HomeMy WebLinkAboutCHANGE ORDER - BID - 7643 DISPLAY & EXHIBIT CASES FOR MUSEUM OF DISCOVERYCHANGE ORDER NO.
PROJECT TITLE: Display & Exhibit Cases for FCMoD
CONTRACTOR: Exhibit Design Associates
PROJECT NUMBER: 7643
DESCRIPTION: Changes to scope of work
fF..
J
Supplier #
OV# getch#
1. Reason for change: Design changes to original SOW
2. Description of Change: Addition of 5 cases, deletion of 2 cases
3. Change in Contract Cost: $2,263.27
4. Change in Contract Time: none
ORIGINAL CONTRACT COST $_$27,914.90_
TOTAL APPROVED CHANGE ORDER
TOTAL PENDING CHANGE ORDER
TOTAL THIS CHANGE ORDER $2,263.27_
TOTAL % OF THIS CHANGE ORDER
TOTAL C.O.% OF ORIGNINAL CONTRACT
ADJUSTED CONTRACT COST $30,178.17
(Assuming all change orders appro e
ACCEPTED BY: William Baird -
DATE: 7/28/14
Contractor's Representative
ACCEPTED f
BY: DATE:
Project Manage
REVIEWED
BY: DATE:
Title:
APPROVED
BY: DATF
Title:
APPROVED
BY: DATE:
Purchasing Agent over $60,000
Contractor
Project File
Architect
Engineer
Purchasing