HomeMy WebLinkAboutCORRESPONDENCE - RFP - 7507 APP SENIOR CENTER EXPANSIONCHANGE ORDER NO. 01
PROJECT TITLE:
Fort Collins Senior Center Expansion
CONTRACTOR:
BW Systems
PROJECT NUMBER:
WO # 424311
DESCRIPTION:
Add Security Camera
In preparing change orders show in order as separate numbered paragraphs the following:
Reason for change: Adding camera to the scope
2. Description of change:Adding a Security camers at the Pool Chemical Storage Door
3. Change in contract
4. Change in contract time: No Change
(Attach additional sheets as required)
$ 2.109.06
ORIGINAL CONTRACT COST
$51,928.96
TOTAL APPROVED CHANGE ORDERS
$0.00
TOTAL PENDING CHANGE ORDERS
$o.00
TOTAL THIS CHANGE ORDER
$2,109.06
TOTAL % OF THIS CHANGE ORDER 4•06%
Total C.O. % of Original Contract 4.06%
ADJUSTED CONTRACT COST
$54.038.02
(Assuming all change orders approved)
ACCEPTED BY
Project Manager Brian Hergott
REVIEWED BY:
Print Name
APPROVED BY:
Print Name
APPROVED BY. -
Print Name
If over $60,000 - Purchasing Director
cc: City Clerk Project File
Contractor Purchasing
Engineer
August 8, 2014
Date
/'-