HomeMy WebLinkAboutCHANGE ORDER - RFP - 7455 FORT COLLINS SENIOR CENTER EXPANSION (6)CHANGE ORDER NO. 06
PROJECT TITLE: Fort Collins Senior Center Expansion
CONTRACTOR: The Neenan Company
PROJECT NUMBER: 7455
DESCRIPTION: Building Expansion for Additional Services
In preparing change orders show in order as separate numbered paragraphs the following:
1. Reason for change: There were additional scope items added during the finishes of the project.
2. Description of change:Modified building finishes, landscaping changes, etc.
3. Change in contract cost: $ 45,368.12
Fortyive Thousand EightHundred even an oars
4. Change in contract time: Add one day to the project completion giving a new date for substantial
completion or building o June ,
(Attach additional sheets as required)
ORIGINAL CONTRACT COST $4,383,702.00
TOTAL APPROVED CHANGE ORDERS $1,371,895.54
TOTAL PENDING CHANGE ORDERS $0.00
TOTAL THIS CHANGE ORDER $45,368.12
TOTAL % OF THIS CHANGE ORDER 1.03%
Total C.O. % of Original Contract 32.33%
ADJUSTED CONTRACT COST $5,800,965.66
ACCEPTED BY:
ACCEPTED BY: A, —)—
Project Manager
REVIEWED BY:
r_�77:T.1�l�7
APPROVED BYO
Print Name
cc: City Clerk
Contractor
Engineer
Bob Adams - Recreation Director
Ken Mannon - Operation Servlees 01metor
If over $60,000 - Purchasing Director
Project File
Purchasing
Dale
/o iy Av
Date
C � �
Date
A /� /
Date
Date
archistructione
The Neenan Company LLLP
2607 Midpoint Drive,
Fort Collins, CO 80525
Tel: 970 493-8747 Fax: 970 493-5869
OWNER CHANGE ORDER
Project #: 2761A Change Order #: OCO-006
Project Name: Fort Collins Senior Center Contract: 2761A
Project Address: 1200 Raintree Drive Change Order Date: 10/10/2014
Fort Collins, CO 80526
Owner: City Of Fort Collins Title: FCSC Scope Changes and Owner
Address: P.O. Box 580 Credits
Fort Collins CO 80522
Attn: Brian Hergott
Tel: (970) 221-6804
Fax:
NEENAN and Owner previously entered into an Agreement for the above referenced project. NEENAN and Owner desire to issue a change order
for the Agreement as described below. As modified hereby, the Agreement remains in full force and effect and NEENAN and Owner ratify and
affirm the Agreement in all respects.
Description: 1. Furnish and Install Multipurpose Room tile and base previously removed from TNC scope
2. Electrical Adds/Changes
3. Revise Detention Pond B due to water level
4. Soils T&M 6/10, 6111, 6/5
5. Core Drilling Requested by B Hergott for data
6. Furnish and install additional snowmelt sensor
7. LEED Review Fee paid by TNC at request of Brian Hergott
6. Furnish and install 9 comfort height seats
9. Replace existing hone strobes 1 fort with syncronizable devices. This work does not include adding
any new device locations.
10. Install Owner -Provided grab bars in renovated restrooms at Owner's request
11. Credit for Owner Supplied Pavers
12. ESI card access and additional licenses (restock fee excluded)
13. Over -ex, import fill 5/19 & 5120
14. DELETED FROM CO - Add 1-Year Landscape Maintenance contract for Ramirez Landscaping
15. Repair Existing Inlet structure adjacent to Cardio (Core opening)
16. Upgrade Carpet Adhesive for High Moisture Content
17. DELETED FROM CO - Power to screens and projectors in Multipurpose
18. Return unspent window blinds allowance
19.1plywood in storage rooms 108,127,148
20.Remove and Replace sidewalks at request of City Engineering
21.Reconcile weather conditions Allowance
22. Credit to Owner for eliminating Asphalt paving Warranty
22.Deduct for Air Barrier Retest
23. 215 Sidewalk replacement
24. Increase Landscape Allowance
25. Credit for deleted comer guards
26. Deduct for electrical work at shed location
27. Credit to Owner for eliminating asphalt paving warranty
Change Item
Change Item Description
Amount
OCI-077
Plywood in storage rooms 108,127,148
$2.911.06
OCI.078
Return unspent window blinds allowance
-$1,134.12
OCI,D82
Upgrade Carpel Adhesive for High Moisture Content
$3,367.91
OCI.085
Repair Existing Inlet structure adjacent to Cardio (Core opening)
$4,187.97
OC1 086
Over -ex, Import IN 5119 & 5120
$6,854.60
OCI.087
ESI card access deduct for compuler, RTEs, and door contacts (restock fee excluded)
42,472.07
The Neenan Company LLLP
ILI 1 I 2607 Midpoint Drive,
Fort Collins, CO 80525
archistructione Tel: 970 493-8747 Fax: 970 493-5869
OWNER CHANGE ORDER
Project #: 2761 A Change Order #: OCO.006
Project Name: Fort Collins Senior Center Contract: 2761A
Project Address: 1200 Raintree Drive Change Order Dale: 10/10/2014
Fort Collins, CO 80526
Change Item
Change Item Description
Amount
OCI-088
Credit for Owner Supplied Pavers
•$2,529.55
OCI,090
Furnish and Install Multipurpose Room file and base
$1,277.71
OCI.091
Added outlet In Multipurpose Hallway for TV
$295.03
OCI 092
Revise Detentlon Pond B due to water level
$2,642.25
OCI.093
Soils T&M
$4,733.08
OCI.094
Core Drilling Requested by B Hergon for data
$599.27
OCI.095
Furnish and install additional snowmelt sensor
$172.88
OC1,096
LEED Review Fee
$2,000.00
OCI.097
Furnish and Install 9 comfort height seats
$999.94
OCI.098
Replace existing hone strobes 1 fort with syncronizabfe devices. This work does not include
$6.827.05
adding any new device locations.
OCI-099
Install Owner,Provided grab bars in renovated restrooms at Owner's request
$472.97
OCI-100
Remove and Replace Sidewalks Required by City Engineering
$2,53T68
OCI.101
Increase Weather Condillons Allowance
$15,423.50
OCI-102
Alr Barrier Diagnostic and Restest
-$8,704.00
OCI.103
215 Sidewalk repair reibursement
-$2,744.00
OCI.104
Landscape Adds and Deducts
$9,659.94
OCI.105
Deduct for Corner Guards
-$527,96
OCI.106
Deduct for electrical termination, outlet and lights at shed.
-$1,044.02
OCI-107
Credit for Asphalt Warranty.
-$439.00
Total: $45,368.12
The Neenan Company LLLP
2607 Midpoint Drive,
Fort Collins, CO 80525
archistruction® Tel: 970 493-8747 Fax: 970 493-5869
OWNER CHANGE ORDER
Project #: 2761 A Change Order #: OCO-006
Project Name: Fort Collins Senior Center Contract: 2761A
Project Address: 1200 Raintree Drive Change Order Date: 10/10/2014
Fort Collins, CO 80526
The Original Contract Price was.....................................................................................................I........
S4,383,7e200
Net Change by Previously Authorized Requests and Changes.....................................................................
$1,371,895.54
The Conlract Price Prior to This Change Order was ..................................................
. ........ I......................
$5,755,597.54
The Contract Price will be Increased 9y................................................................................................
$45,368.12
The New Contract Price Including This Change Order will be.......................................................................
$5,800,965.66
The Contract Time Will Be Changed 6y............................................................................I...............
1 day
The Scheduled Substantial Completion Date as of this Change Order therefore Is
...........................................
ACCEPTED:
The Neenan Company LLLP
By: Neenan Management Company
Its: General Partner
City Of Fort Collins
Signed:
By: David Shigekene
By:
Its: President
Date:
Date: