HomeMy WebLinkAboutCHANGE ORDER - RFP - 7577 DESIGN FOR GARDENS ON SPRING CREEKSECTION 00950
CHANGE ORDER NO.
PROJECT TITLE: Design for the Gardens on Spring Creek
CONTRACTOR: Russell+Mills Studios
PROJECT NUMBER: 46615
DESCRIPTION:
1. Reason for change: Additional services for maior amendment process
2. Description of Change: Need for 3 submittals and additional work by the acoustical engineer
3. Change in Contract Cost: $31,000
4. Change in Contract Time: 30 days
ORIGINAL CONTRACT COST
TOTAL APPROVED CHANGE ORDER
TOTAL PENDING CHANGE ORDER
TOTAL THIS CHANGE ORDER
TOTAL % OF THIS CHANGE ORDER
TOTAL C.O.% OF ORIGINAL CONTRACT
ADJUSTED CONTRACT COST
ACCEPTED BY:
REVIEWED BY:
Manager
APPROVED BY:
Title:
$ 151,660.00
31,000.00
182,660.00
31,000.00
100%
20%
$ 182,660.00
DATE:
DATE:
DATE:
APPROVED BY: DATE:
Director of Purchasing & Risk Management
(over$60,000)
cc: City Clerk Contractor Engineer
Project File Architect Purchasing