HomeMy WebLinkAboutWORK ORDER - BID - 8046 ARTHUR DITCH BRIDGE REPLACEMENT - OAK & WHITCOMB INTERSECTION)
WORK ORDER
PURSUANT TO AN AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
CTL THOMPSON, INC
DATED: Thursday January 15, 2015
Work Order Number: OakWhit TAD 1.15
Purchase Order Number:
Project Title: Arthur Ditch Bridge Replacement —Oak and Whitcomb
Original Bid1RFP Project Number & Name: 7291 Geolechnlcai Testing Services
Commencement Date: January 2015
l 5-0 EYs/
Completion Date; July 1, 2015
Maximum Fee: (time and reimbursable direct costs): $7170.00
Project Description: Identified scove of geotechnical tests for Arthur Ditch replacement (01
Oak and Whitcomb Sheets.
Scope of Services: See Attached.
Professional agrees to perform the services
identified above and on the attached forms in
accordance with the terms and conditions
contained herein and in the Professional Services
Agreement between the parties. In the event of a
conflict between or ambiguity In the terms of the
Professional Services Agreement and this work
order (Including the attached fors) the
Professional Services Agreement shall control.
The attached forms consisting of 2 (LkDj pages
are hereby accepted and incorporated herein, by
this reference, and Notice to Proceed is hereby
given.
Professional
City of Fart Collins
By:
Project Mai germ
By:
Gerry Paul
Director of Purchasing and Risk Management
(over $60,000,00)
Data
T.iga?(+O.R R O l MyT AFO=.-i
January 27, 2015
City of Fort Collins
Engineering Department
281 N. College Avenue
P.O. Box 580
Fort Collins, Colorado 80522-0580
Attention: Mr. Tracy Dyer
Subject: Fee Estimate for Construction Observation
and Materials Testing Services
Arthur Ditch Bridge Replacement — Oak Street and Whitcomb Street
Fort Collins, Colorado
Fee Estimate No. PC 15-0028
At your request, CTLIThompson, Inc. is pleased to provide this revised fee estimate for Construction
Observation and Materials Testing services for the Arthur Ditch Bridge Replacement— Oak Street
and Whitcomb Street project located in Fort Collins, Colorado.
We understand that the city will use our estimate for the basis of establishing a budget for the
project and to issue a purchase order for our services. Our estimated scope of services and
associated fees were prepared according to the terms and conditions of our professional services
agreement with the City of Fort Collins and are presented below.
Earthwork: Compaction testing will be required for box culvert subgrade, box culvert backfill,
pavement subgrade, sidewalk subgrade, and aggregate base course. We estimate a total of 20 site
visits will be necessary.
Engineering Technician
20 days x 2 hrs/day x $60/hr
$2,400.00
Proctor
3 tests x $80/ea
$240.00
Atterberg Limits
3 tests x $60/ea
$180.00
Gradation
3 tests x $70/ea
210-00
Subtotal:
$3,030.00
Concrete Testino: Concrete testing will be required for the box culvert, sidewalk, and curb and
gutter. We estimate 20 concrete tests consisting of 4 cylinders each will be necessary.
Concrete Cylinders 20 tests x $160/test $3,200.00
Subtotal: $3,200.00
400 N. Link Lane I Fort Collins, Colorado 80524
Telephone: 970.206-9455 Fax: 970-206-9441
Ir
Asphalt Testing: Compaction testing will be required during asphalt placement. We estimate the
project will require 2 days of asphalt compaction testing and 2 laboratory samples.
Engineering Technician
2 days x 4 hm/day x $60/hr
$480.00
Lab Density (Rice)
2 tests x $80/ea
$160.00
AC Content/Gradation
2 tests x $150/ea
3� 00_00
Subtotal:
$940.00
TOTAL ESTIMATED FEE:
$7,170.00
It should be emphasized that this estimate is based upon assumptions of actual quantities and
contractor's schedule. The fee will be charged only for the actual hours and unit rates presented for
tests and observations requested by the owner, contractor or subcontractors who schedule the
services.
If we can be of further assistance, please contact us at your convenience.
Very truly yours,
CTL I THOMPSON, INC.
Heather Grubb
Field Department Manager
CITY OF FORT COLLINS
AMUR DRCH BRIDGE REPLACEMENT -OAK ST B WHITCOMB ST
CTL I T FEE ESTIMATE NO. M15-0028