HomeMy WebLinkAboutWORK ORDER - BID - 7391 MISCELLANEOUS CONCRETE ANNUAL (38)WORK ORDER
PURSUANT TO AN AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
VOGEL CONCRETE, INC.
DATED: 10/21 /2014
Work Order Number. 1-VOG-902070-2014FAIRWAY
Purchase Order Number:
Project Title: Fairway Sidewalk Installation and Ramo Uoorade
Original Bid/RFP Project Number & Name: 7391 (Annual Concrete Maintenance Contract)
Commencement Date: 0 1
Completion Date: 04/15/2014
Maximum Fee: (time and reimbursable direct costs): $39,658.62
Project Description:
Vogel Concrete INC will install of 560' of 6' sidewalk from College Avenue to Fossil Blvd along Fairway
Lane, as well as upgrade 5 ramps, curb, gutter and aprons to current ADA standards at the intersection
of Fossil Blvd and Fairway Lane. Vogel Concrete Inc services are provided through an existing federally
procured contract with the City and they have the ability to complete construction in time efficient
manner.
Scope of Services:
Professional agrees to perform the services
identified above and on the attached forms in
accordance with the terms and conditions
contained herein and in the Professional Services
Agreement between the parties. In the event of a
conflict between or ambiguity in the terms of the
Professional Services Agreement and this work
order (including the attached forms) the
Professional Services Agreement shall control.
The attached forms consisting of one (, page are
hereby accepted and incorporated herein, by this
reference, and Notice to Proceed is hereby given.
D¢tej 10/21/2014
City of Fort
Date: 10/21 /2014
By:
Gerry Paul
Director of Purchasing and Risk Management
(over$60,000.00)
Date: