HomeMy WebLinkAboutCHANGE ORDER - RFP - 7490 POUDRE RIVER DOWNTOWN PROJECT (4)COFC2014.05_LNG_Scope&Budget Letter_2014-06.docx June 17, 2014
375 East Horsetooth Road, Bldg. 5 y Fort Collins, Colorado y 80525
Phone: (970) 226-0120 y Fax: (970) 226-0121 y www.acewater.com
June 17, 2014
Mr. Will Welch
Wm.T.Welch Company, LLC
1315 Oakridge Drive, Suite 100
Fort Collins, CO 80525
RE: Poudre River Link-n-Greens Restoration Project – Additional Services
(ACE Project No. COFC2014.05)
Dear Will:
Attached to this letter is a work request compiled by BHA for additional services associated with the
Link-n-Greens River Restoration. In general, these additional services were precipitated by increased
effort during both the overlot grading process and construction observation due to field changes made
during construction. Specific services are defined in the attached letter from BHA, as well as the
associated scopes of work prepared by Interwest and ACE (also attached). The total amount of this
change order request is $20,590.
Based on their detailed understanding of the Link-n-Greens work, BHA has allocated costs for these
additional services as shown in the attached documentation. Based on BHA’s detailed cost breakout, it
appears the cost allocation between City departments for these additional services is as follows:
Park Planning $1,650 which equates to 8.0136%
Natural Areas $1,390 which equates to 6.7508%
Stormwater $17,550 which equates to 85.2356%
Please review this information to confirm that it meets the City’s understanding and expectations of the
additional services to be provided for the Link-n-Greens River Restoration. If you have any questions or
comments concerning any of this information, please do not hesitate to contact me.
Sincerely,
Anderson Consulting Engineers, Inc.
Gregory J. Koch, P.E.
Vice President
Attachment
BHA Design Incorporated
1603 Oakridge Drive
Fort Collins, CO 80525
Page 1 of 2 voice: 970.223.7577
fax: 970.223.1827
landscape architecture | planning | urban design www.bhadesign.com
Mr.GregKoch April22,2014
AndersonConsultingEngineers,Inc.
375EHorsetoothRoad
FortCollins,CO80525
RE:LinkͲnͲGreensRiverRestorationAreaProjectͲAdditionalServicesRequest#1
DearGreg,
Thefollowingisanoutlineoftheadditionalservicerequestwehavediscussedwithyoufor
theLinkͲnͲGreensRiverRestorationAreaProject.Therequestincludesadditionalfeesfor
bothAndersonConsultingEngineersandforInterwestConsultingGroupforadditional
effortsnotincludedintheoriginalscopeofservicefortheproject.
Theadditionaltasksrelatetoincreasedeffortduringtheoverlotgradingprocessand
constructionobservationduetofieldchangesmadeduringconstruction.Thesefield
changesrequiredadditionalmeetingsandcoordination,engineering,andhydraulicchecks
toverifythechangescontinuedtomeettheintentoftheCLOMR.Thefieldchanges
includedareasrelatedto:
Ͳ Thereduction/eliminationofthepotentialspilloverLemayAvenue,
Ͳ Gradingchangestoretainadditionalareasofexistingtrees
Ͳ ProposedadjustmentstothewestendoftheWoodwardsite
Ͳ AdjustmentstothealignmentofthePoudreRiverTrail
Ͳ Bridgeabutmentcoordinationduetomodifiedconstructionwidths
Ͳ Recorddrawingeffortsassociatedwiththechangesnotedabove
Thecontractadjustmentsareoutlinedbelow:
InterwestEngineers
TotalFeeforAdditionalServices=$2,900
OriginalContractAmount(LaborandExpenses)Ͳ$38,750
NewContractAmountͲ$41,650
AndersonConsultingEngineers
TotalFeeforAdditionalServices=$17,690
OriginalContractAmount(LaborandExpenses)Ͳ$65,500
NewContractAmountͲ$83,190
OverallContractAdjustments
TotalFeeforAdditionalServices=$20,590
BHA Design Incorporated
1603 Oakridge Drive
Fort Collins, CO 80525
Page 2 of 2 voice: 970.223.7577
fax: 970.223.1827
landscape architecture | planning | urban design www.bhadesign.com
OriginalContractAmount(LaborandExpenses)Ͳ$222,315
NewContractAmountͲ$242,905
I’vealsoannotatedthechangesbytaskontheattachedDesignFeespreadsheet.Please
feelfreetocallwithanyquestions.
Sincerely,
ForBHADesign,Inc.
For
AngelaK.Milewski date AuthorizedSignature date
DESIGN FEES revised 4/22/2014 for Additional Service Request #1
BHA Design
TeamLead,
Landscape
Architecture,Planning
Interwest
CivilEngineering
Anderson
Consulting
Engineers
BankStabilization
Biohabitats
Restoration
Consulting
Northern
Engineering
Surveying,Easements
Task
Total
Anticipated
Cost
Allocation
TASK1
BankStabilization
StructuralDesign
$17,740
$9,659
$27,399
Natural
Areas
TASK2
PoudreTrailDesign
$4,500
$11,500
$13,150
$16,000
$17,650
Parks
TASK3
TempTrailConnection
PoudreTrailtoLemay
$750
$600
$1,350
Parks
TASK4
CDOTROWGrading
DESIGN FEES revised 4/22/2014 for Additional Service Request #1
BHA Design
TeamLead,
Landscape
Architecture,Planning
Interwest
CivilEngineering
Anderson
Consulting
Engineers
BankStabilization
Biohabitats
Restoration
Consulting
Northern
Engineering
Surveying,Easements
Task
Total
TASK10
Construction
Specifications
$5,000
$5,000
Natural
Areas
TASK11
Meetingsand
Coordination
$8,000
$8,000
$8,640
$14,390
$3,019
$27,659
$33,409
Natural
Areas/
Stormwater
TASK12
Construction
Observation–Demo&
BankStabilization+
CLOMRaddendum
$5,500
$1,000
$1,500
EXHIBIT A
CHANGE ORDER NO. 1
for the
LINK-N-GREENS OPEN SPACE ENGINEERING SERVICES
The proposed Woodward Link-N-Greens campus site is generally bounded on the north and
south by Lincoln Avenue and Mulberry Street, respectively; and on the east and west by Lemay Avenue
and the UDALL Natural Area, respectively. In July 2013, ACE contracted with the City of Fort Collins to
assist the project team with post CLOMR related activities. The following is a summary of what has been
completed under the original Scope of Work and what work has already been conducted outside of the
original Scope of Work.
• Task 1 – Bank Stabilization Structural Design: Bank stabilization final design plans were prepared
and included in the overall design plan set. This task was completed largely according to the
original Scope of Work.
• Task 2 – Hydraulic Evaluation of Site Modifications: Site modifications proposed by City Staff
were hydraulically evaluated and a final plan was developed to be included in the overall design
plan set. This task was completed largely according to the original Scope of Work.
• Task 3 – Overtopping of Lemay Avenue: ACE conducted a hydraulic evaluation to see if there
were any flood related adverse impacts associated with extending the commercial pad south to
Mulberry Street in order to eliminate the overtopping potential of Lemay Avenue during large
storm events. However, the City Stormwater department has internally determined that this
approach would likely be construed by FEMA as a levee, which is an undesirable method of
addressing this issue. Consequently, the City has internally continued to pursue different
avenues toward addressing the overtopping potential of Lemay Avenue. This task was
completed largely according to the original Scope of Work.
• Documentation of Task 2 and 3: A CLOMR addendum was prepared to summarize efforts
associated with Tasks 2 and 3. This report was prepared, submitted to the City of Fort Collins
and approved. The preparation of this report was completed largely according to the Scope of
Work.
• Task 4 – Construction Services: This effort was largely set aside to assist the contractors from a
technical standpoint in the implementation of the bank stabilization and overlot/final grading.
At this time, assistance has only been provided for the overlot grading and the initial stages of
the bank stabilization. However, during the overlot grading process several issues developed
requiring significant engineering effort outside of the original Scope of Work. Included in these
efforts were the following: (a) several hydraulic checks to ensure that the overlot grading was
meeting the intent of the CLOMR prior to the turnover of the property from Woodward to the
City; and (b) several hydraulic checks to verify additional field changes (i.e. keeping various areas
higher relative to the plans, keeping additional areas of trees, and proposed changes to the
Woodward site plan) were meeting the intent of the CLOMR.
• Task 5 – Meetings and Coordination: The time originally established in Task 5 for meetings and
coordination has been depleted. In addition, due to the complexity of the project additional
meetings and coordination have been required, which were not identified in the original Scope
of Work. These meetings and coordination efforts were largely the result of field changes made
during the overlot grading process (See the description provided above for Task 4). In addition,
several meetings were attended to support the City of Fort Collins on the issue of
reducing/eliminating the potential spill over Lemay Avenue.
• Task 6 – Design Team Project Management: This task is ongoing and is largely being completed
according to the original Scope of Work.
Though the efforts associated with Task 4, 5, and 6 in the original Scope of Work have not been
completed; the additional work effort associated with Tasks 4 and 5 have largely exhausted the original
budget. Consequently, this proposed Change Order for Engineering Services associated with the Link-N-
Greens Open Space is respectfully being submitted to not only cover the remaining efforts associated
with Tasks 4, 5 and 6 but to cover additional efforts that have been requested but have not yet been
completed. Detailed tasks outlining these efforts are provided below.
Task 1 – Construction Services (Previously Task 4)
With the overlot grading completed and the open space being transferred to the City of Fort
Collins, efforts are underway to install bank stabilization measures and perform final grading. The intent
of this task is to provide technical and field observation assistance to the contractor doing both the bank
stabilization and final grading. With respect to the bank stabilization, ACE staff will provide guidance in
the field for placement of the proposed revetment as it is anticipated that much of this work will follow
the “design-build” technique. For the final grading, ACE staff will provide guidance in meeting the
finished grade elevations assumed in the CLOMR. It is noted that the City of Fort Collins has requested
additional time be accounted for in this task due to the following: (a) higher than average flow in the
river; (b) higher than normal groundwater levels for this time of year; (c) to help address potential field
changes as they relate to the CLOMR; and (d) the overall sensitivity of finished grades to the final LOMR.
To this end, six (6) hours a week through April 15 (approximately 8 weeks) and two (2) hours per week
through the completion of the final grading (approximately 12 weeks) have been included for
construction services.
Task 2 – CLOMR Addendum No. 2
Since the completion of the first CLOMR addendum, prepared as part of the previous Scope of
Work, several field changes have either taken place or have been proposed including the following: (a)
modifications to significantly reduce or eliminate the overtopping of Lemay Avenue for storm events up
to the 100-year; (b) minor deviations from the proposed grading plan as a result of the overlot grading;
(c) keeping many of the trees adjacent to the river, which requires keeping the ground higher than
planned; and (d) modifications to the grading in support Woodward site plan revisions.
A CLOMR addendum, similar in nature to what was prepared in September 2013 for this project,
will be completed to document these changes. This addendum will provide assurances to the City that
all the proposed modifications to the plan identified in the CLOMR can be implemented in accordance
with all City and FEMA floodplain rules and regulations.
Task 3: Meetings and Coordination (BHA Task 11 - Meetings and Coordination)
Coordination between the City of Fort Collins, BHA, Interwest and ACE Staff has been, and will
continue to be a key component throughout the duration of this project. Consequently, this task
assumes the following: (a) weekly coordination meetings with both the City of Fort Collins and
Woodward; (b) weekly coordination meetings with the City of Fort Collins Natural Areas; and (c) up to
six additional coordination meetings with vested parties relevant to the project.
Task 4: Design Team Project Management (BHA Task 14 - Design Team Project Management)
ACE will support BHA by coordinating contracting efforts with the City’s Project Manager for the
Poudre River Downtown Project. This will include preparing, coordinating and issuing subcontracts and
task orders; and providing invoicing services.
BUDGET
for the
LINK-N-GREENS OPEN SPACE ENGINEERING SERVICES
PROJECT: LNG Open Space Engineering Services Anderson Consulting Engineers, Inc.
CLIENT: City of Fort Collins Direct Labor ODC's Totals
Project Project Senior
ACE PROPOSAL NO.: COFC2013.02 Principal Manager Engineer II GIS/CADD Admin. Other
PREPARED BY: AMH Engineer Technician Direct
DATE: 3/26/2014 $160/hr $115/hr $96/hr $80/hr $65/hr Costs
160 115 96 80 65
Task/Description Hours Hours Hours Hours Hours Cost Hours Cost
1. Construction Services (Previously Task 4) 72 72 $8,280
2. CLOMR Addendum No. 2 24 4 28 $3,020
3. Meetings and Coordination (BHA Task 11) 50 50 $5,750
4. Design Team Project Management (BHA Task 14) 4 4$640
TOTAL PROJECT HOURS 4146004 154
TOTAL PROJECT BUDGET $640 $16,790 $0 $0 $260 $0 $17,690
EXHIBIT B
April 14, 2014
Ms. Angie Milewski
BHA Design
1603 Oakridge Drive
Fort Collins CO 80525
RE: Woodward Blue Home Natural Area Improvements
Change Order #1 Request
Dear Angie,
Attached is the project scope and fee estimate for the additional services associated with the Natural Area
project south of Woodward.
Description
Interwest Consulting Group (Interwest) will provide civil engineering services for the design of Natural Area
features within Lot 4 of the Woodward Technology Center.
The services to be provided as part of this change order will generally include:
• Design modifications to the Poudre River Trail plans based on field alignment changes
• Grading Plan changes based on field adjustments to various pockets of trees and existing conditions
• Bridge Abutment coordination regarding the modified construction widths
• Record Drawing efforts associated with the changes noted above
Scope of Services
I. Poudre River Trail Design Modifications – Interwest will coordinate with the contractor and the
owner’s representative in regard to field modifications to the trail alignment. This task includes design
exhibits for the contractor for trail realignment.
Fee: $1,150
II. Grading Plan Changes – Interwest will revise the trail and bridge grading based on the field
modifications noted above.
Fee: $750
III. Bridge Abutment Coordination – Interwest will perform an additional site visit and coordinate with
the owner’s representative relative to the as-constructed bridge abutments that did not follow the
design specifications. This task includes a verification of the storm flow capacity with the resulting
narrowed bridge opening.
Fee: $500
IV. Record Drawings – Interwest anticipates the need for expanded record drawing services to reflect the
trail and bridge changes noted above. These changes will be based on contractor provided drawings
and/or field surveys to documents the as-constructed conditions.
Fee: $500
Please call me at 970-460-8487 if you have any questions or need any additional information.
Sincerely,
Robert Almirall, PE
Senior Project Manager
Thanks'Bob.''I'spoke'with'Will'about'this'project'again'this'morning'and'he'is'still'working'through'the'City'paperwork,'etc.''I
apologize'for'the'delay'in'getting'you'folks'paid;'I'assure'you'it'will'be'soon.
'
Greg
'
Gregory'J.'Koch,'P.E.
Vice'President
ANDERSON(CONSULTING(ENGINEERS,(INC.
www.acewater.com
Greg.Koch@acewater.com
(970)'226O0120''x207
'
From:'Bob'Almirall'[mailto:balmirall@interwestgrp.com]'
Sent:'Tuesday,'September'23,'2014'4:36'PM
To:'Greg'Koch
Cc:''William'Welch';''ahansen@acewater.com';'Renee'Haynes
Subject:'Woodward'Natural'Areas'invoice
'
Hi,'Greg.''This'is'an'Interwest'invoice'for'the'Woodward'Natural'Area'site;'however,'the'only'time'listed'is'for'Blake'Larsen'to
inspect'the'pedestrian'bridge'crossing'and'make'remediation'recommendations.''This'is'just'a'pass'through'with'no'markup.
'
Let'me'know'if'you'have'any'questions.''Thanks.
'
Bob
Greg Koch <Greg.Koch@acewater.com>
To: Bob Almirall <balmirall@interwestgrp.com>
Cc: 'William Welch' <wwelch@wmtwelch.com>, Renee Haynes <rhaynes@interwestgrp.com>, Aaron Hansen
<Aaron.Hansen@acewater.com>
RE: Woodward Natural Areas invoice
September 23, 2014 6:09 PM
Hi#Bob,
#
Thank#you#for#the#invoice.##I#need#to#check#in#with#Will#to#see#if#the#PO#has#been#processed#yet.##I#believe#there#was#a#delay#as
the#damage/repair#issue#was#being#worked#out.##If#I#understand#correctly,#it#seems#that#is#now#behind#us.##I’ll#see#if#I#can#get
everything#processed#quickly#in#order#to#catch#up.
#
Thanks#for#your#patience,
#
Greg
#
Gregory#J.#Koch,#P.E.
Vice#President
ANDERSON(CONSULTING(ENGINEERS,(INC.
www.acewater.com
Greg.Koch@acewater.com
(970)#226Q0120##x207
#
From:#Bob#Almirall#[mailto:balmirall@interwestgrp.com]#
Sent:#Wednesday,#September#3,#2014#10:03#AM
To:#Greg#Koch
Cc:#'Welch#William'#;#Aaron#Hansen;#Renee#Haynes
Subject:#Woodward#Natrual#Area#Project#Invoice
#
Hi,#Greg.##Attached#is#an#invoice#for#the#Natural#Area#project#south#of#Woodward.##There#is#no#time#for#Interwest#but#this
includes#the#invoice#from#Northern#Engineering#to#do#the#site#survey#the#team#requested#and#Will#confirmed#was#billable.##I
would#like#to#get#them#paid#as#soon#as#we#can.
#
There#are#also#several#old#invoices#noted#that#have#not#yet#been#paid#if#you#could#please#look#into#those#I’d#appreciate#it.
#
Thanks.
#
Bob
#
#
Greg Koch <Greg.Koch@acewater.com>
To: Bob Almirall <balmirall@interwestgrp.com>
Cc: "'Welch William' " <wwelch@wmtwelch.com>, Aaron Hansen <Aaron.Hansen@acewater.com>, Renee Haynes
<rhaynes@interwestgrp.com>
RE: Woodward Natrual Area Project Invoice
September 3, 2014 4:31 PM
Hi#Will,
#
This#was#addressed#to#Matt#Day,#so#I#quick#changed#it#to#your#name.##If#I#missed#something#or#there#is#anything#I#need#to#fix#or
adjust,#I’d#be#happy#to#do#so#when#I#get#back.
#
Thanks#for#looking#this#over#and#nice#chatting#with#you#today,#it#had#been#a#while!
#
Greg
#
Gregory#J.#Koch,#P.E.
Vice#President
ANDERSON(CONSULTING(ENGINEERS,(INC.
www.acewater.com
gjkoch@acewater.com
(970)#226S0120##x207
#
COFC2014.….pdf (563 KB)
Greg Koch <Greg.Koch@acewater.com>
To: 'William Welch' <wwelch@wmtwelch.com>
Link-n-Greens change order
June 17, 2014 4:56 PM
1 Attachment, 563 KB
$15,720
$27,020
$22,220
$34,020
Natural
Areas/
Woodward/
Stormwater
TASK13
Construction
Observation–Trailand
Planting
$8,500
$1,000
$7,439
$16,939
Natural
Areas
TASK14
DesignTeamProject
Management
$30,000
$6,600
$7,240
$36,600
$37,240
Natural
Areas
FIRM TOTALS $82,250
$38,750
$41,650
$65,500
$83,190 $32,815 $3,000
$222,315
$242,905
TOTAL DESIGN FEES
$222,315
$242,905
IncludesExpenses
$750
$6,500
$7,250
Stormwater
TASK5
StormDrainageOutfall
Designs
$1,500
$11,250
$1,800
$14,550
Nat.Areas/
Stormwater/
Woodward
TASK6
WaterlineandHydrant
Design
$1,000
$600
$1,600
Natural
Areas
TASK7
GradingPlans
$5,250
$3,500
$4,250
$10,300
$5,579
$24,629
$25,379
Natural
Areas
TASK8
FinalPlantingPlans
$8,000
$7,119
$15,119
Natural
Areas
TASK9
CoordinateCity
EntitlementReviews
$6,000
$6,000
Natural
Areas