PRE-BID MEETING NOTES
Thursday, July 10, 2014
Project Location
Scope of Work
The Work includes the following:
erosion control and permitting
traffic control including road closure
and detours
excavation, grading and
embankment
installation of CBC underpass w/
head & wing walls
2 steel pedestrian bridges and
abutments
tunnel lighting system
storm sewer culvert pipe
colored concrete trail paving
water mainline relocation work
asphalt removal and paving
guardrail installation
utility relocation/coordination
fence installation
seeding and restoration
2
Access, Staging & Traffic Control
North Side of Trilby
Easement area with
fence delineation
South side of Trilby
Stay within limits of
disturbance area
Access, Staging & Traffic Control – 38E
North shoulder area
Easement area
delineated by existing
fencing
Other Areas Possible
Maintain Limits of
Disturbance
3
Access, Staging & Traffic Control
Access, Staging & Traffic Control
Full Closure of Trilby Road (as shown in plans) will be
allowed for 15 consecutive days - Refer to section 01010 for details.
Detour route is schematic for bidding purposes only
Traffic Control for the project will be paid for Lump
Sum and will include all costs for all traffic control
associated with the project for the full duration of the
project.
4
FCLWD
Waterline
Relocation
- by Contractor
PSCO Gas Line
Completed by Utility
CoFC Elec. Line
Completed by Utility
Cable/Phone
Completed by Utility
Utility Coordination & Relocation
Road Closure for Trilby Road
Full Closure of Trilby Road will be allowed for 15
consecutive days
– Refer to section 01010 for details
Closure dates subject to approval by the City
All Traffic Control Plans and approvals per City
requirements
$2,500/Day Lane Rental Fee accessed
5
Colorado Stormwater Discharge Permit – Permit by City and reassigned to
Contractor at Notice to Proceed.
Erosion Control for the project will be paid for Lump Sum. It will include any and
all costs for erosion control, maintenance, adjustments and compliance associated
with the project for the full duration of the project.
The following permits are required, but may not be all inclusive:
R.O.W. Use Permit (from City of Fort Collins) – Acquired by the OWNER
Colorado Stormwater Discharge Permit – Acquired by the CONTRACTOR,
City of Fort Collins Flood Plain Use Permit – Acquired by the OWNER
C.O.E. Nationwide Permit – Acquired by the OWNER
Contractor is responsible for all permits required for this Work and
the expected times required to obtain permits.
PERMITS
KEY ITEMS
C.S.D.Permit and Erosion Control
Road Closure – Construction, Traffic
Control & info to public
Underpass and Wing Wall installation
Utility relocation and working near utilities
Timing of paving
Pedestrian Bridges
Grade tolerances / F.E.M.A. floodplain
Minimizing disturbance in Natural Area
6
QUESTIONS?
SITE WALK – starting point