ADDENDUM NO. 3
SPECIFICATIONS AND CONTRACT DOCUMENTS
Description of BID 7676: E Lincoln Ave & S Lemay Ave Improvements
OPENING DATE: 3:00 PM (Our Clock) August 19, 2014
To all prospective bidders under the specifications and contract documents described
above, the following changes/additions are hereby made and detailed in the following
sections of this addendum:
1. Revisions to the Bid Schedule
A. Increase in item 202 “Removal of Pavement Markings” from 0 SF to 2089
SF. This item is reflected correctly in plan set on page 4 and is now
corrected in Exhibit 1 – Revised Bid Schedule.
B. AutoCad (CAD) files are available upon request from Tracy Dyer, Project
Engineer. Please send an email request to tdyer@fcgov.com for an
electronic copy of these files.
2. Exhibit 1 – Revised Bid Schedule
Please note that the Revised Bid Schedule has also been uploaded as a
separate Microsoft Excel file.
Please contact John Stephen, CPPO, LEED AP, Senior Buyer at (970) 221-6777 with
any questions regarding this addendum.
RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED BY A WRITTEN
STATEMENT ENCLOSED WITH THE BID/QUOTE STATING THAT THIS
ADDENDUM HAS BEEN RECEIVED.
Financial Services
Purchasing Division
215 N. Mason St. 2nd Floor
PO Box 580
Fort Collins, CO 80522
970.221.6775
970.221.6707
fcgov.com/purchasing
Addendum 3 – 7676 E Lincoln Ave & S Lemay Ave Improvements Page 2 of 6
EXHIBIT 1 – REVISED BID SCHEDULE
1 201 Clearing and Grubbing 1 LS $ -
2 202 Removal of Tree 54 EA $ -
3 202 Removal of Median Tree 39 EA $ -
4 202 Removal of Tree Stump 5 EA $ -
5 202 Removal of Median Shrubs and Topsoil (stockpile, redistribute) 1,790 CY $ -
6 202 Removal of Concrete Irrigation Structures 1 LS $ -
7 202 Removal of Pipe 121 LF $ -
8 202 Removal of Traffic Barricade 2 EA $ -
9 202 Removal of Bollard 4 EA $ -
10 202 Removal of Pavement Markings 2,089 SF $ -
11 202 Removal of Sidewalk 72 SY $ -
12 202 Removal of Concrete Pan 160 LF $ -
13 202 Removal of Curb and Gutter 3,177 LF $ -
14 202 Removal of Concrete Curb Ramp 16 SY $ -
15 202 Removal of Median Cover/Splash Guard 1,063 SY $ -
16 202 Removal of Concrete Pavement 553 SY $ -
17 202 Removal of Asphalt Mat 5,664 SY $ -
18 203 Unclassified Excavation (CIP) 5,225 CY $ -
19 203 Embankment (CIP) 1,118 CY $ -
20 203 Haul and Dispose 2,800 CY $ -
21 203 Borrow (Class 5 or 6 ABC) (CIP) 1,381 CY $ -
22 203 Muck Excavation - (CIP) 1,307 CY $ -
23 203 Potholing 1 LS $ -
24 208 Erosion Control (SWMP, BMPs, Permits) 1 LS $ -
25 210 Reset Traffic Sign 21 EA $ -
26 210 Reset Riprap 6 CY $ -
27 210 Reset Fire Hydrant 1 EA $ -
QUANTITY UNIT UNIT COST TOTAL COST
BID
NO.
CONTRACT
ITEM NO.
CONTRACT ITEM
Addendum 3 – 7676 E Lincoln Ave & S Lemay Ave Improvements Page 3 of 6
28 210 Reset Water Blow Off 1 EA $ -
29 210 Reset Bus Stop Bench & Sign 1 EA $ -
30 210 Reset Mailbox 1 EA $ -
31 210 Adjust Manhole 5 EA $ -
32 210 Adjust Valve Box 2 EA $ -
33 304 Aggregate Base Course (Class 5 or 6) 5,917 TON $ -
34 306 Reconditioning (8 Inch) 10,414 SY $ -
35 403 Hot Mix Asphalt (Grading S) (75) (PG 64-22) 2,408 TON $ -
36 403 Hot Mix Asphalt (Grading S) (100) (PG 64-28) 1,269 TON $ -
37 403 Hot Mix Asphalt Patch (Gradins S) (74) (PG 64-22) 73 TON $ -
38 412 Concrete Pavement (8 Inch Driveway) 425 SY $ -
39 412 Concrete Pavement (11 Inch) 1,014 SY $ -
40 412 Enhanced Concrete Crosswalk 49 SY $ -
41 412 Median Nose 17 SY $ -
42 506 Riprap (Type L) 10 CY $ -
43 603 8 Inch PVC Sewer Pipe (CIP) 70 EA $ -
44 603 15 Inch RCP (CIP) 58 LF $ -
45 603 15 Inch HDPE Pipe (CIP) 168 LF $ -
46 603 15 Inch Concrete End Section 1 EA $ -
47 603 15 Inch HDPE End Section 1 EA $ -
48 603 18 Inch Reinforced Concrete Pipe (CIP) 32 LF $ -
49 603 24 Inch Reinforced Concrete Pipe (CIP) 264 LF $ -
50 603 24 Inch Reinforced Concrete End Section 1 EA $ -
51 604 Inlet Type R (5 Foot) 1 EA $ -
52 604 Inlet Type R (10 Foot) 2 EA $ -
53 604 Manhole Slab Base (4 Foot) 2 EA $ -
54 604 48 Inch Flat Top Storm Sewer Manhole 2 EA $ -
55 608 Temporary Asphalt Sidewalk (3" Depth) 299 TON $ -
Addendum 3 – 7676 E Lincoln Ave & S Lemay Ave Improvements Page 4 of 6
56 608 Concrete Sidewalk (6 Inch) 1,473 SY $ -
57 608 Concrete Curb Ramp w/ Truncated Dome (8 Inch) 143 SY $ -
58 609 Curb and Gutter Type 2 (Section I-B) 2,757 LF $ -
59 609 Curb and Gutter Type 2 (Section II-B) 2,239 LF $ -
60 610 Exposed Aggregate Median Splash Guard (4 Inch) 1,781 SF $ -
61 610 Exposed Aggregate Median Cover 1,590 SF $ -
62 619 8 Inch PVC Water Main (C-900) 50 LF $ -
63 619 8 Inch x 6 Inch Reducer 1 EA $ -
64 619 8 Inch x 24 Inch Tapping Saddle 1 EA $ -
65 619 8 Inch Gate Valve 1 EA $ -
66 619 Fire Hydrant Assembly 1 EA $ -
67 626 Mobilization 1 LS $ -
68 630 Type III Barricade 3 EA $ -
69 630 Construction Zone Traffic Control 1 LS $ -
70 207 Median Topsoil 1,790 CY $ -
71 207 Tree Lawn Topsoil 319 CY $ -
72 207 Lincoln Ave Parkway Topsoil 250 CY $ -
73 212 Dryland Seed 47,475 SF $ -
74 213 Landscape Boulders - 'A' Boulder 31 EA $ -
75 213 Landscape Boulders - 'B' Boulder 28 EA $ -
76 213 Landscape Boulders - 'C' Boulder 16 EA $ -
77 213 Landscape Weed Barrier Fabric (ALL Inorganic beds) 739 SY $ -
78 213 Steel Edger 1,560 LF $ -
79 213 Wood (Organic) Mulch 9,420 SF $ -
80 213 Inorganic Mulch 6,650 SF $ -
81 214 Ornamental Street Tree 2" 32 EA $ -
82 214 Deciduous Street Tree 2" 3 EA $ -
83 214 Shrubs 5 Gal 418 EA $ -
84 214 Perennials 1 Gal 536 EA $ -
Landscaping Items
Addendum 3 – 7676 E Lincoln Ave & S Lemay Ave Improvements Page 5 of 6
85 214 Ornamental Grasses 1 Gal 337 EA $ -
86 214 Landscape Maintenance (2 Year) (Medians Only) 1 LS $ -
87 623 Irrigation System-Medians 15,653 SF $ -
88 623 Sprinkler Irrigation, West ROW, served from Private Property 7,308 SF $ -
89 623 Drip Irrigation, West ROW, served from Private Property 1,400 SF $ -
90 623 Bubbler Irrigation Zones to New Trees, West ROW, north of Magnolia 2 EA $ -
91 623 Bubbler Irrigation Zones to New Trees, West ROW, south of Magnolia 6 EA $ -
92 623 Irrigation Concrol System- Medians and southwest tree bubbler zones 1 EA $ -
93 623 Back Flow Concrete Pad and Enclosure- Median 1 EA $ -
94 212 Turf Sod - West Parkway 7,330 SF $ -
95 213 Landscape Boulders - 'A' Boulder 10 EA $ -
96 213 Landscape Boulders - 'B' Boulder 7 EA $ -
97 213 Landscape Weed Barrier Fabric (ALL Inorganic beds) 138 SY $ -
98 213 Steel Edger 420 LF $ -
99 213 Wood (Organic) Mulch 1,500 SF $ -
100 213 Inorganic Mulch 1,250 SF $ -
101 214 Ornamental Street Tree 2" 11 EA $ -
102 214 Deciduous Street Tree 2" 10 EA $ -
103 214 Shrubs 5 Gal 60 EA $ -
104 214 Ornamental Grasses 1 Gal 70 EA $ -
105 210 Reset Cathode Protection Unit 3 EA $ -
106 210 Reset Street Light 7 EA $ -
107 210 Reset Water Meter 1 EA $ -
108 614 Magnolia Intersection Traffic Signal 1 LS $ -
109 614 Signing 7 EA $ -
110 619 Blow-off Fire Hydrant Assembly 1 EA $ -
111 - Bus Shelter 1 EA $ -
112 625 Construction Surveying 1 LS $ -
113 627 4 Inch Double Yellow Lane Line 340 LF $ -
Work To Be Performed By Others
Landscaping Items - Phase 2
Addendum 3 – 7676 E Lincoln Ave & S Lemay Ave Improvements Page 6 of 6
114 627 4 Inch Yellow with 4 Inch Dashed Yellow Line 2,900 LF $ -
115 627 4 Inch Dashed White Lane Line (10' long with 30' gap) 1,227 LF $ -
116 627 8 Inch Solid White Channelizing Line 4,388 LF $ -
117 627 4 Inch Solid White Line 1,521 LF $ -
118 627 4 Inch Dotted White Line 1,314 LF $ -
119 627 Crosswalk Bars 64 EA $ -
120 627 Pavement Marking 410 SF $ -
TOTAL BASE BID $ -
IN WORDS