions exist throughout the proposed area of excavation. If different subsurface conditions are encountered at the time of construction, the actual conditions should be evaluated to determine any excavation modifications necessary to maintain safe conditions. Although evidence of underground facilities such as septic tanks, vaults, and basements was not observed during the site reconnaissance, such features could be encountered during construction. If unexpected fills or underground facilities are encountered, such features should be removed and the excavation thoroughly cleaned prior to backfill placement and/or construction. Any over-excavation that extends below the bottom of foundation elevation should extend laterally beyond all edges of the foundations at least 8 inches per foot of over-excavation depth below the culvert base elevation. The over-excavation should be backfilled to the culvert base elevation in accordance with the recommendations presented in this report. Depending upon depth of excavation and seasonal conditions, surface water infiltration and/or groundwater may be encountered in excavations on the site. It is anticipated that pumping from sumps may be utilized to control water within excavations. Well points may be required for significant groundwater flow, or where excavations penetrate groundwater to a significant depth. The subgrade soil conditions should be evaluated during the excavation process and the stability of the soils determined at that time by the contractors’ Competent Person. Slope inclinations flatter than the OSHA maximum values may have to be used. The individual contractor(s) should be made responsible for designing and constructing stable, temporary excavations as required to Geotechnical Engineering Report Arthur Ditch Bridge Replacement (RFP 7525) Ŷ Fort Collins, Colorado December 3, 2013 Ŷ Terracon Project No. 20135038 Responsive Ŷ Resourceful Ŷ Reliable 7 maintain stability of both the excavation sides and bottom. All excavations should be sloped or shored in the interest of safety following local, and federal regulations, including current OSHA excavation and trench safety standards. As a safety measure, it is recommended that all vehicles and soil piles be kept a minimum lateral distance from the crest of the slope equal to the slope height. The exposed slope face should be protected against the elements 4.2.4 Subgrade Preparation After the existing fill, existing concrete box culverts, and deleterious materials have been removed from the construction areas, the top 8 inches of the exposed ground surface should be scarified, moisture conditioned, and recompacted to at least 95 percent of the maximum dry unit weight as determined by ASTM D698 before any new fill/bedding or foundation is placed. If pockets of soft, loose, or otherwise unsuitable materials are encountered at the bottom of the excavations, the proposed culvert elevations may be reestablished by over-excavating the unsuitable soils and backfilling with compacted engineered fill. After the bottom of the excavation has been compacted, engineered fill can be placed to bring the culvert subgrade to the desired grade. Engineered fill should be placed in accordance with the recommendations presented in subsequent sections of this report. The stability of the subgrade may be affected by precipitation, repetitive construction traffic or other factors. If unstable conditions develop, workability may be improved by scarifying and drying. Alternatively, over-excavation of wet zones and replacement with granular materials may be used, or crushed gravel and/or rock can be tracked or “crowded” into the unstable surface soil until a stable working surface is attained. Use of fly ash or geotextiles could also be considered as a stabilization technique. Laboratory evaluation is recommended to determine the effect of chemical stabilization on subgrade soils prior to construction. Lightweight excavation equipment may also be used to reduce subgrade pumping. 4.2.5 Fill Materials and Placement The on-site soils or approved granular and low plasticity cohesive imported materials may be used as fill material. The soil removed from this site that is free of organic or objectionable materials, as defined by a field technician who is qualified in soil material identification and compaction procedures, can be re-used as fill for the replacement concrete box culverts. It should be noted that on-site soils may require reworking to adjust the moisture content to meet the compaction criteria. Geotechnical Engineering Report Arthur Ditch Bridge Replacement (RFP 7525) Ŷ Fort Collins, Colorado December 3, 2013 Ŷ Terracon Project No. 20135038 Responsive Ŷ Resourceful Ŷ Reliable 8 Imported soils (if required) should meet the following material property requirements: Gradation Percent finer by weight (ASTM C136) 4” 100 3” 70-100 No. 4 Sieve 50-100 No. 200 Sieve 10-50 Soil Properties Value Liquid Limit 30 (max.) Plastic Limit 15 (max.) Maximum Expansive Potential (%) Non-expansive1 1. Measured on a sample compacted to approximately 95 percent of the maximum dry unit weight as determined by ASTM D698 at optimum moisture content. The sample is confined under a 100 psf surcharge and submerged. 4.2.6 Compaction Requirements Engineered fill should be placed and compacted in horizontal lifts, using equipment and procedures that will produce recommended moisture contents and densities throughout the lift. Item Description Fill lift thickness 9 inches or less in loose thickness when heavy, self- propelled compaction equipment is used 4 to 6 inches in loose thickness when hand-guided equipment (i.e. jumping jack or plate compactor) is used Minimum compaction requirements 95 percent of the maximum dry unit weight as determined by ASTM D698 Moisture content cohesive soil (clay) -1 to +3 % of the optimum moisture content Moisture content cohesionless soil (sand) -3 to +2 % of the optimum moisture content 1. We recommend engineered fill be tested for moisture content and compaction during placement. Should the results of the in-place density tests indicate the specified moisture or compaction limits have not been met, the area represented by the test should be reworked and retested as required until the specified moisture and compaction requirements are achieved. 2. Specifically, moisture levels should be maintained low enough to allow for satisfactory compaction to be achieved without the fill material pumping when proofrolled. 3. Moisture conditioned clay materials should not be allowed to dry out. A loss of moisture within these materials could result in an increase in the material’s expansive potential. Subsequent wetting of these materials could result in undesirable movement. Geotechnical Engineering Report Arthur Ditch Bridge Replacement (RFP 7525) Ŷ Fort Collins, Colorado December 3, 2013 Ŷ Terracon Project No. 20135038 Responsive Ŷ Resourceful Ŷ Reliable 9 4.2.7 Grading and Drainage All grades must be adjusted to provide effective drainage away from the proposed replacement concrete box culverts and existing site improvements during construction and maintained throughout the life of the proposed project. Infiltration of water into foundation excavations must be prevented during construction. Water permitted to pond near or adjacent to the perimeter of the proposed box culverts and replacement pavement/concrete flatwork repairs (either during or post-construction) can result in significantly higher soil movements than those discussed in this report. As a result, any estimations of potential movement described in this report cannot be relied upon if positive drainage is not obtained and maintained, and water is allowed to infiltrate the fill and/or subgrade. Backfill against foundations and box culvert walls should be properly compacted and free of all construction debris to reduce the possibility of moisture infiltration. 4.2.8 Corrosion Protection Testing for corrosivity potential was not completed at the time this report was prepared. Once we have completed the testing we will submit a supplemental report with the test results and recommendations for corrosive potential. 4.3 Foundations The proposed replacement box culverts can be constructed on a reinforced concrete slab within a properly bedded excavation underlain by stable, prepared subgrade consisting of either properly compacted subgrade or engineered fill. Conventional-type spread footing foundations may also be used to support other related structures. If pre-cast box culverts are selected, the base of the structure will constitute a reinforced concrete slab; no foundation will be necessary. Design recommendations for box culvert foundations are presented in the following paragraphs. Geotechnical Engineering Report Arthur Ditch Bridge Replacement (RFP 7525) Ŷ Fort Collins, Colorado December 3, 2013 Ŷ Terracon Project No. 20135038 Responsive Ŷ Resourceful Ŷ Reliable 10 4.3.1 Box Culvert - Design Recommendations Description Value Maximum allowable bearing pressure 1 On-site sandy lean clay: 2,000 psf Imported fill: 3,000 psf Lateral earth pressure coefficients 2 On-site sandy lean clay: Active, Ka = 0.41 Passive, Kp = 2.46 At-rest, Ko = 0.57 Imported fill: Active, Ka = 0.27 Passive, Kp = 3.69 At-rest, Ko = 0.42 Sliding coefficient 2 On-site sandy lean clay: µ = 0.37 Imported fill: µ =0.56 Moist soil unit weight On-site sandy lean clay: ܵ = 120 pcf Imported fill: ܵ =130 pcf Minimum embedment depth below finished grade 3 30 inches 1. The recommended maximum allowable bearing pressure assumes any unsuitable fill or soft soils, if encountered, will be over-excavated and replaced with properly compacted engineered fill. 2. The lateral earth pressure coefficients and sliding coefficients are ultimate values and do not include a factor of safety. The box culvert designer should include the appropriate factors of safety. 3. For frost protection and to reduce the effects of seasonal moisture variations in the subgrade soils. The minimum embedment depth is relative to lowest adjacent grade. For structural design of concrete slabs-on-grade, a modulus of subgrade reaction of 100 pounds per cubic inch (pci) may be used for foundations supported on the existing cohesive type soils, and 200 psi if placed on at least 1-foot of granular imported structural fill material. Terracon should be retained to observe the foundation excavation and subgrade stabilization (if necessary) prior to construction. If the soil conditions encountered differ significantly from those presented in this report, supplemental recommendations will be required. Geotechnical Engineering Report Arthur Ditch Bridge Replacement (RFP 7525) Ŷ Fort Collins, Colorado December 3, 2013 Ŷ Terracon Project No. 20135038 Responsive Ŷ Resourceful Ŷ Reliable 11 4.3.2 Box Culverts - Bedding Recommendations To provide for proper support of box culverts, the site must first be prepared. Box culvert installations should be done by an experienced contractor who understands the importance of bedding the structure properly. The bedding under the box culverts must be able to support the full load of the installed box culvert, its contents, and the loading above the box culvert. The surface and subsurface water should be controlled so dry conditions are available during excavation and site preparation. Furthermore, during and after installation, dewatering methods must be used to prevent the migration of bedding materials and to prevent fines from getting into the groove. Any unsuitable or unstable materials below the plan foundation should be removed. Rocks within 6 inches of the box bottom should be removed. After the appropriate excavations are performed and the subgrade is judged stable, the box culverts should be placed or constructed on compacted granular backfill to the specified line and grades. Terracon recommends a bedding thickness of at least 6 inches. The bedding should consist of well-graded crushed stone or crushed gravel meeting the requirements of ASTM C33, gradation 67 (3/4-inch to No. 4) and should be installed and compacted to provide uniform support for the full length and width of each box culvert section. A 2-inch minimum thickness leveling course of fine granular base material can be used as required to achieve a level bedding surface. The final grading for the bedding should be done with a laser or level and grade stakes. For the final grading, the granular material should be screeded using a screed board as long as the width of the outside span of the box. If properly done, the final grading will allow an easier installation while setting the box culvert sections. Improper bedding could prevent the tongue of the box from being properly started into the groove. It is very important that time be spent to ensure the box culvert bedding preparation is done correctly. 4.4 Seismic Considerations Code Used Site Classification 2012 International Building Code (IBC) 1 D 2 1. In general accordance with the 2012 International Building Code, Table 1613.5.2. 2. The 2012 International Building Code (IBC) requires a site soil profile determination extending a depth of 100 feet for seismic site classification. The current scope requested does not include the required 100 foot soil profile determination. The borings completed for this project extended to a maximum depth of about 20½ feet and this seismic site class definition considers that similar soil conditions exist below the maximum depth of the subsurface exploration. Additional exploration to deeper depths could be performed to confirm the conditions below the current depth of exploration. Alternatively, a geophysical exploration could be utilized in order to attempt to justify a more favorable seismic site class. However, we believe a higher seismic site class for this site is unlikely. Geotechnical Engineering Report Arthur Ditch Bridge Replacement (RFP 7525) Ŷ Fort Collins, Colorado December 3, 2013 Ŷ Terracon Project No. 20135038 Responsive Ŷ Resourceful Ŷ Reliable 12 4.5 Lateral Earth Pressures Reinforced concrete walls with unbalanced backfill levels on opposite sides should be designed for earth pressures at least equal to those indicated in the following table. Earth pressures will be influenced by structural design of the walls, conditions of wall restraint, methods of construction and/or compaction and the strength of the materials being restrained. Two wall restraint conditions are shown. Active earth pressure is commonly used for design of free-standing cantilever retaining walls and assumes wall movement. The "at-rest" condition assumes no wall movement. The recommended design lateral earth pressures do not include a factor of safety and do not provide for possible hydrostatic pressure on the walls. EARTH PRESSURE COEFFICIENTS Earth Pressure Conditions Coefficient for Backfill Type Equivalent Fluid Density (pcf) Surcharge Pressure, p1 (psf) Earth Pressure, p2 (psf) Active (Ka) Imported fill - 0.27 On-site sandy clay - 0.41 35 49 (0.27)S (0.41)S (35)H (49)H At-Rest (Ko) Imported fill - 0.42 On-site sandy clay - 0.57 55 68 (0.42)S (0.57)S (55)H (68)H Passive (Kp) Imported fill – 3.69 On-site sandy clay – 2.46 480 295 --- --- --- --- Geotechnical Engineering Report Arthur Ditch Bridge Replacement (RFP 7525) Ŷ Fort Collins, Colorado December 3, 2013 Ŷ Terracon Project No. 20135038 Responsive Ŷ Resourceful Ŷ Reliable 13 Applicable conditions to the above include: „ For active earth pressure, wall must rotate about base, with top lateral movements of about 0.002 H to 0.004 H, where H is wall height; „ For passive earth pressure to develop, wall must move horizontally to mobilize resistance; „ Uniform surcharge, where S is surcharge pressure; „ In-situ soil backfill weight a maximum of 120 pcf and imported soil backfill weight a maximum of 130 pcf; „ Horizontal backfill, compacted between 95 and 98 percent of maximum dry unit weight as determined by ASTM D698; „ Loading from heavy compaction equipment not included; „ No hydrostatic pressures acting on wall; „ No dynamic loading; „ No safety factor included in soil parameters; and „ Ignore passive pressure in frost zone. To control hydrostatic pressure behind the wall we recommend that a drain be installed at the foundation wall with a collection pipe leading to a reliable discharge. If this is not possible, then combined hydrostatic and lateral earth pressures should be calculated for sandy lean clay backfill using an equivalent fluid weighing 90 and 100 pcf for active and at-rest conditions, respectively. For granular backfill, an equivalent fluid weighing 85 and 90 pcf should be used for active and at-rest, respectively. These pressures do not include the influence of surcharge, equipment or floor loading, which should be added. 5.0 GENERAL COMMENTS Terracon should be retained to review the final design plans and specifications so comments can be made regarding interpretation and implementation of our geotechnical recommendations in the design and specifications. Terracon also should be retained to provide observation and testing services during grading, excavation, foundation construction and other earth-related construction phases of the project. The analysis and recommendations presented in this report are based upon the data obtained from the borings performed at the indicated locations and from other information discussed in this report. This report does not reflect variations that may occur between borings, across the site, or due to the modifying effects of construction or weather. The nature and extent of such variations may not become evident until during or after construction. If variations appear, we should be immediately notified so that further evaluation and supplemental recommendations can be provided. The scope of services for this project does not include either specifically or by implication any environmental or biological (e.g., mold, fungi, bacteria) assessment of the site or identification or prevention of pollutants, hazardous materials or conditions. If the owner is concerned about the potential for such contamination or pollution, other studies should be undertaken. Geotechnical Engineering Report Arthur Ditch Bridge Replacement (RFP 7525) Ŷ Fort Collins, Colorado December 3, 2013 Ŷ Terracon Project No. 20135038 Responsive Ŷ Resourceful Ŷ Reliable 14 This report has been prepared for the exclusive use of our client for specific application to the project discussed and has been prepared in accordance with generally accepted geotechnical engineering practices. No warranties, either express or implied, are intended or made. Site safety, excavation support, and dewatering requirements are the responsibility of others. In the event that changes in the nature, design, or location of the project as described in this report are planned, the conclusions and recommendations contained in this report shall not be considered valid unless Terracon reviews the changes and either verifies or modifies the conclusions of this report in writing. APPENDIX A FIELD EXPLORATION SITE LOCATION MAP A-1 20135038 11/5/2013 EDB BCJ EDB EDB Not to scale Project Manager: Drawn by: Checked by: Approved by: Project No. Scale: File Name: Date: Exhibit Project Site Arthur Ditch Bridge Replacement (RFP 7525) 1901Colorado Sharp Point Drive, Suite C Fort Collins, Colorado 80525 Fort Collins, PH. (970) 484-0359 FAX. (970) 484-0454 BORING LOCATION PLAN 1901 Sharp Point Drive, Suite C Fort Collins, Colorado 80525 A-2 PH. (970) 484-0359 FAX. (970) 484-0454 20125038 11/19/2013 EDB BCJ EDB EDB 1” = 80’ Project Manager: Drawn by: Checked by: Approved by: Project No. Scale: File Name: Date: DIAGRAM IS FOR GENERAL LOCATION Exhibit ONLY, AND IS NOT INTENDED FOR CONSTRUCTION PURPOSES 0’ 40’ 80’ APPROXIMATE SCALE Approximate Boring Location 1-1 Arthur Ditch Bridge Replacement (RFP 7525) Northeast of the Intersection of Canyon Ave. and West Mulberry St. Fort Collins, Colorado LEGEND 1-1 1-2 1-3 West Mulberry Street BORING LOCATION PLAN 1901 Sharp Point Drive, Suite C Fort Collins, Colorado 80525 A-3 PH. (970) 484-0359 FAX. (970) 484-0454 20125038 11/19/2013 EDB BCJ EDB EDB 1” = 80’ Project Manager: Drawn by: Checked by: Approved by: Project No. Scale: File Name: Date: DIAGRAM IS FOR GENERAL LOCATION Exhibit ONLY, AND IS NOT INTENDED FOR CONSTRUCTION PURPOSES 0’ 40’ 80’ APPROXIMATE SCALE Approximate Boring Location 2-1 Arthur Ditch Bridge Replacement (RFP 7525) Intersection of South Whitcomb St. and West Oak St. Fort Collins, Colorado LEGEND 2-1 2-2 2-3 South Whitcomb Street West Oak Street BORING LOCATION PLAN 1901 Sharp Point Drive, Suite C Fort Collins, Colorado 80525 A-4 PH. (970) 484-0359 FAX. (970) 484-0454 20125038 11/19/2013 EDB BCJ EDB EDB 1” = 80’ Project Manager: Drawn by: Checked by: Approved by: Project No. Scale: File Name: Date: DIAGRAM IS FOR GENERAL LOCATION Exhibit ONLY, AND IS NOT INTENDED FOR CONSTRUCTION PURPOSES 0’ 40’ 80’ APPROXIMATE SCALE Approximate Boring Location 3-1 Arthur Ditch Bridge Replacement (RFP 7525) Intersection of South Loomis Ave. and West Olive St. Fort Collins, Colorado LEGEND 3-1 3-2 3-3 South Loomis Avenue West Olive Street Geotechnical Engineering Report Arthur Ditch Bridge Replacement (RFP 7525) Ŷ Fort Collins, Colorado December 3, 2013 Ŷ Terracon Project No. 20135038 Responsive Ŷ Resourceful Ŷ Reliable Exhibit A-5 Field Exploration Description The locations of borings were selected by the project team during an on-site meeting. The borings were located in the field by measuring from existing site features. The ground surface elevation was surveyed at each boring by the City of Fort Collins. The borings were drilled with a CME-45 truck-mounted rotary drill rig with solid-stem augers. During the drilling operations, lithologic logs of the borings were recorded by the field engineer. Disturbed samples were obtained at selected intervals utilizing a 2-inch outside diameter split- spoon sampler and a 3-inch outside diameter ring-barrel sampler. Penetration resistance values were recorded in a manner similar to the standard penetration test (SPT). This test consists of driving the sampler into the ground with a 140-pound hammer free-falling through a distance of 30 inches. The number of blows required to advance the ring-barrel sampler 12 inches (18 inches for standard split-spoon samplers, final 12 inches are recorded) or the interval indicated, is recorded as a standard penetration resistance value (N-value). The blow count values are indicated on the boring logs at the respective sample depths. Ring-barrel sample blow counts are not considered N-values. A CME automatic SPT hammer was used to advance the samplers in the borings performed on this site. A greater efficiency is typically achieved with the automatic hammer compared to the conventional safety hammer operated with a cathead and rope. Published correlations between the SPT values and soil properties are based on the lower efficiency cathead and rope method. This higher efficiency affects the standard penetration resistance blow count value by increasing the penetration per hammer blow over what would be obtained using the cathead and rope method. The effect of the automatic hammer's efficiency has been considered in the interpretation and analysis of the subsurface information for this report. The standard penetration test provides a reasonable indication of the in-place density of sandy type materials, but only provides an indication of the relative stiffness of cohesive materials since the blow count in these soils may be affected by the moisture content of the soil. In addition, considerable care should be exercised in interpreting the N-values in gravelly soils, particularly where the size of the gravel particle exceeds the inside diameter of the sampler. Groundwater measurements were obtained in the borings at the time of site exploration. After completion of drilling, the borings were backfilled with auger cuttings, sand (if needed), and asphalt patch (if needed). Some settlement of the backfill and/or patch may occur and should be repaired as soon as possible. A-3 A-3 A-3 A-4 A-4 A-4 APPENDIX B LABORATORY TESTING Geotechnical Engineering Report Arthur Ditch Bridge Replacement (RFP 7525) Ŷ Fort Collins, Colorado December 3, 2013 Ŷ Terracon Project No. 20135038 Responsive Ŷ Resourceful Ŷ Reliable Exhibit B-1 Laboratory Testing Description The soil samples retrieved during the field exploration were returned to the laboratory for observation by the project geotechnical engineer. At that time, the field descriptions were reviewed and an applicable laboratory testing program was formulated to determine engineering properties of the subsurface materials. Laboratory tests were conducted on selected soil samples. The results of these tests are presented on the boring logs and in this appendix. The test results were used for the geotechnical engineering analyses, and the development of foundation and earthwork recommendations. The laboratory tests were performed in general accordance with applicable locally accepted standards. Soil samples were classified in general accordance with the Unified Soil Classification System described in Appendix C. „ Water content „ Plasticity index „ Grain-size distribution „ Consolidation/swell „ Dry density 0 10 20 30 40 50 60 0 20 40 60 80 100 CL or OL CH or OH ML or OL MH or OH PL PI 9.0 9.0 9.0 4.0 9.0 9.0 Boring ID Depth Description SANDY LEAN CLAY (CL) SILTY SAND SANDY LEAN CLAY SILTY, CLAYEY SAND SANDY LEAN CLAY SANDY LEAN CLAY CL SM CL SC-SM CL CL Fines P L A S T I C I T Y I N D E X LIQUID LIMIT "U" Line "A" Line 35 43 41 25 38 34 17 34 20 20 0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 100 10 1 0.1 0.01 0.001 6 16 20 30 40 50 1.5 6 200 810 72.9 44.8 60.9 14.5 55.0 0.9 1.6 2.3 0.0 7.3 14 LL PL PI %Silt %Clay 1 4 3/4 1/2 60 fine U.S. SIEVE OPENING IN INCHES U.S. SIEVE NUMBERS HYDROMETER 17 34 20 20 18 18 9 21 5 20 D100 Cc Cu SILT OR CLAY 4 D30 D10 %Gravel %Sand 0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 100 10 1 0.1 0.01 0.001 6 16 20 30 40 50 1.5 6 200 810 0.9 62.0 14 LL PL PI %Silt %Clay 1 4 3/4 1/2 60 fine U.S. SIEVE OPENING IN INCHES U.S. SIEVE NUMBERS HYDROMETER 16 18 D100 Cc Cu SILT OR CLAY 4 D30 D10 %Gravel %Sand 3-2 SANDY LEAN CLAY(CL) 34 3-2 9.5 9.0 GRAIN SIZE IN MILLIMETERS PERCENT FINER BY WEIGHT coarse fine 3/8 3 100 3 2 140 COBBLES GRAVEL SAND USCS Classification 37.1 D60 coarse medium 9.0 Boring ID Depth Boring ID Depth GRAIN SIZE DISTRIBUTION -8 -7 -6 -5 -4 -3 -2 -1 0 1 2 100 1,000 10,000 AXIAL STRAIN, % PRESSURE, psf SWELL CONSOLIDATION TEST ASTM D4546 NOTES: Sample exhibited 0.6 percent compression upon wetting under an applied pressure of 1,000 psf. 1901 Sharp Point Drive, Suite C Fort Collins, Colorado PROJECT NUMBER: 20135038 PROJECT: Aurthur Ditch Bridge Replacement SITE: Three intersections Fort Collins, Colorado CLIENT: J-U-B Engineers, Inc. Fort Collins, Colorado EXHIBIT: B-5 Specimen Identification 9.0 ft Classification , pcf 1-3 81 26 WC, % SANDY LEAN CLAY (CL) LABORATORY TESTS ARE NOT VALID IF SEPARATED FROM ORIGINAL REPORT. TC_CONSOL_STRAIN-USCS 20135038.GPJ TERRACON2012.GDT 12/3/13 -8 -7 -6 -5 -4 -3 -2 -1 0 1 2 100 1,000 10,000 AXIAL STRAIN, % PRESSURE, psf SWELL CONSOLIDATION TEST ASTM D4546 NOTES: Sample exhibited 0.7 percent compression upon wetting under an applied pressure of 1,000 psf. 1901 Sharp Point Drive, Suite C Fort Collins, Colorado PROJECT NUMBER: 20135038 PROJECT: Aurthur Ditch Bridge Replacement SITE: Three intersections Fort Collins, Colorado CLIENT: J-U-B Engineers, Inc. Fort Collins, Colorado EXHIBIT: B-6 Specimen Identification 9.0 ft Classification , pcf 2-1 94 24 WC, % SANDY LEAN CLAY(CL) LABORATORY TESTS ARE NOT VALID IF SEPARATED FROM ORIGINAL REPORT. TC_CONSOL_STRAIN-USCS 20135038.GPJ TERRACON2012.GDT 12/3/13 -8 -7 -6 -5 -4 -3 -2 -1 0 1 2 100 1,000 10,000 AXIAL STRAIN, % PRESSURE, psf SWELL CONSOLIDATION TEST ASTM D4546 NOTES: Sample exhibited 1.1 percent compression upon wetting under an applied pressure of 1,000 psf. 1901 Sharp Point Drive, Suite C Fort Collins, Colorado PROJECT NUMBER: 20135038 PROJECT: Aurthur Ditch Bridge Replacement SITE: Three intersections Fort Collins, Colorado CLIENT: J-U-B Engineers, Inc. Fort Collins, Colorado EXHIBIT: B-7 Specimen Identification 9.0 ft Classification , pcf 3-2 99 19 WC, % SANDY LEAN CLAY(CL) LABORATORY TESTS ARE NOT VALID IF SEPARATED FROM ORIGINAL REPORT. TC_CONSOL_STRAIN-USCS 20135038.GPJ TERRACON2012.GDT 12/3/13 APPENDIX C SUPPORTING DOCUMENTS Exhibit: C-1 Unconfined Compressive Strength Qu, (tsf) 0.25 to 0.50 0.50 to 1.00 1.00 to 2.00 2.00 to 4.00 > 4.00 less than 0.25 Non-plastic Low Medium High DESCRIPTION OF SYMBOLS AND ABBREVIATIONS Hand Penetrometer Torvane Dynamic Cone Penetrometer Photo-Ionization Detector Organic Vapor Analyzer SAMPLING WATER LEVEL FIELD TESTS (HP) (T) (DCP) (PID) (OVA) GENERAL NOTES Over 12 in. (300 mm) 12 in. to 3 in. (300mm to 75mm) 3 in. to #4 sieve (75mm to 4.75 mm) #4 to #200 sieve (4.75mm to 0.075mm Passing #200 sieve (0.075mm) Particle Size < 5 5 - 12 > 12 Percent of Dry Weight Descriptive Term(s) of other constituents RELATIVE PROPORTIONS OF FINES 0 1 - 10 11 - 30 > 30 Plasticity Index Soil classification is based on the Unified Soil Classification System. Coarse Grained Soils have more than 50% of their dry weight retained on a #200 sieve; their principal descriptors are: boulders, cobbles, gravel or sand. Fine Grained Soils have less than 50% of their dry weight retained on a #200 sieve; they are principally described as clays if they are plastic, and silts if they are slightly plastic or non-plastic. Major constituents may be added as modifiers and minor constituents may be added according to the relative proportions based on grain size. In addition to gradation, coarse-grained soils are defined on the basis of their in-place relative density and fine-grained soils on the basis of their consistency. LOCATION AND ELEVATION NOTES Percent of Dry Weight Major Component of Sample Trace With UNIFIED SOIL CLASSIFICATION SYSTEM Exhibit C-2 Criteria for Assigning Group Symbols and Group Names Using Laboratory Tests A Soil Classification Group Symbol Group Name B Coarse Grained Soils: More than 50% retained on No. 200 sieve Gravels: More than 50% of coarse fraction retained on No. 4 sieve Clean Gravels: Less than 5% fines C Cu  4 and 1  Cc  3 E GW Well-graded gravel F Cu  4 and/or 1  Cc  3 E GP Poorly graded gravel F Gravels with Fines: More than 12% fines C Fines classify as ML or MH GM Silty gravel F,G,H Fines classify as CL or CH GC Clayey gravel F,G,H Sands: 50% or more of coarse fraction passes No. 4 sieve Clean Sands: Less than 5% fines D Cu  6 and 1  Cc  3 E SW Well-graded sand I Cu  6 and/or 1  Cc  3 E SP Poorly graded sand I Sands with Fines: More than 12% fines D Fines classify as ML or MH SM Silty sand G,H,I Fines classify as CL or CH SC Clayey sand G,H,I Fine-Grained Soils: 50% or more passes the No. 200 sieve Silts and Clays: Liquid limit less than 50 Inorganic: PI  7 and plots on or above “A” line J CL Lean clay K,L,M PI  4 or plots below “A” line J ML Silt K,L,M Organic: Liquid limit - oven dried  0.75 OL Organic clay K,L,M,N Liquid limit - not dried Organic silt K,L,M,O Silts and Clays: Liquid limit 50 or more Inorganic: PI plots on or above “A” line CH Fat clay K,L,M PI plots below “A” line MH Elastic Silt K,L,M Organic: Liquid limit - oven dried  0.75 OH Organic clay K,L,M,P Liquid limit - not dried Organic silt K,L,M,Q Highly organic soils: Primarily organic matter, dark in color, and organic odor PT Peat A Based on the material passing the 3-inch (75-mm) sieve B If field sample contained cobbles or boulders, or both, add “with cobbles or boulders, or both” to group name. Exhibit C-3 LABORATORY TEST SIGNIFICANCE AND PURPOSE Test Significance Purpose California Bearing Ratio Used to evaluate the potential strength of subgrade soil, subbase, and base course material, including recycled materials for use in road and airfield pavements. Pavement Thickness Design Consolidation Used to develop an estimate of both the rate and amount of both differential and total settlement of a structure. Foundation Design Direct Shear Used to determine the consolidated drained shear strength of soil or rock. Bearing Capacity, Foundation Design, and Slope Stability Dry Density Used to determine the in-place density of natural, inorganic, fine-grained soils. Index Property Soil Behavior Expansion Used to measure the expansive potential of fine-grained soil and to provide a basis for swell potential classification. Foundation and Slab Design Gradation Used for the quantitative determination of the distribution of particle sizes in soil. Soil Classification Liquid & Plastic Limit, Plasticity Index Used as an integral part of engineering classification systems to characterize the fine-grained fraction of soils, and to specify the fine-grained fraction of construction materials. Soil Classification Permeability Used to determine the capacity of soil or rock to conduct a liquid or gas. Groundwater Flow Analysis pH Used to determine the degree of acidity or alkalinity of a soil. Corrosion Potential Resistivity Used to indicate the relative ability of a soil medium to carry electrical currents. Corrosion Potential R-Value Used to evaluate the potential strength of subgrade soil, subbase, and base course material, including recycled materials for use in road and airfield pavements. Pavement Thickness Design Soluble Sulfate Used to determine the quantitative amount of soluble sulfates within a soil mass. Corrosion Potential Exhibit C-4 REPORT TERMINOLOGY (Based on ASTM D653) Allowable Soil Bearing Capacity The recommended maximum contact stress developed at the interface of the foundation element and the supporting material. Alluvium Soil, the constituents of which have been transported in suspension by flowing water and subsequently deposited by sedimentation. Aggregate Base Course A layer of specified material placed on a subgrade or subbase usually beneath slabs or pavements. Backfill A specified material placed and compacted in a confined area. Bedrock A natural aggregate of mineral grains connected by strong and permanent cohesive forces. Usually requires drilling, wedging, blasting or other methods of extraordinary force for excavation. Bench A horizontal surface in a sloped deposit. Caisson (Drilled Pier or Shaft) A concrete foundation element cast in a circular excavation which may have an enlarged base. Sometimes referred to as a cast-in-place pier or drilled shaft. Coefficient of Friction A constant proportionality factor relating normal stress and the corresponding shear stress at which sliding starts between the two surfaces. Colluvium Soil, the constituents of which have been deposited chiefly by gravity such as at the foot of a slope or cliff. Compaction The densification of a soil by means of mechanical manipulation Concrete Slab-on- Grade A concrete surface layer cast directly upon a base, subbase or subgrade, and typically used as a floor system. Differential Movement Unequal settlement or heave between, or within foundation elements of structure. Earth Pressure The pressure exerted by soil on any boundary such as a foundation wall. ESAL Equivalent Single Axle Load, a criteria used to convert traffic to a uniform standard, (18,000 pound axle loads). Engineered Fill Specified material placed and compacted to specified density and/or moisture conditions under observations of a representative of a geotechnical engineer. Equivalent Fluid A hypothetical fluid having a unit weight such that it will produce a pressure against a lateral support presumed to be equivalent to that produced by the actual soil. This simplified approach is valid only when deformation conditions are such that the pressure increases linearly with depth and the wall friction is neglected. Existing Fill (or Man-Made Fill) Materials deposited throughout the action of man prior to exploration of the site. Existing Grade The ground surface at the time of field exploration. Exhibit C-5 REPORT TERMINOLOGY (Based on ASTM D653) Expansive Potential The potential of a soil to expand (increase in volume) due to absorption of moisture. Finished Grade The final grade created as a part of the project. Footing A portion of the foundation of a structure that transmits loads directly to the soil. Foundation The lower part of a structure that transmits the loads to the soil or bedrock. Frost Depth The depth at which the ground becomes frozen during the winter season. Grade Beam A foundation element or wall, typically constructed of reinforced concrete, used to span between other foundation elements such as drilled piers. Groundwater Subsurface water found in the zone of saturation of soils or within fractures in bedrock. Heave Upward movement. Lithologic The characteristics which describe the composition and texture of soil and rock by observation. Native Grade The naturally occurring ground surface. Native Soil Naturally occurring on-site soil, sometimes referred to as natural soil. Optimum Moisture Content The water content at which a soil can be compacted to a maximum dry unit weight by a given compactive effort. Perched Water Groundwater, usually of limited area maintained above a normal water elevation by the presence of an intervening relatively impervious continuous stratum. Scarify To mechanically loosen soil or break down existing soil structure. Settlement Downward movement. Skin Friction (Side Shear) The frictional resistance developed between soil and an element of the structure such as a drilled pier. Soil (Earth) Sediments or other unconsolidated accumulations of solid particles produced by the physical and chemical disintegration of rocks, and which may or may not contain organic matter. Strain The change in length per unit of length in a given direction. Stress The force per unit area acting within a soil mass. Strip To remove from present location. Subbase A layer of specified material in a pavement system between the subgrade and base course. Subgrade The soil prepared and compacted to support a structure, slab or pavement system. Unconfined Compression To obtain the approximate compressive strength of soils that possess sufficient cohesion to permit testing in the unconfined state. Bearing Capacity Analysis for Foundations Water Content Used to determine the quantitative amount of water in a soil mass. Index Property Soil Behavior C Gravels with 5 to 12% fines require dual symbols: GW-GM well-graded gravel with silt, GW-GC well-graded gravel with clay, GP-GM poorly graded gravel with silt, GP-GC poorly graded gravel with clay. D Sands with 5 to 12% fines require dual symbols: SW-SM well-graded sand with silt, SW-SC well-graded sand with clay, SP-SM poorly graded sand with silt, SP-SC poorly graded sand with clay E Cu = D60/D10 Cc = 10 60 2 30 D x D (D ) F If soil contains  15% sand, add “with sand” to group name. G If fines classify as CL-ML, use dual symbol GC-GM, or SC-SM. H If fines are organic, add “with organic fines” to group name. I If soil contains  15% gravel, add “with gravel” to group name. J If Atterberg limits plot in shaded area, soil is a CL-ML, silty clay. K If soil contains 15 to 29% plus No. 200, add “with sand” or “with gravel,” whichever is predominant. L If soil contains  30% plus No. 200 predominantly sand, add “sandy” to group name. M If soil contains  30% plus No. 200, predominantly gravel, add “gravelly” to group name. N PI  4 and plots on or above “A” line. O PI  4 or plots below “A” line. P PI plots on or above “A” line. Q PI plots below “A” line. Modifier RELATIVE PROPORTIONS OF SAND AND GRAVEL GRAIN SIZE TERMINOLOGY Trace With Modifier DESCRIPTIVE SOIL CLASSIFICATION Boulders Cobbles Gravel Sand Silt or Clay Descriptive Term(s) of other constituents < 15 15 - 29 > 30 Term PLASTICITY DESCRIPTION Water levels indicated on the soil boring logs are the levels measured in the borehole at the times indicated. Groundwater level variations will occur over time. In low permeability soils, accurate determination of groundwater levels is not possible with short term water level observations. Water Level After a Specified Period of Time Water Level After a Specified Period of Time Water Initially Encountered Modified Dames & Moore Ring Sampler Standard Penetration Test Unless otherwise noted, Latitude and Longitude are approximately determined using a hand-held GPS device. The accuracy of such devices is variable. Surface elevation data annotated with +/- indicates that no actual topographical survey was conducted to confirm the surface elevation. Instead, the surface elevation was approximately determined from topographic maps of the area. STRENGTH TERMS RELATIVE DENSITY OF COARSE-GRAINED SOILS (More than 50% retained on No. 200 sieve.) Density determined by Standard Penetration Resistance CONSISTENCY OF FINE-GRAINED SOILS (50% or more passing the No. 200 sieve.) Consistency determined by laboratory shear strength testing, field visual-manual procedures or standard penetration resistance < 3 3 - 4 5 - 9 10 - 18 19 - 42 Ring Sampler Blows/Ft. > 42 0 - 1 2 - 4 4 - 8 8 - 15 15 - 30 > 30 Standard Penetration or N-Value Blows/Ft. Descriptive Term (Consistency) Very Soft Soft Medium-Stiff Stiff Very Stiff Hard Ring Sampler Blows/Ft. 0 - 6 7 - 18 59 - 98 19 - 58 > _99 Standard Penetration or N-Value Blows/Ft. 0 - 3 4 - 9 10 - 29 30 - 50 > 50 Descriptive Term (Density) Very Loose Loose Medium Dense Dense Very Dense ASTM D422 1901 Sharp Point Drive, Suite C Fort Collins, Colorado PROJECT NUMBER: 20135038 PROJECT: Aurthur Ditch Bridge Replacement SITE: Three intersections Fort Collins, Colorado CLIENT: J-U-B Engineers, Inc. Fort Collins, Colorado EXHIBIT: B-4 LABORATORY TESTS ARE NOT VALID IF SEPARATED FROM ORIGINAL REPORT. GRAIN SIZE: USCS-2 20135038.GPJ TERRACON2012.GDT 12/3/13 1-1 1-2 2-1 2-3 3-1 SANDY LEAN CLAY (CL) SILTY SAND(SM) SANDY LEAN CLAY(CL) SILTY, CLAYEY SAND(SC-SM) SANDY LEAN CLAY(CL) 35 43 41 25 38 0.09 0.197 0.129 0.126 9.5 12.5 9.5 4.75 12.5 1-1 1-2 2-1 2-3 3-1 9.0 9.0 9.0 4.0 9.0 GRAIN SIZE IN MILLIMETERS PERCENT FINER BY WEIGHT coarse fine 3/8 3 100 3 2 140 COBBLES GRAVEL SAND USCS Classification 26.3 53.7 36.8 85.5 37.7 D60 coarse medium 9.0 9.0 9.0 4.0 9.0 Boring ID Depth Boring ID Depth GRAIN SIZE DISTRIBUTION ASTM D422 1901 Sharp Point Drive, Suite C Fort Collins, Colorado PROJECT NUMBER: 20135038 PROJECT: Aurthur Ditch Bridge Replacement SITE: Three intersections Fort Collins, Colorado CLIENT: J-U-B Engineers, Inc. Fort Collins, Colorado EXHIBIT: B-3 LABORATORY TESTS ARE NOT VALID IF SEPARATED FROM ORIGINAL REPORT. GRAIN SIZE: USCS-2 20135038.GPJ TERRACON2012.GDT 12/3/13 18 16 18 9 21 5 20 18 73 45 61 15 55 62 LL USCS 1-1 1-2 2-1 2-3 3-1 3-2 ATTERBERG LIMITS RESULTS ASTM D4318 1901 Sharp Point Drive, Suite C Fort Collins, Colorado PROJECT NUMBER: 20135038 PROJECT: Aurthur Ditch Bridge Replacement SITE: Three intersections Fort Collins, Colorado CLIENT: J-U-B Engineers, Inc. Fort Collins, Colorado EXHIBIT: B-2 LABORATORY TESTS ARE NOT VALID IF SEPARATED FROM ORIGINAL REPORT. ATTERBERG LIMITS 20135038.GPJ TERRACON2012.GDT 12/3/13 CL-ML 61 F/A Landscaping FA 1 $ 3,500.00 $ 3,500.00 $ 3,500.00 IN WORDS: TOTAL BASE BID ARTHUR DITCH BRIDGE REPLACEMENT- CANYON AVENUE BID SCHEDULE ITEM NO. ITEM DESCRIPTION UNIT QUANTITY UNIT COST COST